Pitfalls - PowerPoint PPT Presentation

1 / 48
About This Presentation
Title:

Pitfalls

Description:

Identify other organizations within your agency or other State agencies that ... Technical appraisal outweighs importance of cost; 14 ... – PowerPoint PPT presentation

Number of Views:42
Avg rating:3.0/5.0
Slides: 49
Provided by: nys7
Category:

less

Transcript and Presenter's Notes

Title: Pitfalls


1
  • Pitfalls
  • Possible Solutions/Preventive Measures

2
  • Pitfall
  • Agency identifies a need for contractual services.

3
  • Solution or Preventive Measure
  • Identify other organizations within your agency
    or other State agencies that have recently faced
    a similar need and how that organization handled
    their procurement.
  • What procurement vehicle did they use?
  • What method of award?
  • What problems did they encounter in procurement
    or managing performance?

4
  • Pitfall
  • Agency does not have a framework for a
    solution
  • It is unknown what products or services the
    vendor community has available
  • Solution or Preventive Measure
  • Survey current providers through a Request for
    Information (RFI).

5
When an RFI might be used
  • If the agency does not know what product, service
    or technology the vendor community has available,
    it may issue a Request For Information (RFI) to
    assess the availability, types, and options of
    goods and services and to help identify potential
    suppliers.

6
Request For Information (RFI)
  • The agency prepares a document which
  • Provides a preliminary description of the program
    objectives and goals, and
  • Solicits input from the vendor community as to
    the availability of products, services and/or
    technology to meet their needs.

7
RFI Mandatory Requirements
  • Notification of the RFI must be published in the
    Contract Reporter (Section VII, 14, Procurement
    Guidelines)
  • The RFI is mailed to all potential offerors known
    by the agency at the time of mailing (Section
    VII, 14, Procurement Guidelines)

8
RFI Other Requirements
  • An open meeting to solicit additional information
    is the recommended approach. All offerors
    responding to the RFI must be notified in writing
    of questions submitted and kept informed of any
    open meetings. (Mandatory Section VII, 14
    Procurement Guidelines)
  • No award may be made under the RFI process.

9
  • Pitfall
  • Agency lacks adequate resources for managing the
    project.
  • Solution or Preventive Measure
  • Seek outside assistance by identifying
    organizations within your agency or other State
    agencies that may have qualified staff.
  • Determine if you need to procure the services of
    a project manager to accomplish your project
    goals.

10
  • Pitfall
  • Agency incurs large cost overruns during project
  • Solution or Preventive Measure
  • At outset of the procurement process, agency
    should perform a detailed cost analysis,
    including staff training time, equipment needs,
    contractual costs, set-aside for contingencies
    (unexpected events), etc.

11
  • Pitfall
  • All available procurement vehicles were not
    evaluated in developing bid documents.
  • Solution or Preventive Measure
  • Review all procurement vehicles to insure the
    correct fit. Consider Preferred Sources, OGS
    centralized contracts, OGS backdrop contracts,
    discretionary purchasing, IFBs, RFPs, single or
    sole source.

12
  • Pitfall
  • An RFP was used when an IFB would have fit the
    scope of services, causing
  • An unnecessary administrative burden
  • Increase to processing time (inception to
    commencement of work)
  • Extra cost

13
  • Solution or Preventive Measure
  • An IFB is the best method if
  • Exact specifications are known
  • Price is very important
  • An RFP is the best method if
  • Exact specifications are not known
  • A highly complex technical solution is needed
  • Technical appraisal outweighs importance of cost

14
  • Types of services which should be procured by
    these methods
  • IFB Commodity purchases janitorial guard
    duty auditing.
  • RFP Modernization of an existing system (Human
    Resources, Payroll, Financial Management, etc.)
    Development of a new system (Electronic Benefits
    Transfer-EBT, Replacement Medicaid System-RMS,
    Connections, etc.)

15
  • Pitfall
  • An old RFP was used for the current procurement
    which was not in accordance with all applicable
    State statutes and procedures.
  • Solution or Preventive Measure
  • Review the old RFP to insure that it complies
    with all applicable State statutes and procedures
    and update it, if necessary.

16
  • Pitfall
  • Electronic payments process not used for payments
    to vendors

17
  • Solution or Preventive Measure
  • Payee completes an Electronic Payments
    Authorization Form to enroll in this program.
  • Benefits
  • Faster access to cash by your vendors
  • Direct deposit access within 24 hours
  • Less paperwork to process for New York State
  • OSC Payment Bureaus volume
  • 17.5 million transactions annually
  • 15,000 daily payments to vendors, municipalities
    and employees
  • Vendor receives e-mail alerts when monies are
    ready to be deposited into their accounts
  • Vendors receive one electronic payment for all
    their invoices for that day

18
  • Solution or Preventive Measure
  • For further information, contact OSCs Bureau of
    Accounting Operations at (518) 474-4032 or
    e-mail epunit_at_osc.state.ny.us
  • Visit OSC website at http//www.osc.state.ny.us
  • See Accounting Bulletin A-474

19
  • Pitfall
  • A cost of living increase for a renewal year was
    negotiated but the original RFP/IFB and contract
    did not allow for an escalation (no contract
    escalation clause).
  • Solution or Preventive Measure
  • The RFP/IFB or original contract must have an
    escalation clause to allow cost of living
    adjustments.
  • The amendment would be rejected and the agency
    would submit a reduced amendment amount.

20
  • Pitfall
  • Contract performance did not produce a meaningful
    result.
  • Solution or Preventive Measure
  • RFP/IFB/Contract should, wherever possible, be
    for specific outcomes (deliverables).
  • RFP/IFB/Contract should have identifiable
    measures of performance.
  • Require liquidated damages, a letter of credit or
    performance bond.

21
Liquidated Damages
  • Examples
  • Direct Damages
  • Termination for cause is exercised and agency is
    forced to re-bid. Any additional contracts
    incurred costs above original contracted amount
    constitute direct damages and the terminated
    vendor should be held responsible.
  • Specific dollar limits as to liability must be
    stated in the RFP/IFB contract.

22
Liquidated Damages
  • Consequential Damages
  • Vendors inability to deliver contract
    deliverables in accordance with specifications
    and timeliness, i.e. non-conformance, which
    causes disruption to agency programs, loss of
    Federal or other reimbursement funds or create
    other negative impacts should be measured and
    assessed against the vendor.
  • Up-time of systems, processing of claims,
    inoperable systems, etc. are a few examples of
    what can lead to an agency incurring
    consequential damages.

23
  • Pitfall
  • Agency develops an unclear specification and/or
    provides insufficient bidding information this
    can result in an insufficient number of firms
    bidding or a bid protest, etc.
  • Solution or Preventive Measure
  • Develop clear, detailed specifications allowing
    bidders to submit responsive proposals.
  • If needed, seek outside assistance
  • Identify other organizations within your agency
    or other State agencies for qualified staff
  • Solicit outside consultant services
  • Section 163.A reminder

24
  • Pitfall
  • Agency writes restrictive specifications
    resulting in a lack of adequate competition,
    complaints or protests, etc.
  • Solution or Preventive Measure
  • Restrictive specifications are a reason for
    rejection and rebid of a contract.

25
  • Pitfall
  • Did not establish criteria prior to the initial
    receipt of bids (lock box), including the use
    of a finalist slate, if applicable.
  • Solution or Preventive Measure
  • Review Section 163.7 of NYS Finance Law.
  • Contract will be rejected.

26
  • Pitfall
  • A percentage, rather than a number, is used to
    determine who qualifies for the finalist slate
    this might result in an insufficient number of
    qualifying bidders.
  • For example, RFP states all bidders within 10
    percent of highest composite score qualify for
    the finalist slate. Only one bidder meets this
    standard. The RFP allows for interviews for
    finalists only. What if the only qualifying firm
    performs poorly at the interview?

27
  • Solution or Preventive Measure
  • Use a number, for example, the top three highest
    composite scores will qualify for the finalist
    slate this insures adequate competition in the
    final round.

28
  • Pitfall
  • Did not publish relative weights in bid document
    (technical vs. cost).
  • Solution or Preventive Measure
  • Review Section 163.9.b of NYS Finance Law.
  • The contract will be rejected.

29
  • Pitfall
  • Price offered should be reviewed objectively.
    The content or level of effort should be
    considered when evaluating the technical
    proposals.
  • Solution or Preventive Measure
  • Technical proposal should include a manning
    schedule to help determine if the proposed level
    of effort is realistic in regard to achieving the
    end work product.

30
  • Pitfall
  • Multiple award not in RFP/IFB or without a
    defined selection procedure as to how the work
    will be distributed
  • Solution or Preventive Measure
  • Review Section 163.10.c of NYS Finance Law.
  • You must define the up to number of firms that
    can be awarded a contract.
  • You must define your selection procedure for the
    actual work (task orders etc.)

31
  • Pitfall
  • Points assigned to cost did not represent a
    meaningful worth.
  • Solution or Preventive Measure
  • Review intent of State Finance Law, Article 11
    (particularly Sections 163.1.j, 163.7 and
    163.9.b) and Procurement Guidelines.

32
  • Pitfall
  • When using the formula in the Procurement
    Guidelines, a high dollar bid may skew the points
    assigned to the mid-range bids.
  • Solution or Preventive Measure
  • Use the following recommended formula to provide
    a more balanced assignment of cost points.

33
Recommended Cost Formula
  • Low bid / bid being evaluated x maximum points
    for cost cost score

34
  • Pitfall
  • Agency did not respond to a vendors request for
    debriefing did not notify unsuccessful vendors
    in a timely manner.
  • Solution or Preventive Measure
  • Review Procurement Guidelines, Section VII, page
    6, number 11 page 45, number 2.
  • Debriefing is mandatory.

35
  • Pitfall
  • The agencys application of evaluation scoring
    differs from their RFP/IFB/evaluation instrument.
  • Solution or Preventive Measure
  • Review State Finance Law, Article 11, and the
    Procurement Guidelines. A rebid of the services
    may be required.
  • Develop the RFP and evaluation instrument at the
    same time.

36
  • Pitfall
  • Award made to a non-responsive bidder, i.e.,
    vendor did not meet specification requirements or
    submit proper forms, etc.
  • Solution or Preventive Measure
  • This is not acceptable and is subject to
    rejection and rebid of the services.

37
Example Non-Responsive Bidder
  • The RFP/IFB requires unlimited liability on the
    part of the vendor. During negotiation with the
    awarded vendor, the agency negotiates a lesser
    liability, creating a material change to the
    original procurement.
  • Agency should carefully consider and weigh the
    importance of its RFP/IFB requirements.

38
Example Non-Responsive Bidder
  • For instance, when requiring unlimited liability,
    the agency should carefully weigh
  • Reasonableness of this requirement
  • Necessity of this requirement
  • Are there a sufficient number of vendors who will
    bid on the specific services being procured if
    this requirement is present?

39
Example Non-Responsive Bidder
  • Any material change(s) to a procurement document
    (RFP/IFB) may prejudice other offerors as well as
    potential offerors who did not submit a bid.
    These awards are subject to rejection and a
    re-bid of the services.

40
  • Pitfall
  • Agency awards a reduced scope of work from
    originally requested in the RFP/IFB.
  • Solution or Preventive Measure
  • This is not acceptable unless it is a minor
    reduction. The agency must be able to defend
    that any bidder or potential bidder was not
    prejudiced.

41
  • Pitfall
  • Agency submits a contract whose start date is
    prior to OSC review and approval process

42
  • Solution or Preventive Measure
  • Refer to Comptrollers bulletin G-195 for
    guidance and to State Finance Law, section 112.
  • May cause vendor to not receive payments for any
    services rendered prior to OSC approval date.
  • Sometimes approving a late contract results in an
    award that may not achieve the optimum result.
  • Alternative approaches might have been introduced
    if work had not started (different method of
    award, relative weights, etc. might have been
    recommended to use)

43
  • We strongly recommend publishing your mandatory
    contract provisions into the RFP or IFB, since
  • This allows potential bidders to raise concerns
    prior to submitting a bid, and
  • Eliminates a vendor or vendors unwilling to meet
    these mandatory provisions, thus avoiding
    prolonged and fruitless contract negotiations if
    this vendor is the highest ranked firm thus
    saving the agency time and money, and avoiding
    delay of their program needs being met.

44
In Summary
  • Openness
  • Questions and answers are disclosed to all
    bidders
  • No verbal (one on one) communications with
    vendors
  • Debriefing losing vendors upon request

45
In Summary
  • Fairness
  • Create an even playing field
  • Clear, detailed specifications
  • No altering of evaluation criteria after bids
    have been received

46
In Summary
  • Due Diligence
  • Knowledge of applicable rules and regulations
  • State Finance Law
  • Procurement Guidelines
  • Procurement Stewardship Act
  • OSC G-Bulletins

47
In Summary
  • Achieving Goals
  • Communicate your needs/goals and reach a full
    understanding with the awarded vendor

48
In Summary
  • Following these outlined steps should produce a
    protest-free procurement and a smooth approval
    process.
Write a Comment
User Comments (0)
About PowerShow.com