A Joint Code of Practice - PowerPoint PPT Presentation

1 / 18
About This Presentation
Title:

A Joint Code of Practice

Description:

Contents. 1 Objective of the Code. 2 Compliance with the Code. 3 Introduction ... Code is pre-requisite for obtaining Insurance on all projects where the value of ... – PowerPoint PPT presentation

Number of Views:23
Avg rating:3.0/5.0
Slides: 19
Provided by: lbor
Category:

less

Transcript and Presenter's Notes

Title: A Joint Code of Practice


1
  • A Joint Code of Practice
  • for the Procurement, Design and Construction of
    Tunnels and Associated Underground Structures
  • in the United Kingdom
  • Objectives and Summary Presentation

2
Key Insurer Objectives
  • Have in place risk assessment and management
    procedures for the tunnelling sector
    to
  • Reduce the probability of a loss happening
  • Reduce the size of a claim when it happens
  • Provide Insurers with a better framework for
    understanding risks during the underwriting
    process
  • Provide increased certainty on financial exposure

3
Key Insurer Objectives
  • Create an auditable trail for Insurers to
    ensure compliance
  • Acknowledge that the Joint Code will not prevent
    claims happening

4
JCoP for Tunnelling Contents
1 Objective of the Code 2 Compliance with the
Code 3 Introduction 4 Definitions and Terms
used in the Code 5 Risk Assessment and
Management 6 Client Role and Responsibilities
7 Project Development Stage 8 Construction
Contract Procurement Stage 9 Design 10
Construction Stage
5
JCoP for Tunnelling
Section 1 - Objective of the Code
  • To promote and secure Best Practice for the
    minimisation and management of risks associated
    with Tunnel Works
  • Applies to Project Development, Design,
    Construction Contract Procurement and
    Construction Stages of a Project
  • Does not supersede, replace or override existing
    Standards, legislation etc.

6
JCoP for Tunnelling
Section 2 Compliance
  • Compliance with the Code is pre-requisite for
    obtaining Insurance on all projects where the
    value of the Tunnel Works is 1m or above

7
JCoP for Tunnelling
Section 3 Introduction
  • Requires identification of hazards and the
    management of associated risks to ensure their
    reduction to a level as low as reasonably
    practicable (ALARP)
  • Responsibility for risk management to be
    explicitly allocated to relevant parties and
    clearly identified

8
JCoP for Tunnelling
Section 4 Definitions and Terms
9
JCoP for Tunnelling
Section 5 Risk Assessment and Management
  • Defines Risk ( consequence of a hazard x
    likelihood of occurrence)
  • Lists hazards (as events which have the
    potential to impact on a Tunnel Works project)
    and includes
  • health and safety
  • the environment
  • the design and the costs and programme for design
  • the construction of the project including the
    programme and cost for construction
  • Third Parties and existing facilities

10
JCoP for Tunnelling
Section 5 Risk Assessment and Management
(contd)
  • Notes that hazards should be identified on a
    project-specific basis
  • Risks to be identified and quantified through
    Risk Assessments for all stages of a project
  • Highlights the requirement for clarification of
    the allocation of risks (ie ownership - risk
    owners are those best able to manage the risks)

11
JCoP for Tunnelling
Section 5 Risk Assessment and Management
(contd)
  • Requires Risk Registers to identify the hazards,
    consequent risks, mitigation/contingency plans,
    proposed actions, responsibilities, critical
    dates for completion of actions and when actions
    have been closed out
  • Risk Registers are to provide the auditable
    trail throughout the life of a project to
    demonstrate compliance with the Code.

12
JCoP for Tunnelling
Section 6 Client Role and Responsibilities
  • Requires Clients to have demonstrable technical
    and contract management competence appropriate to
    the type, scope and extent of the project
    proposed

13
JCoP for Tunnelling
Section 7 Project Development Stage
  • Site and ground investigations to be designed,
    planned, procured and supervised by suitably
    competent personnel
  • Site and ground investigations to be executed by
    competent organisations

14
JCoP for Tunnelling
Section 8 Construction Contract Procurement
Stage
  • Selection of type of contract by the Client
    should take due regard of the allocation of risks
    to the parties to the Contract and consequently
    the liabilities of the parties to the Contract

15
JCoP for Tunnelling
Section 9 Design Stage(s)
  • Principle is to achieve a robust design i.e.
    where risk of failure or damage is extremely
    remote
  • Includes for preliminary and detailed designs and
    temporary works and permanent works designs
  • Section is not prescriptive in terms of Design
    Methods

16
JCoP for Tunnelling
Section 9 Design Stage(s) (contd)
  • Design Risk Assessments to consider the impact
    on the design and hence its implementation of
    design criteria variations, potential failure
    mechanisms and intermediate construction stages

17
JCoP for Tunnelling
Section 10 Construction Stage
  • Requirement for a Project Risk Management Plan to
    identify means and methods of monitoring,
    reviewing and updating Construction Stage Project
    Risk Register
  • Construction Stage Project Risk Register to
    include all project related risks identified at
    the Construction Stage together with
    project-related risks brought forward from the
    Client's pre-contract Risk Register and which may
    include health and safety risks

18
JCoP for Tunnelling
Section 10 Construction Stage (contd)
  • Carry out constructability reviews jointly with
    the Designer to ensure construction methods are
    suitable and appropriate
  • In the case of self-certification, Contractor to
    demonstrate how independent supervision of
    construction will be controlled and maintained
  • Value engineering proposals to include Risk
    Assessments
Write a Comment
User Comments (0)
About PowerShow.com