Albanian Power Distribution Privatization - PowerPoint PPT Presentation

1 / 22
About This Presentation
Title:

Albanian Power Distribution Privatization

Description:

... Options Report delivered in January, and included appendices ... Ongoing Concession transactions in power generation: Fieri TPP, Ashta HPP and Devoll River HPPs ... – PowerPoint PPT presentation

Number of Views:38
Avg rating:3.0/5.0
Slides: 23
Provided by: albani9
Category:

less

Transcript and Presenter's Notes

Title: Albanian Power Distribution Privatization


1
Albanian Power Distribution Privatization Transact
ion Issues and Risks Assessment and Allocation
Investors Roundtable Tirana, April 8,
2008 Private Enterprise Partnership Southeast
Europe Infrastructure
2
Agenda
Project Background and Status
Transaction Risks Assessment
Supply Risk Retail Tariff Level Distribution
Technical and Non-technical Losses Protection of
Vulnerable Consumers Regulatory Risk Other Risks
3
Project Background and StatusMilestones Achieved
(1)
  • January 22, 2007 IFC appointed as Lead Advisor
    by Albanias Ministry of Economy, Trade and
    Energy (METE).
  • Projects main objectives
  • Unbundling of Albanian Electricity Company
    (KESH) distribution business
  • Structuring of a PSP transaction
  • Executing an open, transparent and competitive
    bidding process
  • IFC has contracted for this project the following
    specialized consultants
  • Technical consultant SNC Lavalin
  • Accounting consultant Ernst Young
  • Legal consultant Gide Loyrette Nouel
  • Efforts towards the privatization of Power
    Distribution in Albania are integrated with all
    parties involved Work is closely coordinated
    with other activities undertaken by the GoA with
    the assistance of donors community.
  • September 07 Technical, legal and accounting Due
    Diligence review was completed . Preliminary key
    findings were presented to the government on July
    18.

4
Project Background and StatusMilestones Achieved
(2)
  • A number of regulatory reports and comments were
    delivered during the Due Diligence review
  • Electricity Market Functioning
  • Distribution and Public Supplier Organization
  • Tariff Regulatory Framework
  • The Strategic Options, as identified by IFC, were
    presented to the GoA in December. Final draft of
    Strategic Options Report delivered in January,
    and included appendices on
  • Public Supplier Organization
  • Accounting Issues and Pro-Forma BS and PL
  • Legal Due Diligence Report
  • Corporate Due Diligence Report
  • Draft of the Distribution Privatization Law
  • Distribution and Public Supplier Organizational
    Arrangements
  • An Invitation for Expression of Interest was
    published in the Economist issue of March 1st,
    2008.

5
The Wholesale-Retail Public Supply Model
Schematics
TSO
KESH Gen
Distribution Company

Wholesale Public
Retail Public Supplier
Wholesale Public Supplier


Supplier
Tariff Customers
Imports
Eligible Customers
Other Sources
Distribution Company covers distribution losses
at import market prices
A separate Public Supplier legal entity must be
created after a short transition period
NOTE DIAGRAM FOCUSES ON THE REGULATED MARKET FOR
TARIFF CUSTOMERS ONLY
6
Wholesale/Retail Public Supply ModelRoles and
Responsibilities
  • Wholesale Public Supply license holder will
    remain with KESH, but will be organized under a
    separate management structure within a transitory
    period and eventually as a separate legal entity
  • Retail Public Supply license will be granted to
    the DSO, but RPS will have to be organized under
    a separate management structure within a
    transitory period and eventually perhaps as a
    separate legal entity
  • Retail Public Supplier (RPS) is responsible for
  • buying energy from WPS and reselling it to the
    tariff customers. Price to Tariff Customers is
    pass-through plus a RPS margin
  • tariff Customer load forecast
  • billing and collection
  • Distribution System Operator (DSO) will be
    responsible for
  • operating, maintaining and expanding the
    distribution system throughout Albania
  • buying energy in the open market to cover the
    losses in the distribution system (technical and
    non-technical)

7
Risk Assessment and Allocation Main Risks
  • Supply Risk
  • Retail Tariff Level
  • Distribution Technical and Non-technical Losses
  • Protection of Vulnerable Consumers
  • Legal, Regulatory and Contractual Risk
  • Other Risks

8
Risk Assessment and AllocationSupply Risks
  • The risk that supply may not meet demand because
    of low production and interconnection capacities
  • Table 1 Power generated and purchased

9
Risk Assessment and AllocationSupply Risk
Mitigation
  • The physical constraints are expected to be
    largely eliminated for one or more years by
  • the commissioning of the Vlore thermal power
    plant in 2009, which will add about 800 GWh of
    annual production, and
  • the completion of a 400 kV transmission
    interconnection to Podgorica in the same year
  • Ongoing Concession transactions in power
    generation
  • Fieri TPP, Ashta HPP and Devoll River HPPs
  • The removal of the financial constraint will be
    largely achieved by
  • requiring DSO to buy energy for losses at market
    prices with a pass through of quantities and
    prices to tariff customers
  • implementing a fully adequate mechanism to allow
    the Wholesale Public Supplier to pay for
    additional supply expenses in poor hydrological
    periods

10
Risk Assessment and AllocationObligation to
Supply Risk
  • The Obligation-to-supply risk has been allocated
    to the Wholesale Public Supplier by adopting the
    Wholesale - Retail Supply Model
  • Wholesale Public Supplier (WPS) has the
    obligation to provide sufficient supply to Retail
    Public Ssupplier (RPS) to satisfy Tariff
    Customers demand
  • The DSO companys failure to supply caused by its
    own actions (e.g. poor transformer maintenance)

11
Risk Assessment and AllocationObligation to
Supply Mitigation
  • ERE will monitor the process and assess the
    adequacy of supply from Wholesale Public
    Supplier. Also the public supply tariff will be
    set to provide the WPS with sufficient revenue to
    cover reasonable levels of costs and profits
  • Distribution and retail tariffs will be set to
    provide DSO and RPS with
  • sufficient revenue to cover reasonable levels of
    operating costs and justified and prudent
    investments realized and reasonable profits and
  • incentives to reduce costs and operate
    efficiently
  • Incentives to ensure the reduction in non-payment
    of bills by tariff customers.

12
Risk Assessment and Allocation Retail Tariff
Level Risks
  • The risk that electricity revenue do not cover
    for power purchase costs
  • Table 2 Cost and Revenue for MWh produced and
    purchased

13
Risk Assessment and Allocation Retail Tariff
Level Mitigation
  • Tariffs will be set at cost-recovery level and
    power purchase costs will be fully passed through
    to tariff customers.
  • Distribution and retail tariffs will be set to
    provide DSO and RPS with sufficient revenue to
    cover reasonable levels of costs and profits
  • The tariff that Wholesale Public Supplier will
    charge the Retail Public Supplier will be
    determined in the regulated contract between WPS
    and RPS and will be monitored by ERE
  • The RPS will be allowed to pass through to tariff
    customers the cost of power purchased from WPS
  • DSO will be allowed to pass through to tariff
    customers the cost of power purchased to cover
    losses

14
Risk Assessment and Allocation Distribution
Losses
  • Risk DSO will fail to reduce technical and
    non-technical losses.
  • Presently the losses in the Distribution System
    are high. Total losses in 2007 are estimated at
    36.4, of which 35.4 are distribution losses
  • Table 3 Total energy produced and purchased
    compared with total energy billed

15
Risk Assessment and Allocation Distribution
Losses Mitigation
  • The Distribution Operator will have full
    responsibility to reduce technical and
    non-technical losses
  • The effectiveness of the Distribution Operator to
    reduce losses will be benchmarked
  • The amount of power purchased by the DSO to cover
    losses will be allowed to recover in Distribution
    tariffs
  • Price of power purchased by the DSO to cover
    losses will be allowed to recover in Distribution
    tariffs

16
Risk Assessment and Allocation Collection Risk
  • Risk that the company will be unable to will be
    unable to meet its revenue targets. This might
    occur for one or more of the following reasons
  • customers refuse to pay their bills,
  • customers tamper or disconnect meters,
  • company employees receive bribes to make illegal
    connections or under collect metered or billed
    amounts,
  • and government officials or courts are unable or
    unwilling to support disconnections or other
    actions against non-paying customers
  • Table 4 Percentage of Collections

17
Risk Assessment and Allocation Government
Support for Reduction of Non-technical Losses and
Increase in Collections
  • The most important support has been the complete
    elimination of arrears of government budgetary
    and non-budgetary entities (as of end of 2006) to
    KESH by mid-2007
  • The Government will continue to
  • support in strengthening the state and
    governments institutions role in prosecuting
    illegal consumers of electricity and persistent
    non-payers
  • ensure that all electricity bills of budgetary
    and non-budgetary entities are paid, if necessary
    through payments by the Ministry of Finance
  • The Government together with its lead advisor
    will engage in public information activities that
    will
  • Inform the Albanian consumers on the transaction
    structure role of Wholesale and Retail Public
    Supplier and all the privatization process
  • Be organized in parallel with the privatization
    transaction

18
Risk Assessment and Allocation Protection of
vulnerable consumers
  • WPS, RPS and vulnerable consumers would bear the
    adverse effect of any failure to implement a
    satisfactory mechanism to protect vulnerable
    consumers.
  • The draft ERE Regulations for Captive Customers
    provide for a two-block tariff structure for all
    tariff customers, including households, with the
    first block enjoying the hydro benefit and the
    second block having a price based on the cost of
    marginal energy
  • For 2008 ERE has established a first block for
    household consumption with a width of 300 kWh and
    a price of 7 lek/KWh. The second block is
    established at above 300 kWh with a price of 12
    lek/kWh.

19
Risk Assessment and Allocation Regulatory Risks
  • Risk that the regulator will reinterpret existing
    regulations or create new ones that will increase
    costs or reduce revenues.
  • The regulator disallows the prices paid or the
    quantities purchased.
  • Operating Cost Risk Risk that the company will
    not be able to recover the costs of operating its
    distribution system (i.e. the wires function)
    or the costs of retailing electricity (i.e. the
    supply function) either because the regulator
    disallows certain operating costs or sets
    unrealistic performance targets.
  • Capital Cost Risk Risk that the company will not
    be able to recover its capital costs because the
    regulator sets a low allowed capital base,
    disallows costs of certain capital expenditures,
    or sets low rates of return.

20
Risk Assessment and Allocation Regulatory Risks
Mitigation
  • Solid and Transparent Regulatory Framework
  • Potential investors will have an opportunity to
    comment and give feed-back on the final draft of
    the ERE regulatory documents
  • World Bank Partial Risk Guarantees (PRG), which
    are designed to help mitigate government-related
    performance and policy risks associated with
    privatizations
  • PRG can ensure that the regulatory framework
    committed to in the pre-privatization phase will
    be adhered to and not changed unilaterally
    following privatization
  • It is a transitional instrument to be used until
    the country has developed sufficient regulatory
    track record and has built up confidence in its
    sector policies
  • IBRD would require a counter-guarantee for the
    PRG from GOA as well as compliance with the
    Banks policies

21
Risk Assessment and Allocation Other Potential
Risks
  • Political Risks Risk of expropriation,
    nationalization, war, civil, disturbances and
    breach of contracts
  • Government Subsidy Risk Risk that the government
    does not pay promised subsidies or pays with
    considerable delay.
  • Inflation Risk Risk that the companys tariff
    will not be adjusted for general inflation.
  • Foreign Exchange Convertibility Risk Risk that
    the government will not give the company access
    to sufficient foreign exchange to repatriate
    earnings and to pay for costs incurred in other
    currencies.

22
Risk Assessment and Allocation
Note MDB Multilateral Development Bank, ECA
Export Credit Agency
Write a Comment
User Comments (0)
About PowerShow.com