Title: DEVELOPING THE ORGANISATIONAL DESIGN FOR THE SPMC
1NDPW TRANSFORMATION RESTRUCTURING
PRESENTATION TO THE PORTFOLIO COMMITTEE NDPW
Project Plan
16 April 2003
2Contents
- NDPW Transformation Project Background and
Overview Role-players, roles and responsibilities - Transformation Project Plan
3Change imperatives
- Need for client focused approach
- Government as a whole was changing
- Client becoming more aware of service standards
- Public Works function under review in other parts
of the world - Transformation of DPW continuous and efficiency
driven - Infusing business principles in our approach
-
4NDPW Transformation Project Background and
Overview
- The Department was faced with major challenges in
the delivery of its core mandate as envisaged by
the new government strategy, key among them being
the following - An inability to maximize the R.O.I. on State
Assets due to the non-existence of an Asset and
Property Management wing - An inability to deliver services quickly and
efficiently to client departments - An inability to take leadership of the Industries
within which the Department operates and in
particular to lead an Industry Wide
Transformation effort - The Department then embarked on a transformation
effort aimed at changing this state of affairs
and adopted the following key strategic drivers
to inform its transformation route - CUSTOMER FOCUS To provide service delivery
excellence through customer focused world class
operations. - OWNERSHIP To maximise government shareholder
value through best practice immovable asset
portfolio management practices. - POLICY To provide leadership in the setting and
monitoring of construction and property related
transformation programmes, policies and
regulatory guidelines governing government and
the industries at large. - POVERTY To maximise the impact of government
initiatives on the poor by driving the effective
implementation of governments community
development programmes
5The strategic focus of the department will rest
on the 2 interlinked legs.
New NDPW
Policy Ownership
Operations
HEAD OFFICE
HEAD OFFICE
Shared Services
- Owner
- Policy development
- Social development
- Strategic Property Asset Management
- Accommodation Services
- Strategic Planning
- Customer focus
- Service delivery
REGIONAL OFFICES
REGIONAL OFFICES
- Decentralization
- Single Point of Accountability
Compliance guidelines and directives Implementatio
n in regions
6NDPW Transformation Project Background and
Overview.
- The Department was on the brink of implementing a
Transformation Plan based on different timelines
when Resolution 7 8 of 2002 were introduced as
a Framework for the Transformation of the Public
Service. - The Department then aligned its Transformation
Implementation to this government wide effort. - The Department was faced with a massive challenge
as it was not merely restructuring but truly
seeking to Transform itself into a commercially
robust entity able to meet its private sector
competitors on equal footing and able to deliver
maximum return to the State and its Clients
whilst operating within the bureaucratic
confines. - The Department rolled out its Transformation
during August 2002. - During this Implementation Phase a lot of
grievances were received arising from the
matching and placing exercise. - This prompted the new Director General in
consultation with the Minister to order a review
of the whole project, the outcome of which
resulted in the whole process being reviewed. - The decision to review gave members of staff and
the management team another opportunity to
critically analyze the whole project and to
reassess the new Implementation Framework.
7NDPW Transformation Project Background and
Overview.
- The Project Team that is managing transformation
consists of a Project Manager and a multi
disciplinary project team reporting to him. - This Project Team is responsible for the delivery
of the entire Transformation effort which is
aligned to the 30 June 2003 deadline of
implementing Resolution 7 8 of 2003. - Transformation will continue beyond the 30th of
June but the people issues will have been
resolved and finalized by then. - The Team has developed a Project Plan Detailing
how Transformation will be delivered
8Contents
- NDPW Transformation Project Background and
Overview Role-players, roles and responsibilities - Transformation Project Plan
9The transformation project plan has a number of
sub-projects that must be well coordinated to
ensure successful outcomes
Change management
DPSA Report Review
To-Be Processes
To-Be operational policies procedures
Ideal To-Be NDPW
Current As-Is NDPW
To-Be Org Structure
To-Be IT/IS
Matching Placement
Close-out reports
10For each of these sub-projects there are specific
activities and expected outcomes with cross
dependencies and timelines.
Activities
Timelines
Dependencies
Outcomes
Resources
Change management
Critical Review
DPSA Report Review
Critical Review
Critical Review
Critical Review
To-Be Processes
To-Be operational policies procedures
Critical Review
Critical Review
To-Be Org Structure
To-Be IT/IS
Critical Review
Matching Placement
Critical Review
Critical Review
Close-out reports
11Overview
Change Management
DPSA Report Review
Process mapping
Operational Policies Procedures
Structural review
Space Planning
IT/IS Systems
Matching placement
Phase 1 Closeout Reports
12Change Management
Project Dependencies None Critical Success
factors Accessibility to all stakeholders,
Project Reliability, Timeous Reporting
Change Management
Dipsticking
DG Messages to All Staff
Teleconferences
Pamflets to All Staff
WorxNews
Vistits/Meetings (EMC/TMC/Manco/DTT/ALL Staff
Team Resources C. Alexander, L. Mxenge, K.
Oagile, Communications et al Outcome Approved
activity planning
Frequently Asked Questions Reply Leaflets
Start 01/04/2003 Continuous
Counselling/Motivational Speakers/Team Building
Sessions
13DPSA Report Review
Project Dependencies None Critical Success
factors Availability of stakeholders, formal
approval of activity planning by stakeholders
(Minister, DG, DPSA)
Meetings Meetings with DPSA, Internal
Stakeholders, DTT, DGs Office re outcomes of
DPSA report
Documentation drafting Report formulation
responding to outcomes of DPSA report with
activity planning going forward
Start 13/03/03 Finish 20/03/03
Start 17/03/03 Finish 27/03/03
Team Resources C. Alexander, K. Oagile, L.
Fakazi, G. Sebati, L. Mabuntana, J. Tsimo, B.
Annandale et al Outcome Approved activity
planning
To-Be Processes, Policies Procedures
14To-Be Processes, Operational Policies
Procedures...
Project Dependencies Approved activity
plan Critical Success factors Organisational
buy-in through extensive consultation
- Process mapping
- Design and delivery of draft high level processes
- Detailed design consultations
- Presentations / Roadshow on detailed designs (RO
HO) - Delivery of final process mapping
- Approval of final report
Team Resources C. Alexander, L. Dhlomo, J.
Tsimo, P. Chiapasco, J. Vermaak et al Outcome
Approved To-Be Processes, Policies Procedures
and Organisational Structure
Start 26/03/03 Finish30/04/03
- Operational Policies Procedures
- Review of existing policies procedures per
process - Design and delivery of draft policy and procedure
manuals - Presentations / Roadshow on final policy and
procedure manual - Incorporation of input from road show
- Approval of operational policies procedures
Start 04/04/03 Finish30/04/03
To-Be Structure space planning
15To-Be Organisational Structure including Space
Planning
Project Dependencies Alignment of To-Be
Processes Critical Success factors
Organisational buy-in through extensive
consultation, structure alignment with ENE budget
estimates
- Structural review
- Review with TMC / Senior management
- Review with Managers per cluster
- Review with HR Finance (costing)
- Review with Office of the DG
- Approval of structure
- Costs made up of
- Staffing costs
- Annual increases
- Annual bonuses
- Merit awards
- Notch increments
- Severance packages
- Pension payouts
- Leave liability
- Deployment costs
- Recruitment costs
Start 28/03/03 Finish24/04/03
- Space Planning
- Draft space requirements
- Costing and layout
- Approval of space requirements
- Final space requirements
- Commence with acquisition of accommodation
Start 07/04/03 Finish25/04/03
Team Resources C. Alexander, G. MacMaster, J.
Vermaak, J. Tsimo, S. Mosegomi et al Outcome
Approved and Affordable To-Be Organisational
Structure
To-Be IT/IS
16To-Be Organisational IT/IS Systems
Project Dependencies Inputs from To-Be
Processes, Operational Policies
Procedures Critical Success factors Alignment
with user needs, IT budget availability,
procurement and implementation roll-out time
- IT/IS Systems
- Procurement of enterprise architecture systems to
design To-Be IT/IS systems - Input of user needs based on To-Be Processes
- Design of required enterprise architecture
- Procurement of systems
- Implementation
- Testing
- Roll-out
Start 01/04/03 Finish30/07/03
Team Resources C. Alexander, N. Mosupye, J.
Tsimo, L. Mabuntana et al Outcome IT/IS
infrastructure enabling To-Be business needs
Matching and Placement
17Matching placement and project closeout
Project Dependencies Approved To-Be
Structure Critical Success factors Approved
matching placement criteria and implementation,
availability of data / information required to
implement criteria
- Matching placement
- Design and DPSA approval of matching placement
criteria and implementation plan - Compilation of all data / information required to
apply criteria - Internal matching placement
- Advertising within Dept External for SMS
- Consultation letters to excess staff
- Interviews appointments
- Development of excess vacancy list
- Open up applications for severance package VERP
- IDTT approval re external adverts
- Second round of advertising (external)
- Shortlisting
- Interviews (all adverts done before 1 June)
- Interviews appointment deadline
- Counselling severance package
- Reports
- Draft report on transformation
- Final report on transformation
Start 14/04/03 Finish29/07/03
Team Resources C. Alexander, K. Oagile, L.
Fakazi, G. Sebati, P. Chiapasco, L. Mabuntana et
al Outcome Populated To-Be organisational
structure
- Closeout Reports
- Draft report on transformation
- Final report on transformation
Start 01/08/03 Finish18/08/03
18There are additional key factors for that top and
senior management need to keep in mind for
achieving successful transformation
Critical Success Factors
- 100 buy-in by top management to the aims and
objectives of transformation - Transformation effort must be driven from top
management level - Strong involvement and support required from
senior management particularly in the cascading
of transformation initiatives to lower levels of
the Department - Accessibility of top and senior management to
staff across the organisation - Accessibility of (correct) information to staff
across the organisation - Clients must be increasingly informed of
envisaged service delivery improvements and major
transformation project milestones - Financial and other resources must be available
for meaningful participation and effective
project implementation - Work teams must pro-actively identify and manage
project risks
19Conclusion-Key challenges
- Alignment DPSA process with Government wide
transformation (Resolutions 7 8) - -Time pressures
- -Interpretation issues
- Transformation fatigue
- Morale issues
- Improving communication with all levels of staff
- Increasing pace of change
- Finalising the new structure (and costing
thereof) - Expediting appointment process
- Stabilising leadership core
- Need to change mind-sets
- Need to establish efficiency to inform continuous
transformation of DPW.