Title: SR 240 Slipform Paving Case Study
1SR 240 Slipform Paving Case Study
Alisa Cotter, Mike Hansen, and Eric McGarrah
2Where is SR 240?
3SR 240 is a Major Tri-Cities Route
- 60,000 ADT
- 110,000 ADT in 2025
- Original Alignment of 4 HMA Lanes (inadaquate)
- Project will replace with 8 PCC Lanes with a
depth of 11 inches.
4Project to Date
- Westbound lanes were closed and reconstructed
first. - Westbound lanes closed and traffic diverted to
eastbound lanes. - 2 temporary lanes were constructed to maintain
capacity.
- Westbound lanes opened to allow the construction
of the eastbound lanes.
5Batching
- Temporary batch plant located within ½ mile of
project. - Plant relocated from Spokane.
6Batching
- Aggregate was stored on site.
- Loaded into bins that feed the plant the
appropriate gradation for the mix. - A weighing system is used to ensure the correct
gradation.
7Batching
- Once aggregate is proportioned it goes into the
horizontal drum followed by - Water, cement, and admixtures.
- The horizontal drum mixes the components.
- The mix is then transferred to the tilt drum.
8Batching
- The tilt drum then transfers the mix to the end
dump trucks.
9The Mix
- A standard WSDOT mix was used.
- Maximum water/cement ratio of 0.44.
- Minimum cement content of 564 lbs/yrd3.
- Type 1 cement.
- 4,416 psi average 28 day compressive strength.
- 718 psi average 14 day flexural strength.
10The Mix
- Pave-Air, a proprietary air entraining agent, was
added for improved workability. - Masterpave, a proprietary water reducing agent,
was added to decrease water/cement ratio.
11Plant Production
- Materials are constantly delivered to the site.
- Two drums allow a second batch to be produced
while a truck is being loaded.
12Plant Production
- Ten end dump trucks were used.
- 9 yd3 per truck
- 1.5 minutes to load.
- 3 minutes from arrival to departure.
- 300 - 350 yrd3/hr
- 33 - 39 trucks/hr
13Noted Project Plant Issues
- WSDOT inspector noticed that the mix was 20-40
lbs low per batch. - Contractor was instructed to increase cement
content or batches would be rejected. - Resulting in a temporary plant shut down.
- We dont know what caused this . . . . ?
- Mechanical issue
- Cement Shortage at the plant.
14Mix Delivery
- Short delivery time allowed the use of end dump
trucks (2-3 min). - Trucks had to avoid the paving wire.
- Turn around point was provided.
- Trucks had to back up 500 -1000ft.
15Mix Delivery
- Concrete trucks had priority on and off the
project.
16High Productivity of Delivery and Placement
- Unusually high productivity was achieved with
only ten trucks because of . . . - Proximity of the plant.
- Thoughtful and efficient traffic control plan.
- Width of the paving.
- Use of a slip from paver.
17Set Up for Slipform Paving
- Surveyors must determine the elevation of the HMA
at 50 intervals to set the guide wire. - Number 1 tripping hazard for 1rst year engineers,
isnt that right Alisa.
18Set Up for Slipform Paving
- Bundles of dowel bars and containers of curing
compound must be laid out.
19Set Up for Slipform Paving
- Water is sprayed ahead of the paving to cool the
HMA base and keep water from being sucked out of
the mix.
20The Slipform Paver Needs Space
- The new alignment of this project provide a lot
of space. - Typical spatial needs include
- 2-3 feet on either side for tracks.
- Loading dowel bars.
- Access for laborers.
- Finishing
21Start-up of Slipform Paving
- The transverse construction joint must be
constructed. - 40-50 full width spot grinding was done at the
construction joints.
22Start-up of Slipform Paving
- A wetter mix is usually associated with the
initial batches making it difficult to maintain
the pavement edge.
23Start-up of Slipform Paving
- The paver has not developed the head that is
required, possibly resulting in surface voids.
24Concrete in the Slipform Paver
- The concrete is moved from side to side with the
bucket on the front of the paver.
25Concrete in the Slipform Paver
- The concrete is then vibrated by a series of
vibrators.
26Dowel Bar Insertion
27Dowel Bar Insertion
28Dowel Bar Insertion
29Loading of Dowel Bars
30Possible Issue of Dowel Bar Insertion
- Dowel bars need to be placed appropriately.
- Dowel bars are inserted using vibration and the
vibration continues when the inserters are pulled
back. - Does this alter the dowel bars alignment?
- Are the paint marks denoting the dowel bar
location in the right location?
31Mid-Slab Tie Bar Insertion
32Side Tie Bar Insertion
33Noted Paving Issues
- Shims were used at the construction joint because
the form was not as tall as the depth of the
paving. This might result in stress point that
could induce cracking.
34Noted Paving Issues
- There was 3 observed stoppages in the paving due
to the dowel bar bundles not being in the proper
location. Probably resulting in imperfection in
smoothness. - WSDOT allowed a deviation in the dowel bar
placement. - Only outside lanes had dowel bars across entire
width. - Inside lanes only had dowel bars in the wheel
path. - Saved the project about 56,000.
- Will this bite them later?
35Finishing
- Initial finishing is done by the side forms and
profile pan followed by a float and carpet drag
on the paver.
36Finishing
- Edge finishing requires 4 laborers (2 on each
side), one to remove the valley from invert on
the profile pan, the other to finish. - The finishing quality of this edge is very
important if there is an adjacent lane of PCC to
be paved.
37Transverse Tining
38Curing
39Noted Issues of the Curing
- The curing compound was tested twice and failed
twice. - WSDOT allowed the use at twice the application
rate. - During testing the contractor found it difficult
to apply a uniform cure in windy conditions. The
wind was not an issue during the case study.
40Compressive Strength Testing
- Minimum 28 day compressive strength of 3,216
psi.
41Air Entraining Testing
- Air entrainment between 3 and 7.
42Ride Testing and Pavement Depth
- The pavements smoothness was tested using a
profilograph. - Pavement depth was determined from coring.
43Contractor Bonus
- The contractor received a 3 bonus for gradation,
cylinder breaks, and air entrainment. Totaling
107,500 - The contractor also received 64,300 for the
pavements ride smoothness and 86,500 for
additional pavement thickness.