Title: Summary of Blayer Replacement Workshop
1Summary of B-layer Replacement Workshop
- October ATLAS Week
- CERN, 10 October 2007
- G. Darbo - INFN / Genova
- Workshop page
- http//indico.cern.ch/conferenceDisplay.py?confId
20119
2B-Layer Workshop
http//indico.cern.ch/conferenceDisplay.py?confId
21107
- B-layer Replacement WS
- Sept. 28-29, 2007
- Workshop numbers
- 1 1/2 days
- 6 Sessions round table
- 56 registered participants
3Why Pixel Replacement
- B-layer was designed to survive 3 years of LHC
nominal luminosity (1034cm-2s-1) - NIEL fluence 1015 neq/cm2 (mainly from pions)
- Ionising Dose 500 kGy (50 Mrad)
- Sensors
- Not fully depleted at 600 V ? lower charge
collected, lower efficiency - Leakage current (noise)
- Charge trapping ? lower charge collected, lower
efficiency - Electronics
- Transistor VT shift due to charge trapping in
the gate oxide (Ionisig Radiation). FE and MCC
tested to 500 kGy) - New LHC machine scenario could move replacement
date into the future, but large unknowns on
operation and cooling runaway may make it
sooner. - Target date for the Workshop studyWinter
shutdown 2012
4Replacement Constraints
- Aim of the replacement is to improve, or at least
restore, initial performance of the Pixel (ID)
detector. - This scenario involves improvements to
sensor/electronics design, to module and
mechanical geometry. - Hope for beam pipe radius reduction, such that a
3237 mm radius pixel detector can be inserted
inside the existing detector. - The new b-layer could be inserted together with
the beam pipe in this scenario. - Two scenarios have been studied and analysed in
the workshop - Add a small R b-layer leave existing one
(having reduced efficiency) - Add a small R b-layer remove the existing one
(remove material) - The additional constraint we used in the study
was the replacement date 2012 and the shutdown
time 6 months
A
B
5Layout Simulation Method and Software
- DC1 model of ID upgraded pixel.
- Latest xKalmanOO (tracking).
- Private version of b-tagging software with
secondary vertices and recalibration for
different trackerprocess configurations - B-tagging software was not specifically tuned for
new setup (all track selection cuts were the same
as for current pixel).
Ref. V. Kostyukhin, P. Nevski, A. Rozanov
Results presented for upgraded pixel with added
layer (4L) and with modified single b-layer
together with results obtained with current
pixel detector (3L).
Modified layout with single b-layer
Layout with 4-layers L4
Rb1 37.0 mmRb2 absentR1 88.5 mmR2
122.5 mm
Rb1 37.0mmRb2 50.5mm R1 88.5mmR2 122.5mm
6Material Studies Performance
Modified layout with Single b-layer X0 1.2
New b-layer X0 1.2
Z resolution
- Performance equivalences in old studies
- Decrease of the b-layer radius from 5 cm to 4 cm
(20 effect) - Decrease of the z-pitch in b-layer from 400 um to
200 um - Decrease of the material in b-layer by 0.6
- Loss of 1 / 2 pixel module/chip inefficiency in
b-layer - Partial (2/3) missing the intermediate pixel
layer (R9cm) - Pile-up of 1034 cm2s-1 without muon pointing to
primary vertex.
3L
4L
Ref. A. Rozanov
7 b-tagging u-jets
3d significance of primary-secondary vertices
distance for vertices in u-jets (fake)
Ref. V. Kostyukhin
Bigger tail for 4L pixel ? means problem for
b-tagging.
3L
4L
for vertices in b-jets (real)
Mean value should be inversely proportional to
resolution ( B-particle decay is the same,
resolution is better).In fact 3D resolution is
not significantly better.
3L
4L
8 B-tagging Results
Ref. V. Kostyukhin
Preliminary!!!
WH(120)?uu(bb), no pileup, ATLFAST jets,
reconstructed primary vertex.
- Tracking performance seems ok for 4 layers case
but b-tagging is worse comparing with current
design. Track part of b-tagging is mainly
responsible for worsening. - Layout with new single b-layer at R37mm and
removed current b-layer gives significantly
better performance with existing tracking
software. - Single b-layer at R37mm provides some increase
of b-tagging rejection at high ? region weak
point of existing pixel detector.
9Radiation Protection at CERN
10Disconnect / Extract the Pixel
Ref. D. Giugni
TASKS in this ENVIROMENT Set up and align the
DST, Extract the detector, Rotate the DST, Hook
up the DST to the crane. DURATION, MANPOWER,
INTEGRAL DOSE 84h, 3 people, 3.1mSv
lt50 µSv/h ? Simple controlled radiation area
/ Low occupancy areas lt 2 mSv/h ? Limited stay
area / Low occupancy areas
- The area of the ATLAS beam line will be
classified as Controlled Radiation Area. - Assuming that the Full Body Dose exceeds 50µSv/h
the area should also be classified as Limited
Stay Area(lt 2mSv/h). - This means that workers have a controlled access,
must wear a personal dosimeter an operational
dosimeter and be classified as Radiation
Workers. - This assumption is justified by the fact that
the calorimeter in front of the IDEP has zone
with dose rate at 500mSv/h.
11On Surface in the SR1
TASKS in this ENVIROMENT Remove SQPs, Access
the beam pipe, Remove the beam pipe, Remove and
insert the B-layer, Connectivity Test DURATION,
MANPOWER, INTEGRAL DOSE 600h (depending upon
the scenario), 4 people present, 28.9mSv
Supervised Radiation AREA lt 15 µSv/h
ITT
Simple Controlled Radiation AREA lt50µSv/h
- Great attention has to be paid to avoid
radioactive contamination. Grinding and cutting
activated material would cause a contamination in
the airborne and on the surfaces.
Ref. D. Giugni
12Services - Additions
Intreferes with T0 Cables
OSP
Detector
ISP
Requires Removal Of all SQP on this side
Modify
BPSS
- (Some) critical issues
- Service Panels (SQPs) are highly integrated both
electrically and mechanically - Electrical modularity of services locked in
Mechanically - Tight envelopes make re-arrangement of services
difficult - Penetration at PP1 uses almost all real estate at
package ends - Fibers case A requires new opto-fibers to be
re-routed (difficult) and remapping with new
electronics, case B fiber reuse requires same
nominal location of New Optical drivers
Ref. E. Anderssen
13What to Open
- Case AA-Side (to insert B-layer leaving existing
one) - Need to install new cooling circuits, cant be
C-Side, not quite enough spare Holes - Requires complete disassembly of at least 2 SQPs
to get at least 6 cooling circuits in - Gives access to BPSS to install new PP0s
- A lot of work, all after removal, likely on
critical path - Case BC-Side (to remove existing B-layer and add
a new one) - Need clear aperture to pass BP and new BL
incannot pass PP1 Cruciform - Only required removal of T0 cables and enough
SQPs to be comfortable removing BPSS - Remove SQPs but not dissassemble to modify for
cable routing of new PP0s - Access to BPSS to install new PP0s
- On Critical Path, but less work than A
- Both require removal of BPSS and at least 2 SQPs
on one side. - Schedule
- Case A and B differ in the needed operations but
the total time will not differ greatly. Case B
requires, in first analysis 9.5 months. Case A
could be slightly faster. - More detailed studies are needed.
Ref. E. Anderssen
Ref. D. Giugni
14Envelope Studies
- New beam pipe radius
- Nominally reduced to R25, theoretically to R17
(instead of R29 now) but - R17 will require feedback from future Atlas run
see Rays talk at - Current B-layer envelope R45.5 to R74 28.5 mm.
- Case A IR35 OR41
- Case B IR35 OR71.5
- Studies which might give more space
- Insulation thickness between BP and B-Layer
- Radial Adjustment of Beam-pipe
- Assembly sequence/tooling which requires less
clearance
Ref. A. Catinaccio
15Layout Concepts Single Layer
Monolitic OD 88 mm ID 75 mm
- Developing directions
- Made stave prototype (for SLHC upgrade test) with
carbon foams with good thermal conductivity but
relatively high density (?0.55 g/cc). - Thermal and FEA analysis.
- Look to low density (?0.15 g/cc) foam or
nanotubes.
Ref. M. Gilchieriese, M. Garcia Sciveres
Stave - 2 OD 88 mm ID 70 mm
Stave - 1 OD 93 mm ID 70 mm
16Layout Concept Double b-layer
Ref. N. Wermes
incl. angle B2 6o incl. angle B1 10o
nom. radius B2 49 mm nom. radius B1 37 mm
envelope ok
staves B2 20 staves B1 16
Wolfgan Dietsche, Walter Ockenfels
17Local Support Structure - Stave
Ref. K.W. Glitza
- Wuppertal stave studies
- Use homogeneous structure all carbon based.
- Reduce material carbon foam for the cover (
density 0.50.9 g/cm³) thermal conductivity
(in plane 140 W/mK out of plane 70 W/mK) - Material and stability woven carbon pipes
sensor
cover
base
base
pipe
Prototype
18SENSORS WORKING GROUP List of requirements
- radiation hardness figure greater than 3e15
neutrons/cm2 - electrical characteristics
- noise, leakage currents - expected s/n figure
- mechanical characteristics
- thickness, material budget, dead area at edges
- preferred module size
- present size or
- 16.5x17.5 mm2 62x250 mm 2x500mm x 350x50mm
single or multiple chips (as the present design) - cooling options
- present and future large scale production
capability - time scale for production for the b-layer
replacement - cost estimate per 100 wafers (6)
19Sensors
- Basically all technologies covered by
presentations - N-on-n is the Pixel proven technology
- P-on-n gives the same radiation tolerance than
n-on-n, but single-side process cheaper and with
higher yield - Thin sensors lower material, lower leakage
current, lower charge - Diamonds works at room temperature, pCVD
(spatial resolution?) and scCVD (large enough
sensors?). Work at room temperature, low noise,
high cost. - 3D sensors high level of radiation hardness
(highest collected charge after irradiation),
active edge, but cost. - Gossip gaseous detector, many interesting
features, but still on RD stage.
20Electronic Framework
- Electronics designed for higher occupancy,
radiation tolerance, SEU - Larger FE chip increases module live fraction
(70 ? 90) - Feasible single chip (active edge) modules or
standard multi-chip
21System Architecture
- Remove MCC from module and have a SCC at stave
end. - Serial links along the stave to connect FE ? SCC
- Opto-links use same SIMM/GRIN fibers but at
higher speed.
22Front-end Chip - FE-I4
- Laboratories involved Bonn, CPPM, Genova,
Nikhef, LBNL. - Very spread collaboration, difficult organize
common effort. - Submission planned 12/2008.
23Workshop Outcome
- The Workshop was quite successful, attracted more
than 70 people and was the first serious attempt
to look into the b-layer replacement. - It was the first time we did substantial study
in - Simulating the b-tagging performance of the
replacement scenarios. - Analyzing the impact of activation in the
operations to be made to replace the detector. - Evaluating the impact on the schedule of
different scenarios. - We have been somewhat surprised
- Reduction of material is probably more important
than reduction of the radius - Scope is bigger than foreseen for short time
scale. Services are on the critical path.
Reconnect services cannot be done in short time.
Replace services could be faster than
disconnecting and connecting again, but cost
would exceed that of the funded project (34
MSF). - Threshold to change is higher sensors and
electronics could survive longer and risk of the
intervention (in complexity and time scale) are
higher than foreseen.
24What to do next
- Develop a more precise and comprehensive analysis
of the lifetime issues for the present B-layer - Effect of the reduced collected charge from the
sensors has to be studied throughout electronics
signal generation and finally to b-tagging
efficiency. - Define some "thresholds" that would imply risks
we are willing to take, or timescales we are
willing to consider for replacements. - B-layer is the unique layer, in the whole ID,
which its reduced performance would have such a
major effect on Physic achievements (basically,
destroying or seriously degrading b-tagging). - Develop a more complete plan, in collaboration
with TC/PO for the complete replacement
operation, to understand the timescales and
projections for allowed shutdowns. - Push RD to reduce material budget. This must
happen mainly in the fields of sensors,
electronics and integrated support structures
(staves). - Study ways of extending lifetime of present
detector cooling, operating sensors for longer
life (limit bias current to keep them cooler).
25Last but not Least (Conclusions)
- The B-layer replacement, at a modest scope (no
more than about 34 MSF CORE equivalent) is a
funded project, though not approved in detail. - it is not only a necessary intermediate step
before going to a 1035 upgrade but should extend
the secondary vertex related physics reach for
ATLAS (or maintain it for longer). - The timescale must fit with the SLHC, although
that is not an approved project with a
schedule. - We will gain critical experience (pixel hookup
and closing ATLAS) in next months so more natural
time to reach a conclusion on baseline
replacement option is again summer 2008. - More engineering manpower will be released from
the present priority task of Pixel detector
completion and will be directed to the study of
the new detector.