Title: Distance Learning Center
1Distance Learning Center
- Technology Project Management
- Procurement and Contracts
- Part Two
- Melissa Lin, IT Consultant
- HenEm, Inc. Parkville, Missouri
- linm_at_ipfw.edu
- http//www.etcs.ipfw.edu/linm
2Procurement and Contracts
- Types of Contracts
- Incentive Contracts Cost Incentive
- Contract Type versus Risk
- Contract Administration Cycle Rights
3Types of Contracts
- Fixed-Price (FP)
- Cost-Plus-Fixed-Fee (CPFF)
- Cost-Plus-Percentage-Fee (CPPF)
- Guaranteed-Maximum-Shared Savings (GMSS)
- Fixed-Price-Incentive-Fee (FPIF)
- Cost-Plus-Incentive-Fee (CPIF)
4Contractors Risks
LEGEND
FFP FIRM FIXED PRICE
CPFF COST PLUS FIXED FEE
5Firm-Fixed-Price Contract (FFP)
- MAXIMUM RISK WITH CONTRACTOR
- HIGHER NEGOTIATED PROFIT MARGINS
- HIGH LIKELIHOOD OF SCOPE CHANGES
6Firm-Fixed-Price With Economic Price Adjustments
(FPE)
- ADJUSTMENTS FOR ESCALATION FACTORS
- ADJUSTMENTS FOR INFLATION
- NEGOTIATED ADJUSTMENT CYCLE
RISK SHARING METER
100
0
RISK
CONTRACTORS
CUSTOMERS
RISK
RISK
LOCATION
0
100
7Incentive Contracts
- ADDITIONAL PROFITS ARE POSSIBLE BY LOWERING
COST - CUSTOMER AND CONTRACTOR SHARE COST SAVINGS
8Principles of Incentive Contracts
CONTRACTORS 20
CONTRACTORS 20
9Fixed-Price-Incentive-Fee Contract (FPIF)
- CONTRACTOR CAN EARN ADDITIONAL PROFITS
- CONTRACT HAS A CEILING ON PRICE (OR COST) PAID
- PRICE (OR COST) CEILING AT POINT OF TOTAL
ASSUMPTION
10Cost-Plus-Incentive-Fee Contract (CPIF)
- CONTRACTOR CAN EARN ADDITIONAL PROFITS
- ALL COSTS ARE REIMBURSED (COST RUN-UPS)
- A FLOOR AND CEILING EXISTS ON PROFITS
11Cost-Plus-Award-Fee Contract (CPAF)
- ALL COSTS ARE REIMBURSED (COST RUN-UPS)
- NEGOTIATED RANGE OF POSSIBLE PROFITS
- CUSTOMER DETERMINES PROFIT PAID AT COMPLETION
12Cost-Plus-Fixed-Fee Contract (CPFF)
- ALL COSTS ARE REIMBURSED (COST RUN-UPS)
- FEE IS FIXED (IN NOT ) IRRESPECTIVE OF
COSTS - CONTRACTOR IS MOTIVATED FOR EARLY COMPLETION
13Cost-Sharing Contract (CS)
- NO PROFITS ALLOWED
- CUSTOMER AND CONTRACTOR SHARE COSTS
- CONTRACTOR MAY RETAIN CONTROL OF
PROPRIETARY KNOWLEDGE AFTER COMPLETION
14Cost Contract (C)
- NO PROFITS ALLOWED
- CONTRACTOR IS USUALLY A NON-PROFIT ORGANIZATION
- LIMITATIONS ON COSTS ALLOWED MAY BE IMPOSED
15Cost-Plus-Percentage-Of-Cost Contract (CPPC)
- COSTS INCURRED MAY BE UNLIMITED
- CONTRACTORS CAN MAXIMIZE PROFITS
- SCOPE CHANGES MAY BE FREQUENT AND UNLIMITED
16Relative Contract Risk
17Contract Administration Cycle
- Change management
- Specification interpretation
- Adherence to quality
- Warranties
- Subcontractor management
- Production surveillance
- Waivers
- Contract breach
18Contract Administration Cycle (Continued)
- Resolution of disputes
- Project termination
- Payment schedules
- Project closeout
19Order of Precedence
- Specifications (first priority)
- Other instructions (second priority)
- Other documents, such as exhibits, attachments,
appendices, SOW, contract date requirements list
CDRL, etc. (third priority) - Contract clauses (fourth priority)
- The schedule (fifth priority)
20Type of Changes
- Administrative change
- Change order
- Contract modification
- Un-definitized contractual action
- Supplemental agreement
- Constructive change
21Causes of Constructive Changes
- Defective specification with impossibility of
performance - Erroneous interpretation of contract
- Over-inspection of work
- Failure to disclose superior knowledge
- Acceleration of performance
- Late or unsuitable owner or customer furnished
property - Failure to cooperate
- Improperly exercised options
- Misusing proprietary data
- Failure to cooperate
- Improperly exercised options
- Misusing proprietary data
22Reasons for Termination for Convenience of the
Customer
- Elimination of the requirement
- Technological advances in the state-of-the-art
- Budgetary changes
- Related requirements and/or procurements
- Anticipating profits not allowed
23Reasons for Termination for Default Due to
Contractors Actions
- Contractor fails to make delivery on scheduled
date. - Contractor fails to make progress so as to
endanger performance of the contract and its
terms. - Contractor fails to perform any other provisions
of the contract.
24Contract Administration Rights
- Reject the entire shipment
- Accept the entire shipment (barring latent
defects) - Accept part of the shipment
25Summary
- Types of Contracts
- Incentive Contracts Cost Incentive
- Contract Type versus Risk
- Contract Administration Cycle Rights
- Next Project Evaluation and Closing
26Question?
- Answers
- Email linm_at_ipfw.edu
- http//www.etcs.ipfw.edu/linm