Title: YDSS Interceptor Sewer Project Information Package
1YDSS Interceptor Sewer Project Information
Package
Contents
- Cover Letter
- Project Overview
- Feedback Form
- Copy of Minister of Environment Letter dated
Oct 1/04
Public Meeting at Richmond Hill Lions
Hall February 8, 2005
2(No Transcript)
3What was the Original Project
The basis for the project was to intercept flows
from the existing YDSS sewer on Yonge Street to
alleviate capacity constraints in the existing
system
- Class EA Completed June 2003
- Detailed Design 80 Completed Oct 2004
- A diversion manhole was to be constructed at the
southeast corner of 19th Avenue and Yonge Street
followed by a 1500 mm (60 inch) sewer from Yonge
Street to Leslie Street. A 2100 mm (84 inch)
sewer would then be constructed down Leslie
Street which would connect into the existing
Leslie Street trunk sewer approximately 100 m
north of Elgin Mills.
4What Changed October 1, 2004
- Minister of the Environment received bump-up
request on project - Minister subsequently Denies Bump Up Request with
Conditions
- Overview of Conditions
- Comprehensive review of alternative routing
options and alternative sewer design and
construction techniques. - Pro-active, strategic, and ongoing Stakeholder
Relationship Management - Technical assessments sufficient for all permits
and approvals - Analysis of cumulative effects of dewatering
combined with other Regional projects - Independent Peer Reviews
- Technical resource for individual well
complainants - Additional monitoring and reporting requirements
during and after construction - More frequent, effective, interactive public
communication
5YDSS Interceptor Sanitary Sewer
Stouffville Road
Expanded Study Area Natural Features Mapping
- Oak Ridges Moraine
- Jefferson Complex
- Rouge Headwaters
19th Avenue
Leslie Street
Yonge Street
Bayview Ave
Elgin Mills
Major Mackenzie
6What are the routes
Stouffville Road
Expanded Study Area is Bounded By
- Bloomington Side Road
- 16th Avenue
- Bathurst Street
- Highway 404
19th Avenue
Preliminary List of Alignments
Leslie Street
Yonge Street
Bayview Ave
Elgin Mills
- Twinning of Leslie Street
- (Eliminates PS at Elgin Mills)
- Twinning of Yonge Street
- Newkirk Road
- OR Bayview Avenue
Major Mackenzie
7How will the Public be Consulted?
- Established a multi-stakeholder advisory
committee - Regular Public Information Forums - next one
February 8th, followed by another sometime in
March - Additional Outreach Initiatives
- Periodic newsletters with project up-dates
- Public Consultation Web Site to keep stakeholders
informed and to solicit feedback (more
information in a few weeks)
8What are potential stakeholders concerns?
- Concerns regarding the Oak Ridges Moraine,
Jefferson Forest, Headwaters to the Rouge and
fish habitat - Impacts to residents private wells
- Construction nuisance and construction impacts
- Timing of works
9How Will the Routes be Evaluated
- Natural Environmental Considerations
- Potential impacts to water resources and natural
heritage features - Social/Cultural, Economic/Financial,
Legal/Jurisdictional - Potential disruption during construction,
potential impacts to archaeological and built
heritage resources, and compatibility with
current and future land uses - Estimated capital costs and operating and
maintenance efficiencies - Potential land requirements
- Technical Considerations
- Constructability, flow capacity, dewatering
impacts, and potential conflicts with existing
utilities and infrastructure
10Design/Construction Alternatives
- Open Cut Sewer Installation
- Pump Station/ Forcemain
- Lift Station
- Tunneling (Earth Pressure Balance Machine)
11Project Team
12Timing
Current Reporting period