Title: How to Implement the CalARP Program


1
How to Implement the CalARP Program
  • Presented by
  • Beronia Beniamine
  • Senior Hazardous Materials Specialist

2
Introduction
  • Help Administrating Agencies in establishing and
    implementing the CalARP program
  • Guidance to develop a strategy to adequately
    implement the CalARP program.

3
Definition of AA
  • Administrating Agencies (AA) are the local agency
    authorized by OES to implement and enforce the
    CalARP program in California. AAs also known as
    Certified Unified Program Agency (CUPA),
    Participating Agency, or Designated Agency.

4
Regulations
  • Federal Risk Management program (FEDRMP) Title
    40 of CFR, Part 68
  • Federal OSHA Process Safety management Program
    (OSHA PSM)-Title 29 of the CFR Part 1910.119
  • California Accidental Release Prevention Program
    (CalARP) California Code of Regulations, Title
    19, Division 2, Chapter 4.5, Article 1 through
    11.

5
Stationary Source
  • Any buildings, structures, equipment,
    installations, or substances emitting stationery
    activities which belongs to the same industrial
    group, which are located on one or more
    contiguous properties, which are under the
    control of the same person (or persons under
    common control), and from which an accidential
    release may occur.

6
Risk Management Plan
  • Risk Management Plan (RMP) is a document that
    must be a true and accurate reflection of a
    facilitys compliance with the elements of the
    CalARP Program. It summarizes the facilitys
    accidental release prevention program
    implementation activities. Each facility with
    one or more covered processes, must prepare and
    submit a single RMP that includes all covered
    processes.
  • (Note If an RMP is required by the FedARP
    Program, the single RMP may need to be crafted
    to meet AA documentation requirements.)

7
Process
  • Process means any activity involving a regulated
    substance including any use, storage,
    manufacturing, handling, or on-site movement of
    such substances, or combination of these
    activities. A process can be as simple as a
    single storage vessel or a group of drums or
    cylinders in one location or as complicated as a
    system of interconnected reactor vessels,
    distillation columns, receivers, pumps, piping,
    and storage vessels

8
Program Description
  • The program consists of two major components
  • 1. The Risk management Plan (RMP) Review
    process
  • 2. The audits-inspections of the program

9
Review Steps
  • There are 4 major steps that need to be
    considered in establishing the CalARP program
  • Step 1
  • -Notification
  • -Orientation Meeting

10
Review Steps
  • Step 2
  • -Initial Review
  • -Initial Public Notice
  • Step 3
  • -Informal Review
  • -Completeness Review

11
Review Steps
  • Step 4
  • -Public Review
  • -Evaluation Review

12
Notification
  • Send an initial notification letter to Stationary
    Source (SS) with more than the threshold of a
    regulated substance. A business plan inventory
    information, Air Districts , Building
    departments, or other permit issuing agencies
    might be helpful in identifying RMP facilities.
  • Note in the initial notification letter that the
    SS will have one year from the initial
    notification letter to submit the RMP plan.
  • You can suggest a date for the orientation
    meeting or you can call the SS to schedule one.

13
Orientation
  • Orientation meeting might be helpful in opening a
    dialogue between the SS and the agency.
  • Some of the items that need to be discussed at
    the orientation meeting
  • Description of the RMP process
  • The description of the covered process(es)
  • RMP fees
  • Program Level
  • Timeline for the RMP process
  • During the meeting, make sure to
  • Bring a copy of the Guidance, County or OES
  • Request that the facility will inform you of
    their HAZOP meeting schedule

14
Initial Review
  • SS will submit the RMP to the AA for review
  • AA will do the the Initial Review to determine
    that all the required elements pursuant to
    sections 2745.3 through 2745.9 are documented in
    the RMP plan and it contains appropriate level of
    detail.
  • written notice or verbal notice should be
    provided to the SS if deficiencies were found.
  • Always keep copies of the checklist in the
    facility's file.

15
Initial Public Notice
  • After the initial review is completed, the AA
    will publish a notice in a local newspaper of
    general circulation that the RMP has been
    submitted and the AA has initiated the process
    for government and Public review.
  • Always keep a copy of the initial public notice
    in the facility file.
  • Wording in the Initial Public Notice can be very
    simple such as Pursuant to the California Code
    of Regulations, Title 19, Division 2, Risk
    Management Plan(s) RMP have been submitted to
    Name of AA by the following (Name of companies)
    . The department has initiated the process for
    government and public review.
  • A letter will be sent out to SS verifying the
    receipt of their RMP plan and the date of when
    the public notice will be published.

16
Informal Review/ Completeness Review
  • AA will start the informal review to determine
    that the RMP is complete. During the informal
    review, the SS is allowed to receive a feedback
    from the AA prior to the completeness review. If
    there are deficiencies, then the AA will notify
    the SS and a 60 days (facility may request a
    one-time 30 days extension) time frame will be
    given to correct those deficiencies.

17
Type of Deficiencies
  • There are two types of deficiencies
  • Omission Deficiencies- Is the result of the
    exclusion of a local, State , and Federal
    requirement or failure to submit detailed
    information.
  • Error of Fact- Is a result of misstatement by
    the SS. Vagueness, or insufficient evidence may
    be misleading to the RMP reviewer.
  • AA may provide a verbal notice to the SS of any
    deficiencies.

18
Completeness Review
  • If deficiencies are identified, a letter will be
    sent out to the SS notifying them of the
    deficiencies and assigning a date to correct the
    deficiencies. Typically 60 days will be given ,
    however, the SS may request a one-time extension.
  • Failure to correct deficiencies during specified
    time frame shall be subject the owner/operator of
    a stationary source to to the penalties specified
    in Section 25540 and 25541 of HSC
  • Once all the deficiencies are corrected, the RMP
    should be accepted as complete. If the SS fails
    to submit the revised RMP, then enforcement
    action must be considered.

19
Formal Public Review
  • Within 15 days after the RMP is accepted as
    complete, RMP should be made available to the
    public for review and comments.
  • A Public Notice will be published in the local
    newspaper
  • 45 days must be given for public to review and
    comment.

20
Public Notice
  • Public Notice must describe the RMP and state the
    location where it may be reviewed.
  • Be posted in a local newspaper for a period
    specified by the AA.
  • Must notify anyone that has specifically
    requested to be notified.

21
Example of Public Notice
  • Pursuant to the California Health and Safety
    Code, Division 20, Chapter 6.95, Section
    25535.2, facilities that handle regulated
    substances above certain thresholds are required
    to prepare risk management plans. The goal of a
    risk management program is to prevent chemical
    accidents that could cause harm to the public and
    the environment and to reduce the potential
    impact of accidental releases. The risk
    management plan contains an off-site consequence
    analysis that evaluates specific potential
    release scenarios including worst-case and
    alternative scenarios a history of accidental
    releases an integrated prevention program to
    manage risk an emergency response program and a
    management system to oversee the implementation
    of the risk management program. The risk
    management plans for the following facilities are
    available for public review and comment at the
    Stanislaus County Department of Environmental
    Resources, 3800 Cornucopia Way, Suite C, Modesto
    until March 17, 2000.
  •  List companies names and addresses.

22
Audits
  • RMP auditing is the chief administrative control
    through which implementation and enforcement are
    ensured. Audits are periodically performed on the
    RMP to review its adequacy and it can be
    accompanied by inspection.
  • When is determined that an audit is necessary
    then
  • Provide advance notice to the SS, SS need to make
    all the necessary documentation available for
    review and verification at the time of auditing.
  • Send the audit-inspection checklist via e-mail to
    the person in charge of the RMP implementation.

23
Audits
  • Based on the checklist, the AA will send a
    Preliminary determination of Necessary RMP
    Revisions, it shall include the basis for the
    revisions and include a timetable for the
    implementation.
  • The AA will expect to receive a written response
    within 90 days. Upon consultation with the SS,
    the AA will issue the final determination of
    necessary RMP revisions.
  • Failure to make the revisions within 30 days
    after the final determination was received, the
    SS is in violation of Article 3, Chapter 4.5, and
    Division 2 of 19CCR.

24
Inspection
  • Inspection are site visits to check the accuracy
    of the RMP data and implementation of the CalARP
    Program elements. Inspections are performed every
    3 years and are for the purpose of ensuring
    facility compliance with the CalARP Program. The
    following are some steps that need to be taken by
    the inspector
  • Set up an appointment with the facility at least
    5 days in advance.
  • Review the RMP prior to the inspection.
  • Complete the RMP Formal Evaluation Review, using
    the Evaluation Review checklist.
  • Upon arrival at the site, identify yourself and
    ask for the RMP coordinator or the designated
    alternate.

25
Inspection
  • Hold an opening conference, describe how the
    inspection will proceed.
  • The inspector should have a simple sketch of the
    process to be able to identify all equipment and
    operational controls listed in the RMP plan.
  • The inspector should ask any questions that may
    pertain to accidental release risk.
  • Note discrepancies on the CalARP/RMP inspection
    form or violations of the Uniform Fire Code and
    other applicable regulations.