Berkeley Site - PowerPoint PPT Presentation

1 / 9
About This Presentation
Title:

Berkeley Site

Description:

Prepared by Andrew Oborne, Engineering Manager, BNLS ... of stainless steel ILW drums in caves with pond and zinc bromide windows drained) ... – PowerPoint PPT presentation

Number of Views:42
Avg rating:3.0/5.0
Slides: 10
Provided by: BNFL7
Category:
Tags: berkeley | bromide | site

less

Transcript and Presenter's Notes

Title: Berkeley Site


1
Berkeley Site
2
Berkeley Nuclear Licensed Site.
  • Care and Maintenance Preparations Waste
    Management.

Presentation to the RWIN Meeting, Winfrith, 28th
May 2008. Prepared by Andrew Oborne, Engineering
Manager, BNLS Presented on behalf of BNLS by
Roger Streatfield, Magnox South.
3
Contents.
  • Introduction to Berkeley Nuclear Licensed Site
    (BNLS).
  • Site Separation.
  • Periodic Safety Review (PSR) Works.
  • Reactor gas circuit drier desiccant.
  • Caesium Removal Plant (CRP) sludges and resins.
  • Active Waste Vaults.

4
Introduction to BNLS
  • Twin Magnox reactor site Berkeley Power Station
    (BPS).
  • Commissioned 1962.
  • Ceased generation 1989.
  • De-fuelling completed 1992.
  • Gas circuits removed and boilers laid down.
  • Pond drained, decontaminated and demolished.
  • Shielded Area Post Irradiation Examination (PIE)
    Facility Berkeley Centre (BC).
  • Constructed early 1960s.
  • Decommissioning started 2005.
  • De-licensed 11 hectares December 2006.

5
Site Separation
  • Aim Separation of licensed and de-licensed parts
    of the Berkeley Site to allow NDA to pursue
    alternative uses for the land.
  • Key Aspects.
  • 11kV supply separation.
  • Water supply and fire hydrant separation.
  • Sewage system separation.
  • Fire alarm and alarm monitoring system
    separation.
  • Independent security systems.

6
Periodic Safety Review Works
  • Periodic Safety Review being prepared to cover
    site operations from 2009 to 2019 as an ILW waste
    storage facility.
  • Completion of work for reactors to enter Care and
    Maintenance.
  • Safe, compliant storage of unprocessed ILW.
  • Active waste vaults (inspection and assessment to
    demonstrate integrity of underground vault
    structure).
  • Caesium removal plant sludges and resin (transfer
    to new proven tanks, with proven secondary
    containment).
  • Shielded area (storage of stainless steel ILW
    drums in caves with pond and zinc bromide windows
    drained).
  • Enhanced monitoring and surveillance
    capabilities.
  • Reconfiguration of site facilities for extended
    storage.

7
BNLS - Caesium Removal Plant (CRP) Project -
Desiccant
  • Used at BPS to remove moisture from the carbon
    dioxide primary coolant, contaminated by
    tritiated water vapour resulting in 107 x 200
    litre drums. Volume 10.6 m³.
  • To be retrieved and encapsulated in 500-litre
    drums using the LLW Solidification Plant (LLWSP)
    as per BPEO.
  • 360-day formulation trails complete.
  • LOC stage 2 submission in progress.

8
BNLS - Caesium Removal Plant Project Sludge
Resin
  • Vol. 10.6m³ of Sludge stored in Sludge and Sand
    Settling Tank (SSST) 1.
  • Vol. 11.72m³ of Resin stored in Spent Resin
    Storage Tank (SRST) 1.
  • ILW Solidification Plant (ILWSP) identified as
    processing solution following substantial
    engineering review.
  • Waste to be transferred from building tanks to
    Nirex 3m³. container, grouted, cured and
    transferred to ILW store.

9
Active Waste Vault Retrieval (AWVR) Waste
Management Strategy
  • Loose Fuel Element Debris (FED) ILW.
  • Retrieval from vaults.
  • Assay.
  • Transfer to Encapsulation Cell.
  • Place in 3m³ box.
  • Encapsulate.
  • Export to ILW Store.
  • LLW Chute Silo Gravel.
  • Retrieval from vaults.
  • Assay.
  • Transfer to LLW Compound.
  • Dispose to National LLW Repository.
  • Containerised Waste (Vaults, CRP, Shielded Area
    ILW).
  • Retrieval from Vault or import via import bay
    from shielded area.
  • Container Shredded.
  • Waste sorted through rotary screen and assay.
  • Collect as Miscellaneous Contaminated Items
    (MCI)/FED/Mobile.
  • Process to 3m³ drums in accordance with LoCs.
  • Encapsulate.
  • Export to ILW Store.
Write a Comment
User Comments (0)
About PowerShow.com