Title: Status Report on Bonding at Catania
1Status Report on Bonding at Catania
- Salvatore Costa
- University and INFN Catania
2Real Module Bonding
- The first real module bonded in Catania was
bonded early August 2002, just before our clean
room was shut down for transfer to new Department
Building. - It is a TIB module with two 512-strip old CSEM
sensors. - Loop height of 150 (mm or .1 mil ?) was used (too
low for current thinking).
3Test of Real Module Bonded
- Could not read module in Catania. Being the
CMS-like system setup in Catania also relatively
recent, we werent sure whether problem had been
introduced by Bonding or was in Test system.
Brought Module to Florence were a test setup was
in operation. - Enrico Scarlini (who our technician Nunzio
Giudice learns from, besides learning from Paolo
Tempesta) judged all readout bonds good and
correctly done (although with insufficient loop
height for the current prescription), and all
bias bonds also correct except for one from the
bias ring to a HV capacitor pad. - The bad bias bond had to be redone and after
redoing the Module was successfully read in
Florence.
4The Bad Bias Bonds
5Explanation from our Florence colleagues
- Due to insufficient loop height, a likely flexing
of the Module may have caused the bond wire to
touch the p-implanted line, which thus went to
same voltage as the back of the Si, i.e. HV. This
effectively shorted ground and back together. - So, as soon as powered, Module drew maximum
current. - High current burnt tiny contact surface between
wire and silicon and spawned oxide formation on
the bond foot. - This prevented further correct biasing of the
Module even though after moving the Module
around, wire would no longer touch p-implanted
line.
6Test Results before Bonding
7Test Results after Bonding
8Cold Boxes
- Catania is in fact producing Cold Boxes for all
INFN bonding Centers - Boxes produced and distributed 4 (at Catania,
Bari, Firenze, Pisa) - Boxes under construction 2 (for
Padova and Torino)
9Test Systems
- CMS-like is fully operational, as has been for a
while already - ARC installed but
- Struggled for some time to make it work until a
hardware problem was found in a card - Problem repaired, ARC has been tested to the
extent that this is possible without connecting
it to anything internally working - Next week I will organize a real Module readout
with ARC
10 11DataBase Interface Update
- Salvatore Costa
- University and INFN Catania
12Interface Dev Status
- Little progress since last Mtg, Oct 22, due to
teaching duties - Will resume working on it from Dec 10 and still
hope to deliver full, talking to TrackerDB, v.
1.0 around Christmas - A.Profeti has started inserting from Pisa Pull
Test data even as v.0.2 does not yet transmit
such data to TrackerDB. Ive begun saving and
regualarly backing up evry night inserted data
for later shipping to TrackerDB - Played with Relay Appl to query TrackerDB from
within my Perl scripts and it woks indeed - Got some suggestions on rearrangement of present
variables among Tables - Still waiting for written description of some
more useful variables to add
13 Center DB Readiness
Center DB Responsible Form Defaults
Aachen Wolfgang Braunschweig MISSING
Bari Valeria Radicci OK
Catania Salvatore Costa OK
CERN Alan Honma OK
FNAL Bill Kahl OK
Firenze Simone Paoletti OK
Karlsruhe Hans-Jürgen Simonis OK
Padova Maurizio Loreti IN PROGRESS
Pisa Andrey Starodoumov IN PROGRESS
Santa Barbara Bill Kahl OK
Strasbourg Pierre Juillot OK
Torino Ernesto Migliore OK
Vienna Thomas Bergauer OK
Zurigo Klaus Freudenreich OK