Title: The Impact of Ice
1The Impact of Ice
Nebraska Public Power District2006-2007
2Christmas Storm Outcome
- 10 transmission lines out made temporary
repairs to 8 2 remained out of service - 4 telecommunications fibers inoperable no
telecommunications west of Holdrege - 2,500 retail customers impacted
- 21 NPPD technicians assist Dawson PPD
- 1.0 Million in damages (approximate)
3New Years Storm Timeline
- Friday December 29
- Rain, freezing rain, icing, wind
- Saturday December 30
- Severe icing conditions and wind
- Widespread, extensive damage
- Crews respond to numerous outages
- Sunday December 31
- Major effort to assess damage and restore power
4Back-to-Back Storms
Christmas Storm
New Years Storm
5Normal NPPDTransmission System
Grand Island
Lexington
Kearney
Hastings
Holdrege
6System Condition January 1
7System Condition January 4
8Kearney Area Damage Assessment
-Wood Structures
-Steel Towers
-Shield Wire Miles
63
2
42
314
125
2
18
10
43
54
5
1
10
34
52
53
109
1
9Early Priorities
- Kearney
- Lost 4 of 5 transmission feeds
- Priority restoration of second feed
- Rolling blackouts during initial restoration
- Holdrege
- Lost all 3 transmission feeds
- Mobile generation located within the community
- Key Messages
- Energy conservation
- Fragile system
- Safety
10System Status March 2, 2007
- Initial Current
- Miles assessed 2,650
- Customers without power
- NPPD Retail (service restored 1/6/07)
11,612 0 - Wholesale customers 31,000 0
- (service restored 1/19/07)
- Transmission System (approx, 71 repaired)
- Number of line segments out 37
7 - Transmission miles out-of-service
1,053 184 - Number of substations out 18 0
- Miles of conductor down 301
86 - Number of structures damaged 1,136
473 -
- GGS east flow limitation
224 MW 990 MW - Communities on Mobile Generators
14 0 - More than a dozen public power utilities impacted
by storm - Contractors on site throughout reconstruction 260
- 320
Up to
Up to
These MW will depend on transmission system
status, loading conditions and regional
transmission system conditions.
11FEMA Disaster Declaration FEMA-1674-DR
12Ice on a guy wire
13Engineering Design Criteria
- National Electrical Safety Code 1997
- Heavy combined ice and wind loading, ½ inch
radial ice, 40 mph wind, 0F - National Electrical Safety Code 2007
- Heavy combined ice and wind loading, ½ inch
radial ice, 60 mph wind, 15F - New Years storm
- 2 inch radial ice, winds averaging 21 mph, gusts
up to 40 mph, temperatures hovering around
freezing
14Effect of Ice on Power Lines
- Typical weight of conductors without ice ½ to 1
pound per foot - Weight of lines with ice can increase by 4 - 8
pounds per foot - Weight on structures increased up to 8 - 10 times
after ice storm - Example 115kV structure load went from 3,000
pounds to 26,000 pounds (2-inch radial ice)
15(No Transcript)
16Size of ice one week after storm
17The ice mangled 345-kilovolt structures like
twist-ties
18More than 40, 345-kilovolt structures were
destroyed
19The storm snapped H-frame structures like twigs
20More than 300 miles of line and 1,137 structures
were damaged
21Ice on Substation near Holdrege, Neb.
22Emergency Restoration
23Initial Response
- Public Safety
- Cleared roadways
- Public Service Announcements
- Coordinated Emergency Personnel
- Coordinated with Governors Office
- Coordinated with Nebraska Emergency Management
Agency (NEMA) and Federal Emergency Management
Agency (FEMA) - Employee/Contractor Industrial Safety
- Reinforced NPPD Safety policies
- Cognizant of portable generators
24Initial Response
- Assessed damage to transmission infrastructure
- Surveyed more than 1,900 miles of line using
helicopters from Air National Guard, Nebraska
Highway Patrol and a private flying service - Ensured Nebraskans had power
- Needed to energize 115kV substations
- Restore transmission feeds to hardest hit
communities which lost multiple transmission
feeds - Energize distribution system to end-use customers
- Site mobile generation (NPPD, NEMA, FEMA)
- Assist other utilities as resources permit
- Restore telecommunications capability
25Emergency mobile generation was brought in for 14
communities
26Mutual aid near Elgin, Neb.
27Day-after-day diligence for more than 30 days.
The last community on emergency generation was
restored line service on Jan. 29, 2007.
28Reconstruction
29Reconstruction Strategy
- Reconnect Nebraska electrically west to east
- Secure contracts and labor resources to safely
expedite rebuilding transmission system network - Align reconstruction contractors based on
capability, line criticality and proven
performance - Align contractors, mutual aid workers and
District employees with performance expectations
30Restore Transmission System
- Material procurement and delivery
- Focus on primary reconstruction efforts
- Hire and assign contractors
- Parallel efforts (Customer Service Priorities)
- System Network Priorities
- Watch the weather
- Ensure equipment functions
31(No Transcript)
32More than 3,000 wood poles ordered.
33Unloading conductor at NPPDs York Operations
Center for 400 miles of line
34Contractors Reconstructing South of Holdrege, Neb.
35Restoration efforts near Prosser, Neb.
36Questions?
37Long-Term Challenges
- Maintaining electric grid reliability with
weakened high-voltage transmission system - Reconstructing during winter months (possibility
for additional storms) - Repairing electric grid in time for irrigation
season and peak summer electric load - Ensuring timely material deliveries managing
multiple, concurrent projects - Restoring normal generation output from Gerald
Gentleman Station
38Major Impacts
- Over 200 Union Pacific trains stopped due to
downed lines across rails and loss of power to
central signal control - Multiple Fiber Breaks
- Hildreth to Holdrege
- Holdrege J2
- Axtell Holdrege
- Crooked Creek Riverdale
- Riverdale - GI
39New Years Ice Storm Area
Transmission Lines Out-of-Service
39
40Generators at Holdrege
41Loads on Line Supports
Transverse
Tension
Tension
TOP VIEW
Typical Failure Point
Force
42- (This storm) was the greatest catastrophe to
ever hit a Nebraska utility. It will be
remembered and talked about for lifetimes. - Comment describing March 29,1976 ice storm from
NPPD commemorative booklet.