Title: Monthly 2_25/ Page 1
1Monthly Status Report Report due 2/25/01 Schedule
statused as of Feb. 16, 2001
2Project Status Summary
Programmatic Dec Jan Feb
Schedule Dec Jan Feb
Resources Dec Jan Feb
Detailed Description (for items identified as
yellow or red)
- We received the ELS parts back from MSSL / Walton
Plating and completed assembly of the flight
unit. The unit was then vibrated and cycled in
thermal vac. The unit just completed
characterization testing and has only one
remaining task, measurement of mass properties. - We are nearing completion of the Acceptance Data
Package and will be ready for the Pre-Ship Review
scheduled for March 1. - DD250s have been submitted to the NMO for both
the IMA delivery and the upcoming ELS delivery. - Latest project photos and videos are available on
Aspera-3 web site.
3Problem and Concern Summary
PProblem CConcern RResolved
4Accomplishments of the Last Month -ELS
- We received the flight blackened parts from MSSL
/ Walton Plating. The parts looked very good.
We inspected them and decided to use all of the
parts from the latest batch. The parts were then
vacuum baked out prior to assembly. - The flight unit was assembled for flight and then
vibrated to protoflight levels. - Following vibration, a limited functional test
was performed and the unit was then thermal
vacuum cycled. Hot and cold starts were
performed. The unit was left powered on after
the cold start throughout the temperature
transitions and plateaus. High voltage was set
to the maximum level. Everything looked good. - The unit was then removed from the thermal
chamber and installed into the characterization
chamber where the high voltage test was re-run
followed by the full characterization test. We
have completed the testing and are currently
analyzing the data. - The flight spare was reassembled and installed
into the characterization chamber. High voltage
testing was run prior to needing the GSE for the
flight unit TVAC test. - This week, the flight spare was reinstalled back
into the characterization chamber (it was removed
to perform characterization of the flight unit)
for its final testing. This will be complete by
Feb. 27.
5Accomplishments of the Last Month - IMA
- The DD250 for delivery of the IMA hardware was
resubmitted to NMO based on several discussions.
We are awaiting return copies.
6Accomplishments of the Last Month - Data
Reduction Software
- Worked on APAF Software Requirements
Specification (SRS) - Draft to be released by the end of February, 2001
- APAF Software Requirements Review to be Held at
Next ASPERA-3 Team Meeting in Kiruna, Sweden
(March 6-7, 2001) - Continued Packet Definitions for ELS
- Done all we can for now. We're waiting on the
flight software personnel at FMI (Finnish
Meteorological Institute) for feedback. - Continued Providing Technical Assistance for EPO
Web Information - Continued Defining and Implementing IDFS Web
Tools - Held monthly ASPERA-3 Software Status Meeting
(February 23, 2001)
7Planned Activities for the Next Month - ELS
- Measure mass properties of the flight unit.
- Finalize characterization testing of the flight
spare. - Hold ELS Pre-ship Review
- Deliver ELS flight unit to IRF.
- Attend ASPERA-3 team meeting.
8Planned Activities for the Next Month - IMA
9Planned Activities for the Next Month - Data
Reduction Software Tasks
- Attend ASPERA-3 Team Meeting March 6-7 in Kiruna,
Sweden - Conduct APAF Software Requirements Review (at
ASPERA-3 Team Meeting) - Continue Working on APAF Software Requirements
Specification (SRS) - Continue Packet Definitions for ELS as Needed
- Begin Packet Definitions for NPI
- Continue Providing Technical Assistance for EPO
Web Information - Continue Defining and Implementing IDFS Web Tools
10Problem and Concern Status
11 Schedule Summary
- ELS Everything is on track for on-time delivery
of the flight unit to IRF. The remaining
activities are to measure the mass prosperities
of the unit, hold the Pre-Ship Review and hand
deliver the unit to IRF. - Software Some software activities have been
delayed due to hardware activities. The overall
delivery of the software to support mission
operations however continues to be on schedule. - The full-up schedule is available on the ASPERA-3
Web site.
12ASPERA-3 PHASE B/C/D MASTER SCHEDULE