Title: Cascade diagrams and resource histograms
1Cascade diagrams and resource histograms
The table below shows the tasks involved in a
project, with their durations, immediate
predecessors and number of workers required.
How many workers are needed if all activities are
scheduled to start as early as possible?
2Cascade diagrams and resource histograms
Initially, put all tasks at their earliest
possible time.
A
(2)
B
(1)
A, B and C can all start at time zero.
C
(2)
D
E
F
G
Days
2
4
6
8
10
12
14
16
3Cascade diagrams and resource histograms
D must start after both A and B have finished
A
(2)
B
(1)
C
(2)
D
(2)
E
F
G
Days
2
4
6
8
10
12
14
16
4Cascade diagrams and resource histograms
E and F must both start after C has finished
A
(2)
B
(1)
C
(2)
D
(2)
E
(2)
F
(2)
G
Days
2
4
6
8
10
12
14
16
5Cascade diagrams and resource histograms
G must start after both D and E have finished
A
(2)
B
(1)
C
(2)
D
(2)
E
(2)
F
(2)
G
(2)
Days
2
4
6
8
10
12
14
16
6Cascade diagrams and resource histograms
A
You can now use the cascade diagram to construct
a resource histogram showing the number of
workers needed on each day
(2)
B
(1)
C
(2)
D
(2)
E
(2)
F
(2)
G
(2)
Days
2
4
6
8
10
12
14
16
This shows that 6 workers are required
7Cascade diagrams and resource histograms
Problem 1
Only four workers are available. Is it possible
to complete the project in the same amount of
time?
8Cascade diagrams and resource histograms
A
We need to move some tasks so that only four
workers are needed at any given time.
(2)
B
C
(2)
Task B can be moved so that it starts after A has
finished. This means that D must also move.
D
E
(2)
F
(2)
G
(2)
Days
2
4
6
8
10
12
14
16
6
4
2
2
4
6
8
10
12
14
16
9Cascade diagrams and resource histograms
A
The resource histogram is changed to show this
new arrangement.
(2)
B
C
(2)
D
E
(2)
F
(2)
G
(2)
Days
2
4
6
8
10
12
14
16
6
6 workers are still needed
4
2
2
4
6
8
10
12
14
16
10Cascade diagrams and resource histograms
A
Task F can be moved forward to start after D
finishes.
(2)
B
(1)
C
(2)
D
(2)
E
(2)
F
(2)
G
(2)
Days
2
4
6
8
10
12
14
16
6
4
2
2
4
6
8
10
12
14
16
11Cascade diagrams and resource histograms
A
The resource histogram changes again.
(2)
B
(1)
C
(2)
D
(2)
E
(2)
F
(2)
G
(2)
Days
2
4
6
8
10
12
14
16
6
Now only 4 workers are needed.
4
2
2
4
6
8
10
12
14
16
12Cascade diagrams and resource histograms
Problem 2
Only three workers are now available. However,
both tasks D and F can be done by one person, but
taking double the amount of time. What is the
shortest possible time in which the project can
be completed?
13Cascade diagrams and resource histograms
A
This is the new cascade diagram, with D and F
done by one person taking twice as long.
(2)
B
(1)
C
(2)
D
(1)
E
(2)
F
(1)
G
(2)
Days
2
4
6
8
10
12
14
16
18
14Cascade diagrams and resource histograms
A
A new resource histogram is needed.
(2)
B
(1)
C
(2)
D
(1)
E
(2)
F
(1)
G
(2)
Days
2
4
6
8
10
12
14
16
18
15Cascade diagrams and resource histograms
A
Since BDG is now the critical path, it is
probably best to try moving C. This means that E
and F must also move.
(2)
B
(1)
C
D
(1)
E
F
G
(2)
Days
2
4
6
8
10
12
14
16
18
16Cascade diagrams and resource histograms
A
The resource histogram changes
B
C
D
E
F
G
Days
2
4
6
8
10
12
14
16
18
17Cascade diagrams and resource histograms
A
Another change is needed. F is not required for
any other task, so it can be moved later.
(2)
B
(1)
C
(2)
D
(1)
E
(2)
F
(1)
G
(2)
Days
2
4
6
8
10
12
14
16
18
18Cascade diagrams and resource histograms
A
The resource histogram changes again
(2)
B
and this time it shows that the project can be
completed using 3 people in 19 days.
(1)
C
(2)
D
(1)
E
(2)
F
(1)
G
(2)
Days
2
4
6
8
10
12
14
16
18