Title: Albanian Power Distribution Privatization
1Albanian Power Distribution Privatization Transact
ion Issues and Risks Assessment and Allocation
Investors Roundtable Tirana, April 8,
2008 Private Enterprise Partnership Southeast
Europe Infrastructure
2Agenda
Project Background and Status
Transaction Risks Assessment
Supply Risk Retail Tariff Level Distribution
Technical and Non-technical Losses Protection of
Vulnerable Consumers Regulatory Risk Other Risks
3Project Background and StatusMilestones Achieved
(1)
- January 22, 2007 IFC appointed as Lead Advisor
by Albanias Ministry of Economy, Trade and
Energy (METE). - Projects main objectives
- Unbundling of Albanian Electricity Company
(KESH) distribution business - Structuring of a PSP transaction
- Executing an open, transparent and competitive
bidding process - IFC has contracted for this project the following
specialized consultants - Technical consultant SNC Lavalin
- Accounting consultant Ernst Young
- Legal consultant Gide Loyrette Nouel
- Efforts towards the privatization of Power
Distribution in Albania are integrated with all
parties involved Work is closely coordinated
with other activities undertaken by the GoA with
the assistance of donors community. - September 07 Technical, legal and accounting Due
Diligence review was completed . Preliminary key
findings were presented to the government on July
18.
4Project Background and StatusMilestones Achieved
(2)
- A number of regulatory reports and comments were
delivered during the Due Diligence review - Electricity Market Functioning
- Distribution and Public Supplier Organization
- Tariff Regulatory Framework
- The Strategic Options, as identified by IFC, were
presented to the GoA in December. Final draft of
Strategic Options Report delivered in January,
and included appendices on - Public Supplier Organization
- Accounting Issues and Pro-Forma BS and PL
- Legal Due Diligence Report
- Corporate Due Diligence Report
- Draft of the Distribution Privatization Law
- Distribution and Public Supplier Organizational
Arrangements - An Invitation for Expression of Interest was
published in the Economist issue of March 1st,
2008.
5The Wholesale-Retail Public Supply Model
Schematics
TSO
KESH Gen
Distribution Company
Wholesale Public
Retail Public Supplier
Wholesale Public Supplier
Supplier
Tariff Customers
Imports
Eligible Customers
Other Sources
Distribution Company covers distribution losses
at import market prices
A separate Public Supplier legal entity must be
created after a short transition period
NOTE DIAGRAM FOCUSES ON THE REGULATED MARKET FOR
TARIFF CUSTOMERS ONLY
6Wholesale/Retail Public Supply ModelRoles and
Responsibilities
- Wholesale Public Supply license holder will
remain with KESH, but will be organized under a
separate management structure within a transitory
period and eventually as a separate legal entity - Retail Public Supply license will be granted to
the DSO, but RPS will have to be organized under
a separate management structure within a
transitory period and eventually perhaps as a
separate legal entity - Retail Public Supplier (RPS) is responsible for
- buying energy from WPS and reselling it to the
tariff customers. Price to Tariff Customers is
pass-through plus a RPS margin - tariff Customer load forecast
- billing and collection
- Distribution System Operator (DSO) will be
responsible for - operating, maintaining and expanding the
distribution system throughout Albania - buying energy in the open market to cover the
losses in the distribution system (technical and
non-technical)
7Risk Assessment and Allocation Main Risks
- Supply Risk
- Retail Tariff Level
- Distribution Technical and Non-technical Losses
- Protection of Vulnerable Consumers
- Legal, Regulatory and Contractual Risk
- Other Risks
8Risk Assessment and AllocationSupply Risks
- The risk that supply may not meet demand because
of low production and interconnection capacities - Table 1 Power generated and purchased
9Risk Assessment and AllocationSupply Risk
Mitigation
- The physical constraints are expected to be
largely eliminated for one or more years by - the commissioning of the Vlore thermal power
plant in 2009, which will add about 800 GWh of
annual production, and - the completion of a 400 kV transmission
interconnection to Podgorica in the same year - Ongoing Concession transactions in power
generation - Fieri TPP, Ashta HPP and Devoll River HPPs
- The removal of the financial constraint will be
largely achieved by - requiring DSO to buy energy for losses at market
prices with a pass through of quantities and
prices to tariff customers - implementing a fully adequate mechanism to allow
the Wholesale Public Supplier to pay for
additional supply expenses in poor hydrological
periods
10Risk Assessment and AllocationObligation to
Supply Risk
- The Obligation-to-supply risk has been allocated
to the Wholesale Public Supplier by adopting the
Wholesale - Retail Supply Model - Wholesale Public Supplier (WPS) has the
obligation to provide sufficient supply to Retail
Public Ssupplier (RPS) to satisfy Tariff
Customers demand - The DSO companys failure to supply caused by its
own actions (e.g. poor transformer maintenance)
11Risk Assessment and AllocationObligation to
Supply Mitigation
- ERE will monitor the process and assess the
adequacy of supply from Wholesale Public
Supplier. Also the public supply tariff will be
set to provide the WPS with sufficient revenue to
cover reasonable levels of costs and profits - Distribution and retail tariffs will be set to
provide DSO and RPS with - sufficient revenue to cover reasonable levels of
operating costs and justified and prudent
investments realized and reasonable profits and - incentives to reduce costs and operate
efficiently - Incentives to ensure the reduction in non-payment
of bills by tariff customers.
12Risk Assessment and Allocation Retail Tariff
Level Risks
- The risk that electricity revenue do not cover
for power purchase costs - Table 2 Cost and Revenue for MWh produced and
purchased
13Risk Assessment and Allocation Retail Tariff
Level Mitigation
- Tariffs will be set at cost-recovery level and
power purchase costs will be fully passed through
to tariff customers. - Distribution and retail tariffs will be set to
provide DSO and RPS with sufficient revenue to
cover reasonable levels of costs and profits - The tariff that Wholesale Public Supplier will
charge the Retail Public Supplier will be
determined in the regulated contract between WPS
and RPS and will be monitored by ERE - The RPS will be allowed to pass through to tariff
customers the cost of power purchased from WPS - DSO will be allowed to pass through to tariff
customers the cost of power purchased to cover
losses
14Risk Assessment and Allocation Distribution
Losses
- Risk DSO will fail to reduce technical and
non-technical losses. - Presently the losses in the Distribution System
are high. Total losses in 2007 are estimated at
36.4, of which 35.4 are distribution losses - Table 3 Total energy produced and purchased
compared with total energy billed
15Risk Assessment and Allocation Distribution
Losses Mitigation
- The Distribution Operator will have full
responsibility to reduce technical and
non-technical losses - The effectiveness of the Distribution Operator to
reduce losses will be benchmarked - The amount of power purchased by the DSO to cover
losses will be allowed to recover in Distribution
tariffs -
- Price of power purchased by the DSO to cover
losses will be allowed to recover in Distribution
tariffs
16Risk Assessment and Allocation Collection Risk
- Risk that the company will be unable to will be
unable to meet its revenue targets. This might
occur for one or more of the following reasons - customers refuse to pay their bills,
- customers tamper or disconnect meters,
- company employees receive bribes to make illegal
connections or under collect metered or billed
amounts, - and government officials or courts are unable or
unwilling to support disconnections or other
actions against non-paying customers - Table 4 Percentage of Collections
17Risk Assessment and Allocation Government
Support for Reduction of Non-technical Losses and
Increase in Collections
- The most important support has been the complete
elimination of arrears of government budgetary
and non-budgetary entities (as of end of 2006) to
KESH by mid-2007 - The Government will continue to
- support in strengthening the state and
governments institutions role in prosecuting
illegal consumers of electricity and persistent
non-payers - ensure that all electricity bills of budgetary
and non-budgetary entities are paid, if necessary
through payments by the Ministry of Finance - The Government together with its lead advisor
will engage in public information activities that
will - Inform the Albanian consumers on the transaction
structure role of Wholesale and Retail Public
Supplier and all the privatization process - Be organized in parallel with the privatization
transaction
18Risk Assessment and Allocation Protection of
vulnerable consumers
- WPS, RPS and vulnerable consumers would bear the
adverse effect of any failure to implement a
satisfactory mechanism to protect vulnerable
consumers. - The draft ERE Regulations for Captive Customers
provide for a two-block tariff structure for all
tariff customers, including households, with the
first block enjoying the hydro benefit and the
second block having a price based on the cost of
marginal energy - For 2008 ERE has established a first block for
household consumption with a width of 300 kWh and
a price of 7 lek/KWh. The second block is
established at above 300 kWh with a price of 12
lek/kWh.
19Risk Assessment and Allocation Regulatory Risks
- Risk that the regulator will reinterpret existing
regulations or create new ones that will increase
costs or reduce revenues. - The regulator disallows the prices paid or the
quantities purchased. - Operating Cost Risk Risk that the company will
not be able to recover the costs of operating its
distribution system (i.e. the wires function)
or the costs of retailing electricity (i.e. the
supply function) either because the regulator
disallows certain operating costs or sets
unrealistic performance targets. - Capital Cost Risk Risk that the company will not
be able to recover its capital costs because the
regulator sets a low allowed capital base,
disallows costs of certain capital expenditures,
or sets low rates of return.
20Risk Assessment and Allocation Regulatory Risks
Mitigation
- Solid and Transparent Regulatory Framework
- Potential investors will have an opportunity to
comment and give feed-back on the final draft of
the ERE regulatory documents - World Bank Partial Risk Guarantees (PRG), which
are designed to help mitigate government-related
performance and policy risks associated with
privatizations - PRG can ensure that the regulatory framework
committed to in the pre-privatization phase will
be adhered to and not changed unilaterally
following privatization - It is a transitional instrument to be used until
the country has developed sufficient regulatory
track record and has built up confidence in its
sector policies - IBRD would require a counter-guarantee for the
PRG from GOA as well as compliance with the
Banks policies
21Risk Assessment and Allocation Other Potential
Risks
- Political Risks Risk of expropriation,
nationalization, war, civil, disturbances and
breach of contracts - Government Subsidy Risk Risk that the government
does not pay promised subsidies or pays with
considerable delay. - Inflation Risk Risk that the companys tariff
will not be adjusted for general inflation. - Foreign Exchange Convertibility Risk Risk that
the government will not give the company access
to sufficient foreign exchange to repatriate
earnings and to pay for costs incurred in other
currencies.
22Risk Assessment and Allocation
Note MDB Multilateral Development Bank, ECA
Export Credit Agency