CPETECET 470 Project Management - PowerPoint PPT Presentation

1 / 22
About This Presentation
Title:

CPETECET 470 Project Management

Description:

However, you need the schedule to communicate to others what needs to be done ... Inference is based on your level of cognizance at the that time. ... – PowerPoint PPT presentation

Number of Views:20
Avg rating:3.0/5.0
Slides: 23
Provided by: bryanbo
Category:

less

Transcript and Presenter's Notes

Title: CPETECET 470 Project Management


1
CPET/ECET 470Project Management
  • Class 3 - Critical Path

2
Myth 4
  • I dont need a schedule, because I already know
    what needs to be done.
  • Maybe you do
  • However, you need the schedule to communicate to
    others what needs to be done
  • The team needs a vehicle to keep you informed of
    their plans

LESSON The schedule is a communication tool
3
Top Level Schedules 5 Easy Steps
  • List Program Tasks
  • Brainstorming is a good method to generate this
    list
  • All schedules should follow the WBS
  • Note Updates to the WBS should be expected as a
    result of the scheduling process.
  • Start with major deliverables and key milestones
  • Sequence Tasks
  • This is simply putting the tasks in the order
    they will occur
  • Identify Relationships between tasks
  • This requires team members who are cognizant of
    the processes involved
  • Assign Durations to Tasks
  • Analyze plan against program objectives

4
Myth 5
  • I dont have to put that task on the schedule.
    It is inferred from the phase of the program that
    it occurs in.
  • Inference is based on your level of cognizance at
    the that time. Others will be using the schedule
    to manage their work
  • Program team members change throughout the life
    of the program
  • All program efforts must be on the plan at some
    level
  • If it is not on the schedule, it will likely be
    forgotten .until it is too late, causing
    regression

Truth The schedule should document the plan
5
Schedule Analysis
  • What is schedule analysis?
  • Identifying the Critical Path
  • Forward and backward pass analysis
  • Identifying slack

6
Analyze the Plan
  • It is important to analyze any plan to determine
  • The overall health of the plan
  • Level of detail
  • Proper scheduling techniques applied
  • Compliance with significant milestones
  • The viability of the plan
  • Amount of margin in the plan
  • Areas of the plan that require action
  • Current and potential problem areas
  • Progress against the plan
  • Schedule position

7
Myth 6
  • I do not need a schedule because I already know
    what the critical path is.
  • You may have a sense of what the critical path is
  • When you prepare a detailed schedule, items that
    you did not expect or were not watching will
    surface on the critical path
  • Action must be taken to move these items off the
    CP
  • The individuals performing the work will plan for
    details that you may not be aware of

Truth The critical path must be managed, not
dictated
8
The Critical Path Definition
  • A set of activities which determine the earliest
    completion of the project, where any delay in any
    activity will delay the project by an equivalent
    amount
  • The path(s) in the task network with zero slack
  • The path with the longest duration through the
    network

9
Critical Path Exercise
  • Sum the times along each path in a network to
    determine the overall duration of each path.
  • The longest path in the network is the critical
    path.
  • The project cannot end before the critical path
    ends.
  • What is the critical path of the following
    network?
  • How long will this project take to complete?

Task G 6 days
Task C 3 days
Task A 3 days
Task D 7 days
Task H 1 day
Task F 5 days
Task E 4 days
Task B 2 days
10
Critical Path for an Entire Project
  • All tasks are compared to the latest task in the
    project. If a delay in a task would impact this
    date then the task is considered critical

Critical Path 0 7 5 4 0 16 days
11
Critical Path for multiple sets of tasks
  • Each chain of tasks calculates critical path
    separately within its own set of tasks. A
    critical path is calculated for each finish task
    within the project. A task is considered
    critical if it impacts the end of its network of
    tasks.
  • The example shows two chains of connected tasks
    within a single project, each calculating
    critical path from the finish tasks.

Critical Path 0 7 5 4 0 16
days Critical Path 0 6 9 15 days
12
Critical Path Analysis (CPA)
  • The Key Concept used by CPA is that a subset of
    project activities, which make up the longest
    path through the activity network, control the
    entire project
  • If these "critical" activities could be
    identified and assigned to responsible persons,
    management resources could be optimally used by
    concentrating on the few activities which
    determine the fate of the entire project
  • Non-critical activities can be replanned,
    rescheduled and resources for them can be
    reallocated flexibly, without affecting the whole
    project
  • There are three steps to performing Critical Path
    Analysis
  • Forward Pass
  • Backward Pass
  • Float Calculation

13
Forward Pass
  • The forward pass is calculation of the Earliest
    Start and Earliest Finish dates for each task in
    the network
  • Early Start Date the date at which the task's
    predecessors have all been completed
  • Early Finish Date the Early Start Date plus the
    task duration
  • A typical format of reflecting these dates in a
    network is

14
Forward Pass - Exercise
  • Start with the first task in the path and
    calculate the Early dates
  • Assume the project starts on Day 1 of the Project

ES
EF
ES
EF
Task G 6 days
Task C 3 days
ES
EF
Task A 3 days
ES
EF
ES
EF
Task H 1 days
Task D 7 days
ES
EF
Task F 5 days
ES
EF
ES
EF
Task B 2 days
Task E 4 days
15
Forward Pass - Exercise
  • Start with the first task in the path and
    calculate the Early dates
  • We will do the first two tasks together

Day 4
Day 6
ES
EF
Task G 6 days
Task C 3 days
Day 1
Day 3
Task A 3 days
ES
EF
ES
EF
Task H 1 days
Task D 7 days
ES
EF
Task F 5 days
ES
EF
ES
EF
Task B 2 days
Task E 4 days
16
Backward Pass
  • The backward pass is calculation of the Latest
    Start and Latest Finish dates for each task in
    the network
  • Late Start Date the date after which the task
    causes slippage of the project end date. It is
    determined by starting at the end of the project
    and working backwards
  • A typical format of reflecting these dates in a
    network is

17
Backward Pass - Exercise
  • Start with the last task in the path and
    calculate the Latest Dates
  • The Early Finish of the last task on the CP is
    equal to its Latest Finish

LS
LF
LS
LF
LS
LF
LS
LF
LS
LF
18
Backward Pass - Exercise
  • Start with the last task in the path and
    calculate the Latest Dates
  • We will do the first two tasks together

Day 7
Day 12
Task G 6 days
Day 10
Day 15
LS
LF
Day 16
Day 16
LS
LF
19
Forward and Backward Pass
  • Review the Critical Path
  • What do you Notice about the Early and Late Dates?

EARLY DATES LATE DATES on the CRITICAL PATH
20
What is slack?
  • The time between a tasks planned completion date
    and its need date
  • The time available to delay the completion of an
    activity without impacting the project end date
  • Useful to help to determine the impact of tasks
    slippage on the overall program schedule
  • Slack is used to prioritize tasks for resource
    allocation (the less slack, the higher the tasks
    priority because it is more critical)
  • The difference between a tasks Earliest dates
    and its Latest Start / Finish dates
  • Also referred to as Float

21
SLACK Calculation - Exercise
  • How much Slack (or Float) does each task have?
  • Slack LF - EF

22
Class 3 Assignment
  • Complete handout
  • Due Monday
  • Use Microsoft Project to assist you in providing
    answers if you want (good practice to learn the
    software)
  • Read paragraphs 15.4 15.5
Write a Comment
User Comments (0)
About PowerShow.com