Title: AARRRF FRA Cooperative Agreement CA Project Status Updates
1AAR/RRF - FRA Cooperative Agreement (CA) Project
Status Updates
2AAR-FRA Cooperative Agreement
- Universal Onboard Platform (UPO) Project
- Obtained and reviewed clarifications to proposals
received. - Have begun negotiation of contract terms and
conditions with one vendor. - Negotiate extension of proposal validity with one
vendor due to funding availability timeline.
3RRF-FRA Cooperative Agreement
- Messaging Standards
- ARINC continues to facilitate telecons for the
ERAD working group of the Railway Electronics
Standards Committee. Efforts are focused on
interoperability lab set up, test of an ERAD
application over a foreign network, and planning
for connectivity to the UNL test bed site through
BNSF's interoperability lab. - Produced a draft a White Paper on Interoperable
Messaging - Industry CBTC Test Bed at TTC
- Continued development of design documentation for
train simulator, dispatch simulator, and test
environment controller - Employee in Charge Portable Remote Terminal (EIC
PRT) - Held October 19 design demonstration at the AAR
Offices - Attended by FRA, AAR, and member railroads
- All work stopped for 9 weeks pending FRA approval
of administrative change in budget allocations
4RRF-FRA Cooperative Agreement
- 220 MHz RCL Test Bed Development
- TTCI continues to develop test requirements, test
plans and test procedures to complete the CAI
specification - Discussion and Decision Needed
- Should TTCI proceed, at this time, with the
development of a facility to test compliance of
radios to the CAI specification? - Higher Performance Data Radio
- Held QA meeting with prospective RFI respondents
and granted a two week extension of the RFI
response period. - RFI responses received from 5 suppliers.
5WiNG
Wireless Next Gen
RESC Dec 13, 2006
6HPDR Timeline
Dec 12--Review of five respondents to RFI
Dec 19--Distribute materials from Dec 12 meeting
Jan 2--Send letters to respondents
Jan 10--Cutoff for more Clarification Cycle
questions
Jan 11--WiNG Conference Call
Jan 17--Clarification questions to respondents
Feb 16--Deadline for responses to Clarification
Cycle
Feb 22--WiNG Conference Call
Mar 6--Face-to-face meeting with surviving
contenders
TBD--Final determination of vendor(s) to go
forward
TBD--Bench POC tests
TBD--Field Trials
7(No Transcript)