Title: BUILD OPERATE TRANSFER
1 CONSTRUCTION PLANNING SCHEDULING
ARE 413 CONSTRUCTION MANAGEMENT Chapter 5
/Part 2 By MOHAMMED JALALUDDIN LECTURER CONSTRUCT
ION ENGINEERING MANAGEMENT DEPT
2Presentation Outline
- Introduction to Construction Planning
Scheduling - Definitions
- Planning versus Scheduling
- why / when Construction scheduling
- History of scheduling
- Types of scheduling tools/techniques
- Bar Charts
- Advantages
- Disadvantages
- Examples
- Critical Path Method ( CPM)
3Objectives of Class
- To introduce and define construction planning
scheduling - To present different types of scheduling
tools/techniques - To demonstrate purpose and usage of Bar charts,
CPM -
4 Background
- Three factors shape every project PROJECT
TRIANGLE - MONEY The project budget, based on the cost of
the resources the people, equipment, and
materials required to do the tasks. - TIME The time to complete the project reflected
in your project - schedule.
- QUALITY The quality of construction and
finished product. - Adjusting one of these elements affects the other
two. While all three elements are important,
typically one will have the most influence on
your project. In this chapter ,we will be
discussing the control of Time.
5 Definition of Planning
- Project planning is the process of identifying
all the activities necessary to successfully
complete the project - Failure to plan leads to excessive labor cost,
equipment waiting time, delays, waiting for
materials, lack of coordination, and management
inability to react to unexpected events (weather,
equipment breakdowns, shortages) - Planning - Breakdown of project into work items
(activities), define and describe activities to
be performed
6(No Transcript)
7(No Transcript)
8 Definition of Scheduling
- Schedules establish the start ,duration and
completion date of a project or task - Scheduling is the process of listing a number of
duties or events in the sequence that they will
occur - It is a timetable which formulates the activities
that must be accomplished to reach a certain goal
or objective - The timing and sequence of tasks within a
project .A schedule consists of many tasks ,tasks
dependencies and time oriented project
information.
9 Why Construction scheduling ?
- One of the first question an owner or project
manager wants answered is when can the project
be completed ? - Schedules identify all the tasks required to be
completed on a project, determine how long each
will take and place them in logical order. - Schedules establish the start ,duration and
completion date of a project or task - Schedules let people and organizations know in
advance when to expect a certain action to take
place. - Schedules start date determines when goods and
services need to be brought to the job site, when
a work force needs to be mobilized and when
equipment rental begins
10 Why Construction scheduling ? (contd..)
- Consider for example
- For instance ,a large crane can rent from more
than 2500 per week .So if the duration of the
project is not figured closely contractors can
quickly consume in rental
11 When to Schedule ?
- Schedules are useful during all the phases of
project. - Preconstruction Stage
- Scheduling in the preconstruction stage is
important to provide the owner with necessary
information to plan and coordinate properly the
entire design and construction process. - Viewed as an opportunity to design and build the
project on paper prior to the actual
construction - This is the time that project team may decide to
order key long lead purchase item such as
structural steel ,elevators or compressors.
12 When to Schedule ?
- Schedules are useful during all the phases of
project. - Construction Stage
- Schedules are essential to coordination of the
day- to day activities of project - As project progresses ,delays inevitably occur
due to bad weather ,equipment failure ,strikes
etc. - schedules record the actual activities at the
site on day- to day basis and reschedule.
13Planning Versus Scheduling
- A plan shows the activities and their logic
relationships. The activities in a plan do not
have specific start and end dates. - A schedule establishes the specific start and
end dates for the activities. It also establishes
the total project duration. A schedule determines
what resources are needed when for how long for
which activity.
14Scheduling Methods
- Barcharts
- CPM (Critical Path Method)
- PERT (Monte Carlo Simulation)
- LOB (Line of Balance)
- Computer Softwares
- Primavera ( www.primavera.com)
- MS Project ( www.microsoft.com )
15History of Scheduling
- In 1956 the E.I. Du Pont de nemours company
developed a Critical Path Method (CPM) schedule
for a 10 million chemical plant in Louisville,
Kentucky - U.S navy used a Performance Evaluation and
review technique (PERT) network schedule to mange
the development of the Polaris missile - CPM/ PERT were used U.S crops of engineers,
NASA, General electric , Apollo program - Today because of recent advances in computer
hardware and software scheduling are much widely
used by designers and contractors etc. - Scheduling Software
- Primavera ( www.primavera.com)
- MS Project ( www.microsoft.com )
16Types of scheduling tools/techniques
- 2 most common scheduling tools/techniques are
- Bar charts
- Critical Path method (CPM)
- Depending on the user , the schedule can take
different forms .For instance Owner of a 500
million high rise is interested in when the
project is due for completion .Bar charts can
provide this type of information. - Field superintendent or construction manager is
responsible for actual details of the project.
(e.g. delivery of key materials, dry walls) CPM
can provide the necessary details.
17Bar / Gantt Chart
- Developed by Henry Gantt
- Each activity is represented by a bar
- Bar shows start/finish times
- Progress is also shown
- Example
18Typical Bar / Gantt Chart
19Typical Bar / Gantt Chart
20Typical Bar / Gantt Chart
21Advantages of Bar / Gantt Chart
- Simple easy to understand
- Visually effective
- Shows total project in compact form
- Shows plan versus progress
- Can model any activity relationship
22Limitations of Bar / Gantt Chart
- Does not how effect of change on initial plan (
Updating not possible) - Does not integrate cost or resources with
schedule - Does not show interdependences of all activities
23(No Transcript)
24Summary Construction Project Scheduling
- To plan and schedule a construction project
uncertainty and complexity. - A construction project
- involves many parties and people owner,
contractor, engineer, suppliers and
subcontractors. - requires resources money, materials, equipment,
and labors. - takes time, months or years.
- In summary, to plan and schedule a construction
project, we need decide - what to do?
- how to do?
- who will do?
- when will do?
- How much will it cost and how long will it take?