Title: Mponeng Mine
1Mponeng Mine
- Analyst visit
- 13 November, 2003
2Itinerary
- Welcome and Presentation
- Underground visit
- Discussion Mine Planning MRM
- Lunch
- Further QA session (if required)
- Depart for JHB - 2.30pm
3Mponeng - Overview
- Sinking started in 1981
- Main Shaft commissioned 1986
- Sub Shaft commissioned 1993
- South Shaft Deepening Project approved January
1996 - Deepening commenced early 1996
- Currently mine VCR to 109 Level
- Previously Western Deep Levels 1 shaft and South
Mine - Underground mining at an average depth of 2,750m
- Approximately 5,780 employees including
contractors
- Production stats YTD
- 422,011oz
- Total cash costs 236/oz or R58,851/kg
4Mponeng - LTIFR
5LTI Rate AngloGold SA 2003
6Mponeng - Square metres mined
7Mponeng - Cash Costs R/kg
8Mponeng - Cash Costs /oz
9Mponeng ORIGINAL Deepening Project (1996)
- Scope of original project 1996
- Deepen SS1 to exploit VCR to 120 level (3371 mbc)
- Deepen SS2 to exploit CL to 132 level (3751 mbc)
- Increase sub shaft reef hoisting capacity from
150,000 tpm to 240,000tpm to match the capacity
of the main shaft - Extend Life of Mine to 2026
- Recover additional 476 tons gold
- Exploit remaining LCL reserves at TauTona (post
2005) - Partial extraction of TauTona CL pillar (10 tons
gold)
10Mponeng ORIGINAL Project (1996)
11MponengCurrent deepening project to 120L
- Exploits the VCR from 109 120 levels
- Will add 4.0 million incremental ounces to
production - Will require capital expenditure of R1.3 billion
(R130m remaining) - Will increase the LOM by 5 years to 2012 at a
total cash cost of 270/oz - Does not sterilize the reserves below 120 level
- The project comprises the access development to
VCR reef on 113, 116 and 120 levels, completion
of surface ice plants and ore pass extensions and
provision for pumps, sumps and settlers on 121
level whilst maintaining the mill capacity at
160,000 tpm.
12Mponeng Current deepening project to 120L
13Mponeng Current deepening project to 120L
- Changes in scope from 1996 - 2001
- Smooth changeover required additional haulage's
(100,113,116lvls) and refrigeration upgrade - Design changes to in-circle development
- Development cost definition move costs from Opex
to Capex - Shaft bottom infrastructure situated in the
Roodepoort shales - Driefontein ground swap extended life of Tau Tona
UCLR - The new Mponeng and TauTona projects show
better returns than the original 1996 project
14Mponeng Current deepening project to
120LMilestones and updates
- Flat end development on 113 level achieved ahead
of schedule up to 46 crosscut reef intersection - Crosscuts complete on 116 and 120 levels - 48
line - 116 - 46x/c complete Nov 2003
- 120 - 46x/c complete Feb 2004
- 113 - 48 Rse complete Feb 2004
15Mponeng Current deepening project to
120LMilestones and updates
16Future Project VCR120-125Lfor discussion at
13h00
17Safety Induction
18Safety Induction - Overview
- Background
- Paperwork
- Personal protective equipment
- What not to take
- Going down
- Underground
- To sum up
19Background
- No person comes to Mponeng to be injured
- You will experience heat , humidity , pressure
and a certain amount of hazards
20Paperwork
- Age and health exclusions
- lt18 or gt70
- Asthma
- Diabetes
- Heart problems
- Pregnancy
- Indemnity form
21Personal Protective Equipment
- Hard Hats
- Lamp
- Ear muffs or plugs
- Goggles
- Gloves
- Boots
Earplugs
22What Not to Take
- NO cigarettes, lighters, matches
- Why not?
- Presence of flammable gases
- Photographic equipment
- Must have written permission
- Please clean and dry your equipment after use
- Firearms
23Going Down
- Wait for permission to enter cage
- Ear blocking
- Like being in an airplane
- Open your mouth, swallow, yawn
- When you leave the cage
- Follow your guide along planned route
24Underground
- Watch out for locos
- Traveling up/down inclined ends
- Use climbing chain
- Tell guide if tired
- Stop and rest
- Stay with the group
- Do not pull any rocks from its position
25Enjoy Your Visit toMponeng Mine