2Key Policy Issues
- Vision, common values/goals.
- Coordinating land uses added capacity.
- Environmental stewardship.
- Goods movement, better access.
- Evacuation, safety.
- Transit expansion.
- Financial Constraint.
32035 RTP Vision Statement
Our community will have a better quality of life
through improved mobility and a healthier
environment.
4EHR Common Values/Goals
- Better mobility, less congestion costs.
- Reduced rate of growth, VMT, VHT, delay,
congestion index, time/ fuel savings. - Easier access to jobs, homes services.
- Accessibility, user benefits.
- More transit.
- Increased transit mode share, riders, PMT, PHT.
- Coordinated transportation and land use.
- More livable centers, smart streets.
- Best practices, incentives.
- Healthier Environment.
- Better air quality, more green space.
5Coordinating land use and added capacity.
- Mixed use developments, livable centers.
- Neighborhood preservation.
- Smart streets.
6Environmental Stewardship
- More than considerations.
- Proactive measures.
- Wetlands banking.
- Flood plain management.
- Scenario D for planning purposes.
7Goods Movement
- Improved land side access.
- Strategic corridors prioritized.
- Seaports, airports, terminals.
8Evacuation, Safety
- Prioritize evacuation routes- choke points.
- Statewide coordination TxDOT, MPOs.
- Highlight safety/mobility improvements.
9Transit Expansion
- Beyond METRO Solutions-placeholders.
- Regional commuter rail.
- Intercity, interstate rail corridors.
- Regional Coordination-planning.
- Equity- Environmental Justice
10Financial Constraint
- Year of expenditure dollars.
- Inflation rate 4 year.
- Excess toll revenues.
- Right of way costs-to be included.
- Project scope changes.
- METRO cash flow ?
112035 RTP Financial Plan
Development Issues
- Excess toll revenues, used for non-toll
transportation projects. - Revenue forecasts include innovative financing
strategies. - Congestion pricing, managed lanes revenues.
122008-2011Transportation Improvement
Program(TIP) Update
13Linking the TIP and the RTP
- Coordinated Development TIP Programs
- Program 1 - System Development, Preservation
- Program 2 - Demand Management, Air Quality
- Program 3 - Operations Management, Intersection
and Bottleneck Improvements - Program 4 - Transit, Livable Centers
-
14Steps in the Process
SEPT 06 JAN 07 Call for projects and Staff
Rankings
FEB- MARTIP Subcommittee review approve draft
APRTAC andTPC Review Draft
We are here
MAYPublic comment Period
JUNETPC APPROVAL
15Candidate Projects
- s Requested (M)
- Program 1 725
- Program 2 166
- Program 3 624
- Program 4 125
- Submitted
- Program 1 91
- Program 2 37
- Program 3 62
- Program 4 18
Total requested 1.6 billion.
16Funding Available TIP 2010-11
- Estimated Available
- Federal 257 M
- STP 124.8 M
- CMAQ 132 M
- Program 4 120 M
- Requested
- Federal 1.6 Billion
- STP 1.1 B
- CMAQ 496 M
- Transit Formula ?
Does not include all Program 2 since bike/ped is
not summarized.
172008-2011 TIP
Development Issues.
- Staff recommendations being considered
- Need to coordinate investments.
- Strategic corridors, subareas, livable centers.
- Reserve 1 funds for Safety and Hurricane
Evacuation. - Set aside.
- Fund AQ Programs (Commute Solutions, Clean
Vehicles). - Outreach included.
182008-2011 TIP
Development Issues (contd).
- Consider benefits of incremental investments.
- Mega projects.
- Clarify uses of transit formula funds.
- Augmented with STP, CMAQ fund requests.
- STP used in Houston UZA
- Discretionary outside UZA.
19UPCOMING DATES
- February March
- TIP Subcommittee, TAC/TPC Previews.
- April
- Drafts Approved by TAC and TPC-Outreach
- May
- Public Comment Period
- June
- RTP/TIP Approval by TPC
20For More Information
- www.h-gac.com/transportation
- Email
- transportation.comments_at_h-gac.com