Chapter 7 Fine Tuning Task Details - PowerPoint PPT Presentation

1 / 16
About This Presentation
Title:

Chapter 7 Fine Tuning Task Details

Description:

Select the Predecessors tab and adjust dependency type in the Type column. ... Select the Predecessors tab and adjust Lead or Lag time in the LAG column. ... – PowerPoint PPT presentation

Number of Views:46
Avg rating:3.0/5.0
Slides: 17
Provided by: conest
Category:

less

Transcript and Presenter's Notes

Title: Chapter 7 Fine Tuning Task Details


1
Chapter 7Fine Tuning Task Details
  • What will we do in this chapter?
  • Adjust task relationships, look at lead lag
    time.
  • Learn about task constraints and how to apply
    them.
  • Look at the critical path.
  • Interrupt work on a task by splitting it.
  • Create a calendar for a specific task.

2
Chapter 7Fine Tuning Task Details
  • And we will do more.
  • Examine the different task types and how Project
    schedules them.
  • Record deadlines for tasks.
  • Enter a fixed cost and specify how it should
    accrue.
  • Set up recurring tasks.

3
Adjusting Task RelationshipsDependencies -
General
  • Real vs preferred task dependencies. To reduce
    project duration consider the following
  • Do linked tasks have to be linked?
  • Do FS tasks have to be FS or can they be SS or
    FF?

4
Adjusting Task RelationshipsDependencies How
to
  • To adjust task dependencies
  • Select the successor task in any task sheet view
    (Gantt chart etc.)
  • Go to the Task Information dialog box.
  • Select the Predecessors tab and adjust dependency
    type in the Type column.

5
Adjusting Task RelationshipsLead and Lag Time -
General
  • FS tasks can be overlapped by adding lead time or
    delayed by adding lag time, ex
  • Lead construct walls, plaster walls.
  • Lag order equipment, install equipment.

6
Adjusting Task RelationshipsLead and Lag Time
How to
  • To define Lead Lag time
  • Select the successor task in any task sheet view
    (Gantt chart etc.)
  • Go to the Task Information dialog box.
  • Select the Predecessors tab and adjust Lead or
    Lag time in the LAG column.
  • Lead is negative, lag is positive.

7
Task Constraints
  • A constraint is a restriction placed on the start
    or finish date of a task.
  • Controls the degree of flexibility that Project
    has in rescheduling.
  • There are three categories of constraints
    Flexible, Semi-flexible and Inflexible.

8
Task Constraints continued
  • Flexible constraints give Project the most
    flexibility in rescheduling. These should be
    used whenever possible. These are the default.
  • Semi-flexible constraints limit rescheduling
    within date specified.
  • Inflexible constraints totally prevent any
    rescheduling of a task..

9
Task Constraints continued
  • In case of scheduling conflict, constraint takes
    precedence.
  • BEWARE entering a task start or finish date
    applies a semi-flexible constraint to the task.
  • Set task constraints in the Task Information
    dialog box.
  • To remove a constraint, set it to ASAP.

10
Critical Path
  • The critical path is the series of tasks that
    will push out the projects end date if delayed.
  • Free slack is the amount of time a task can be
    delayed before it delays another task.
  • Total slack is the amount of time a task can be
    delayed before it delays project end date.
  • By default a task is critical if it has zero
    slack, this can be changed in Tools -gt Options -gt
    Calculation.
  • View critical path on Detailed Gantt chart.

11
Interrupting Work on a Task
  • If work on a task has to stop for some reason,
    the task can be split.
  • Duration of a split task does not include the
    time of the split unless the task has an Elapsed
    Duration or is Fixed Duration.
  • If duration of a split task changes, it is the
    last segment that changes.

12
Task Calendar
  • A particular task may have to be scheduled
    differently from project calendar working times,
    ex. Task being performed by a machine that runs
    24 hours a day, or a task that has to be done on
    the weekend.
  • Consider resource calendars when applying task
    calendar to a task.
  • Tools -gt Change Working Time to create new
    calendar.
  • Task Info dialog box, Advanced tab to apply new
    calendar to task.

13
Task Types
  • Change task type in Task Info dialog box,
    Advanced tab.
  • See chart on p. 156 of text for values
    recalculated by Project for different task types.
  • Task Type comes into play whenever a tasks work,
    duration or units are edited.

14
Deadline Dates
  • A deadline is a date value entered for a task
    indicating when task must be done.
  • A deadline does not constrain a task.
  • Therefore, if a task must be done by a certain
    date, consider entering a deadline instead of a
    constraint.
  • Task Info dialog box, Advanced tab

15
Fixed Costs
  • A Fixed Cost is an amount of money budgeted for a
    task independent of resources or duration.
  • Fixed Costs can accrue at the start or end of a
    task, or they can be prorated.
  • Enter on any task sheet view
  • Table Entry -gt Cost

16
Recurring Tasks
  • Used for repetitive tasks such as project status
    meetings.
  • Recurring tasks are created with
  • Start no Earlier Than constraints
  • No task relationships
  • Effort driven scheduling turned off
  • Enter on any task sheet view
  • Insert -gt Recurring task
Write a Comment
User Comments (0)
About PowerShow.com