Title: Water Services Training Group
1Water Services Training Group
- 13th Annual Conference
- 10th September 2009
2Prioritising Mains for Rehabilitation/Replacement
in a Large Urban Area
- Alan Curran
- Technical Director
- RPS Consulting Engineers
3Presentation Outline
- Case Study
- Dublin Region Watermains Rehabilitation Project
(DRWRP) Client Dublin City Council - Background
- Drivers Challenges
- DMA Prioritisation
- Mains Selection
- Key Issues and Lessons Learned
- Results
Meeting the Challenges of the Changed Economic
Environment Annual Conference September 2009
4Background Dublin Region Water Supply
- Greater Dublin Water Supply Area 7 LAs
- Serves a population of 1.4m
- Output 546 Ml/day
- Sustainable Prod. 520 Ml/day
- gt8,000km water main
- 600 DMAs
- Future Demand Shortfall Identified in 1996
Meeting the Challenges of the Changed Economic
Environment Annual Conference September 2009
5Background Dublin Region Water Conservation
Project (Stage 1 and 2) - 1998-2002
- Project Achieved
- New Monitoring, Control and Data Systems
- Metering and telemetry systems
- 530 District Meter areas (DMAs)
- Pressure management in selected areas
- A regional GIS system was established
- Regional hydraulic models were constructed
- Burst Record Database
- Establishment of trained leakage control teams
- Reduction in UFW from 42.5 to 28 (64Ml/day)
- Pilot Leakage Driven Water Mains Rehabilitation
- Confirmation that Rehabilitation Essential to
- Maintain Saving
- Reduce below 28
2002-2006 ALC and Systems Well Maintained
Meeting the Challenges of the Changed Economic
Environment Annual Conference September 2009
6DRWRP Drivers and Objectives
- Overriding Purpose
- To Save water by Rehabilitating water mains
- the greatest sustainable water savings,
- in a cost effective manner
- Through an Integrated Approach
- DMA Rehabilitation
- Hot Spot Rehabilitation Isolated High Burst
Frequency Mains - Active Pressure Management
- DMA Optimisation
- Improved Metering infrastructure (where required)
- While Recognising Risks
- Improved Service levels may offset savings
Meeting the Challenges of the Changed Economic
Environment Annual Conference September 2009
7DRWRP Scope
- Scope
- Up to 4 of total mains length ( 280 km) limited
by budget - Higher rate required in long term
- New development unlikely to be targeted (separate
issues)
Meeting the Challenges of the Changed Economic
Environment Annual Conference September 2009
8Challenges Urban Environment
- Complexity of the Network
- Understanding
- Valve Density, Status and Connectivity
- Handling Large Data Sets
- 8,500 km
- gt 600 DMAs
- 55,000 leak records
- Density of Services
- CSL Risk
- Night Users
- DMA Material and Age Mix
- Construction Cost Variability
- Access Issues Traffic Management
Meeting the Challenges of the Changed Economic
Environment Annual Conference September 2009
9Challenges - Leakage
- How to Achieve Success
- Which is ultimately measured at DMA Level
- Selecting the Correct
- DMAs
- Mains within the DMAs
- Accuracy of Leakage Calculations
- UFW does not leakage
- PCC changes with weather and temp.
- Leakage Fluctuates How do you Measure?
- Which Assets are leaking?
- Which DMAs/Assets will offer SUSTAINABLE
savings? - Which DMAs Offer Best VFM?
- Customer Side Leakage
Meeting the Challenges of the Changed Economic
Environment Annual Conference September 2009
10DMA Prioritisation - Objectives
1. DMA Prioritisation
- Data Collection Fitness for Purpose
Assessment - All 7 Authorities, All DMAs
- System Implementation for Data Management,
Leakage Analysis and Ranking - Characterise DMAs e.g. high leakage, high
pressure, unit costs - All DMAs
- Rank and identify shortlist DMAs (and reserves)
- to match available budget
- High-level identification of target mains
within DMAs
Collate Check Data
Agree Candidate DMA List
Characterise DMAs Leakage/Cost
Analyse DMA Leakage
Prepare DMA Rankings
Assign Leakage To DMA Assets
Identify Target Assets
LA Ranking Sense Check
Prioritise DMA Work Packages
Prioritise DMAs
Produce Strategy Report
Ranked DMA List
Strategy Report
Meeting the Challenges of the Changed Economic
Environment Annual Conference September 2009
11DMA Prioritisation Data
1. Strategy Development DMA Ranking
- GIS
- Network
- DMA Boundaries
- Geodirectory - Properties
- Other Network Information
- Pressure Management
- Schematics
- Telemetry
- Flow and Pressure
- DMA Leakage Sheets (ESPB)
- Leak Repair Records
- NRR
- Repeat Leak History
- Network Models
- AZNP
- Detailed Design
- Historical Rehabilitation Unit Costs
Collate Check Data
Meeting the Challenges of the Changed Economic
Environment Annual Conference September 2009
12DMA Ranking Characterise DMAs
SAVINGS
Mains Comm. Pipe Leakage
Meeting the Challenges of the Changed Economic
Environment Annual Conference September 2009
13DMA Ranking Characterise DMAs
SAVINGS
Natural Rate of Rise in Leakage
Meeting the Challenges of the Changed Economic
Environment Annual Conference September 2009
14DMA Ranking Characterise DMAs
COSTS
Mains Rehabilitation Works Costs
Meeting the Challenges of the Changed Economic
Environment Annual Conference September 2009
15DMA Ranking Characterise DMAs
COSTS
SAVINGS
Mains Comm. Pipe Leakage
Mains Rehabilitation Works Costs
/ Ml saved
Ml
Natural Rate of Rise in Leakage
DMA RANKING
Meeting the Challenges of the Changed Economic
Environment Annual Conference September 2009
16DMA Selection and Prioritisation
- 8 Ranking passes carried out Apr-July 06
- Each set reviewed LAs
- DMA Integrity
- sense check /local knowledge
- cross reference LA lists
- Unsuitable DMAs removed
- Need for High burst frequency programme agreed
- Ranked List of 60 for Field Validation
- Shortlist agreed matching DMAs non-responsive
to ALC
Meeting the Challenges of the Changed Economic
Environment Annual Conference September 2009
17Mains Selection - Objectives
- Validate/Improve Data in Candidate DMAs
- Field Work
- Desk Top
- Operations Staff Interview
- Leakage Asset Data
- Detailed Analysis and Scoring
- Recommend Solution
Meeting the Challenges of the Changed Economic
Environment Annual Conference September 2009
18Mains Prioritisation Validation
- 60 Short-listed DMAs and Reserves only (40/20)
- Integrity of the DMAs
- Meter / PRV audits,
- BV checks,
- PZT,
- Leakage Assignment
- Step-testing,
- Burst Geo-referencing and Assignement
- Operations Interview
- Data Review Leakage, Burst History, Customer
Side Leakage Assessment
Meeting the Challenges of the Changed Economic
Environment Annual Conference September 2009
19Mains Selection DMA Integrity
20Mains Selection Assets
21Mains Selection Bursts
22Mains Selection Step Tests
23Mains Selection Data Assessment Scoring
- All available information considered
- Burst Frequency
- Leakage
- Historical Performance
- Operations Knowledge
- Data Assessment and Scoring Applied
- Scoring Indicative
- Solution Recommended
- Further Investigation
- Do not Progress
- Pressure Mgt
- Rehabilitation Full or Partial
- Combination
Meeting the Challenges of the Changed Economic
Environment Annual Conference September 2009
24Mains Scoring L6/07 - Appendix 5
25Mains Scoring L6/07 - Appendix 5
26Results Skellys Lane
27Results Crumlin Cross
28Conclusions
- Good Data is Key to Sound Investment Decisions
- Use Best Available
- Non Domestic metering
- Pipe Samples - Opportunistic
- Improve Existing
- Geo-reference Burst Records
- Maintain GiS
- Maintain Telemetry Records
- Optimise DMA Sizes
- Develop NRR Calculations
- Burst Records
- ALC and Leakage History
- Use Scoring as Guide
Meeting the Challenges of the Changed Economic
Environment Annual Conference September 2009
29Conclusions
- Enormous Challenge
- Integrated Approach Essential
- Ongoing Active Leakage Control
- Pressure Management
- Data Improvements and Understanding of Components
of Demand - Demand Management
- Sustained Asset Renewal
- Mains Services??
- Rehabilitation only Part of the Solution
Meeting the Challenges of the Changed Economic
Environment Annual Conference September 2009
30Conclusions DRWRP Results
- Post 5 Contracts
- Total Length Rehabilitated 51km
- gt 4,000 New Boundary Boxes
- Total Savings 7.9 Ml/day
- Pipe Rehabilitation 2.1 Ml/day
- Pressure Mgt. 2.4 Ml/day
- DMA Optimisation/Metering 3.4 Ml/day
- Pilot DMA 100 Rehab
- Majority Leakage Private Side
- Public Network Leakage Minimal
- Integrated Approach Achieving Success
Meeting the Challenges of the Changed Economic
Environment Annual Conference September 2009