Description:

Blue Lake: Refurbished secondary aeration system. Annual kWh savings = 3,000,000. Seneca: Refurbished secondary aeration system. kWh savings = 899,000 ... – PowerPoint PPT presentation

Number of Views:27
Avg rating:3.0/5.0
Slides: 29
Provided by: Good1
Category:

less

Transcript and Presenter's Notes

Title: A Clean Water Agency


1
Energy Program Update
Presented to the Environment CommitteeJanuary
27, 2009
Jason Willett, Chair, MCES Energy Team
A Clean Water Agency
2
Background 2006
  • Energy team created by MCES General Manager Bill
    Moore
  • Goal 15 percent energy reduction of purchased
    fossil fuel (2010 compared to 2006)

3
Status of Initiatives
  • Energy Conservation
  • Renewable Energy
  • Energy and Carbon Measurement
  • Energy Cost Savings and Financial Issues
  • Energy Collaborations

4
1. Energy Conservation
  • The cheapest energy is the energy you dont use.

5
Energy Conservation and Efficiency
  • Overview
  • Process efficiency, lighting redesign, and
    facility re-commissioning
  • Completed 26 energy-related studies identifying
  • 40 energy saving opportunities totaling 46
    million kWh (3 million/year) of those, MCES
    implemented 16 measures to date 23 million kWh
    (1.4 million/year)
  • 24 more studies planned in 2009

6
Energy Conservation and Efficiency
  • Completed work
  • Metro Aeration study
  • Annual kWh savings 6,700,000
  • Metro Enhanced maintenance in aeration process
  • Annual kWh savings 4,000,000

7
Energy Conservation and Efficiency
  • Completed work
  • Metro Odor control energy improvement
  • Annual kWh savings 688,000
  • Metro Instrument air compressor modifications
  • Annual kWh savings 340,000

8
Energy Conservation and Efficiency
  • Completed work
  • Blue Lake Refurbished secondary aeration system
  • Annual kWh savings 3,000,000
  • Seneca Refurbished secondary aeration system
  • kWh savings 899,000
  • Facility re-commissioning on eight facilities
  • Annual kWh savings 250,000

9
Energy Conservation and Efficiency
  • In process work
  • Metro Tunnel lighting redesign
  • 2008 design 2009 construction

10
Energy Conservation and Efficiency
  • In process work
  • Metro Liquids Business Unit Operating Changes
  • 50 percent reduction sludge pump run hours
  • 8,000 annual hour reduction in grit collector
    drives
  • Less double pumping of sludge
  • Annual kWh savings 3,000,000
  • Metro Steam Trap Program
  • 15 completed in 2008 remainder scheduled for
    2009

11
Energy Conservation and Efficiency
  • In process work
  • Rosemount Decommissioning
  • Annual kWh savings 1,500,000 (net)

Rosemount Plant, 2008
12
Energy Conservation and Efficiency
  • In process work
  • Energy design standards for capital projects
  • Employee energy campaign
  • 1,800 computers reconfigured to go into low
    energy state after inactivity
  • Printer default is two-sided copies
  • Employees to shut down computers and electronics
    when not in use

13
Energy Conservation and Efficiency
  • Identified additional energy efficient
    improvements
  • Seneca New energy efficient HVAC system
  • Blue Lake New energy efficient HVAC system
  • Lift Station L-35 Energy efficient lighting
  • Lift Stations L-74, L-75 Efficient motors

14
2. Renewable Energy
  • Renewable energy can make us energy-independent
    and energy-secure.

15
RD and Renewable Energy
  • Completed RE
  • Fluidized Bed Incinerators/ cogeneration of heat
    and electricity

16
RD and Renewable Energy
  • Completed RE
  • Eagles Point Thermal energy recovery from
    effluent

17
RD and Renewable Energy
  • In process RE
  • Empire Micro-turbine demo project

18
RD and Renewable Energy
  • In process RE
  • Blue Lake Design of liquids process change to
    anerobic digestion and substitution of produced
    biogas for purchased natural gas
  • Metro Heat Pump
  • 2008 Study on energy savings opportunities from
    heat pump and heat recovery technologies
  • 2009 Initiating installation of non-condensing
    turbine/generator
  • Seneca New scrubber heat exchanger

19
RD and Renewable Energy
  • Identified RE possibilities
  • Algae RD
  • Bio-diesel from brown grease

20
RD and Renewable Energy
  • Identified RE possibilities
  • Metropolitan CountiesEnergy Coalition(MCEC)
    Wind Initiative
  • Xcel Energy and MCES Renewable Collaboration,
    possible solar farm at Blue Lake

21
3. Energy and Carbon Measurement
  • You cant manage what you cant measure.

22
Energy and Carbon Management
  • In process work
  • Energy database
  • EPA and Energy Star Program
  • GHG Emissions Research
  • The Climate Registry (TCR) reporting

23
4. Energy Cost Savings and Financial Issues
  • MCES spent 17 million on energy in 2008.

24
Energy Cost Savings and Financial Issues
  • Completed work
  • Carbon costing for alternatives analysis
  • Solar facilities economic analysis
  • Rebates earned in 2008 225,000
  • Peak Control Agreement savings in 2008 350,000

25
Energy Cost Savings and Financial Issues
  • In process work
  • Lift station tariff analysis and charges
  • Xcel Energy rate case
  • Monetization of emission reduction projects
  • FBI turbine accreditation and penalties
  • Peak Control Agreementsreview

26
5. Energy Collaborations
27
Energy Collaborations
  • University of Minnesota (Institute for Renewable
    Energy Environment)
  • Xcel Energy (Process Efficiency Program RE)
  • Metro Energy Policy Coalition (Counties)
  • Inter-agency Energy Environment Team
  • Chamber of Commerce

28
Summary
  • Conservation
  • 66 of goal complete
  • Over 100 of opportunities identified
  • More studies underway
  • Renewable energy
  • Additional possibilities being investigated
  • Financial impact

1.4 million/year conserved .3 rebates
received (2008) .3 peak control savings
(2008) 2.0 million