Distance Learning Center - PowerPoint PPT Presentation

1 / 26
About This Presentation
Title:

Distance Learning Center

Description:

Procurement & Contracts Management - By M. Lin. 3. Types of ... Accept the entire shipment (barring latent defects) Accept part of the shipment. April 18, 2005 ... – PowerPoint PPT presentation

Number of Views:22
Avg rating:3.0/5.0
Slides: 27
Provided by: melis76
Category:

less

Transcript and Presenter's Notes

Title: Distance Learning Center


1
Distance Learning Center
  • Technology Project Management
  • Procurement and Contracts
  • Part Two
  • Melissa Lin, IT Consultant
  • HenEm, Inc. Parkville, Missouri
  • linm_at_ipfw.edu
  • http//www.etcs.ipfw.edu/linm

2
Procurement and Contracts
  • Types of Contracts
  • Incentive Contracts Cost Incentive
  • Contract Type versus Risk
  • Contract Administration Cycle Rights

3
Types of Contracts
  • Fixed-Price (FP)
  • Cost-Plus-Fixed-Fee (CPFF)
  • Cost-Plus-Percentage-Fee (CPPF)
  • Guaranteed-Maximum-Shared Savings (GMSS)
  • Fixed-Price-Incentive-Fee (FPIF)
  • Cost-Plus-Incentive-Fee (CPIF)

4
Contractors Risks
LEGEND
FFP FIRM FIXED PRICE
CPFF COST PLUS FIXED FEE
5
Firm-Fixed-Price Contract (FFP)
  • MAXIMUM RISK WITH CONTRACTOR
  • HIGHER NEGOTIATED PROFIT MARGINS
  • HIGH LIKELIHOOD OF SCOPE CHANGES

6
Firm-Fixed-Price With Economic Price Adjustments
(FPE)
  • ADJUSTMENTS FOR ESCALATION FACTORS
  • ADJUSTMENTS FOR INFLATION
  • NEGOTIATED ADJUSTMENT CYCLE

RISK SHARING METER
100
0
RISK
CONTRACTORS
CUSTOMERS
RISK
RISK
LOCATION
0
100
7
Incentive Contracts
  • ADDITIONAL PROFITS ARE POSSIBLE BY LOWERING
    COST
  • CUSTOMER AND CONTRACTOR SHARE COST SAVINGS

8
Principles of Incentive Contracts
CONTRACTORS 20
CONTRACTORS 20
9
Fixed-Price-Incentive-Fee Contract (FPIF)
  • CONTRACTOR CAN EARN ADDITIONAL PROFITS
  • CONTRACT HAS A CEILING ON PRICE (OR COST) PAID
  • PRICE (OR COST) CEILING AT POINT OF TOTAL
    ASSUMPTION

10
Cost-Plus-Incentive-Fee Contract (CPIF)
  • CONTRACTOR CAN EARN ADDITIONAL PROFITS
  • ALL COSTS ARE REIMBURSED (COST RUN-UPS)
  • A FLOOR AND CEILING EXISTS ON PROFITS

11
Cost-Plus-Award-Fee Contract (CPAF)
  • ALL COSTS ARE REIMBURSED (COST RUN-UPS)
  • NEGOTIATED RANGE OF POSSIBLE PROFITS
  • CUSTOMER DETERMINES PROFIT PAID AT COMPLETION

12
Cost-Plus-Fixed-Fee Contract (CPFF)
  • ALL COSTS ARE REIMBURSED (COST RUN-UPS)
  • FEE IS FIXED (IN NOT ) IRRESPECTIVE OF
    COSTS
  • CONTRACTOR IS MOTIVATED FOR EARLY COMPLETION

13
Cost-Sharing Contract (CS)
  • NO PROFITS ALLOWED
  • CUSTOMER AND CONTRACTOR SHARE COSTS
  • CONTRACTOR MAY RETAIN CONTROL OF

PROPRIETARY KNOWLEDGE AFTER COMPLETION
14
Cost Contract (C)
  • NO PROFITS ALLOWED
  • CONTRACTOR IS USUALLY A NON-PROFIT ORGANIZATION
  • LIMITATIONS ON COSTS ALLOWED MAY BE IMPOSED

15
Cost-Plus-Percentage-Of-Cost Contract (CPPC)
  • COSTS INCURRED MAY BE UNLIMITED
  • CONTRACTORS CAN MAXIMIZE PROFITS
  • SCOPE CHANGES MAY BE FREQUENT AND UNLIMITED

16
Relative Contract Risk
17
Contract Administration Cycle
  • Change management
  • Specification interpretation
  • Adherence to quality
  • Warranties
  • Subcontractor management
  • Production surveillance
  • Waivers
  • Contract breach

18
Contract Administration Cycle (Continued)
  • Resolution of disputes
  • Project termination
  • Payment schedules
  • Project closeout

19
Order of Precedence
  • Specifications (first priority)
  • Other instructions (second priority)
  • Other documents, such as exhibits, attachments,
    appendices, SOW, contract date requirements list
    CDRL, etc. (third priority)
  • Contract clauses (fourth priority)
  • The schedule (fifth priority)

20
Type of Changes
  • Administrative change
  • Change order
  • Contract modification
  • Un-definitized contractual action
  • Supplemental agreement
  • Constructive change

21
Causes of Constructive Changes
  • Defective specification with impossibility of
    performance
  • Erroneous interpretation of contract
  • Over-inspection of work
  • Failure to disclose superior knowledge
  • Acceleration of performance
  • Late or unsuitable owner or customer furnished
    property
  • Failure to cooperate
  • Improperly exercised options
  • Misusing proprietary data
  • Failure to cooperate
  • Improperly exercised options
  • Misusing proprietary data

22
Reasons for Termination for Convenience of the
Customer
  • Elimination of the requirement
  • Technological advances in the state-of-the-art
  • Budgetary changes
  • Related requirements and/or procurements
  • Anticipating profits not allowed

23
Reasons for Termination for Default Due to
Contractors Actions
  • Contractor fails to make delivery on scheduled
    date.
  • Contractor fails to make progress so as to
    endanger performance of the contract and its
    terms.
  • Contractor fails to perform any other provisions
    of the contract.

24
Contract Administration Rights
  • Reject the entire shipment
  • Accept the entire shipment (barring latent
    defects)
  • Accept part of the shipment

25
Summary
  • Types of Contracts
  • Incentive Contracts Cost Incentive
  • Contract Type versus Risk
  • Contract Administration Cycle Rights
  • Next Project Evaluation and Closing

26
Question?
  • Answers
  • Email linm_at_ipfw.edu
  • http//www.etcs.ipfw.edu/linm
Write a Comment
User Comments (0)
About PowerShow.com