Title: Control Through Standard Costs
1CHAPTER 24
CONTROL THROUGH STANDARD COSTS
.
2CHAPTER 24
CONTROL THROUGH STANDARD COSTS
Caution! This chapter is second only to Chapter
15 (bonds) for the amount of grief it causes most
students in this course.
3Nature of Standard Costs
- Up to this point in the course, we have been
using actual costs. - This chapter considers standard costs (i.e., what
costs should be under stated conditions). - The achievement of standard represents a
reasonable and acceptable level of performance. - Standards for materials, labor, and overhead are
determined through engineering studies and time
and motion studies.
4Nature of Standard Costs
5Nature of Standard Costs
DirectMaterial
DirectLabor
ManufacturingOverhead
6Standard Cost Variances
7Standard Cost Variances
The overhead variance is favorable becausethe
actual cost is less than the standard cost.
The materials variance is unfavorable because the
actual cost exceeds the standard cost.
DirectMaterial
DirectLabor
ManufacturingOverhead
8Standard Cost Variances
DirectMaterial
DirectLabor
ManufacturingOverhead
9Standard Cost Variances
10Setting Standard Costs
Engineer
11Setting Standard Costs
Productionmanager
12Setting Standard Costs
HumanResourcesManager
13Setting Standard Costs
ManagerialAccountant
14Advantages of Standard Costs
Improved cost control and performanceevaluation
Better Informationfor planning anddecision
making
More reasonableand easier inventorymeasurements
Cost savings inrecord-keeping
Possible reductionsin production costs
15Disadvantages of Standard Costs
Emphasis onnegativeexceptions maylower morale.
It may be difficultto determinewhich
variancesare significant.
Emphasis on negativeexceptions maylead to
under-reporting.
16Use of Standard Costs in Developing Budgets
17Specifics
O.K., lets get down and dirty with some
specifics!
18Types of Standard Costs
- The total standard cost for one unit of finished
product is the sum of - Standard cost for direct materials
- Standard cost for direct labor
- Standard cost for manufacturing overhead
- necessary to produce one unit of the product.
19Setting StandardsDirect Materials
UsageStandards
PriceStandards
Use competitivebids for the qualityand quantity
desired
Use product design specifications
20Standard CostsDirect Materials
- Standard cost for direct materials is standard
price for one unit of raw material (pound, yard,
etc.) multiplied by the standard quantity of raw
material to produce one unit of product
21Standard CostsDirect Materials
The standard material cost for one unit of
product is standard quantity
standard price for of material
one unit of material
required for one unit of product
- Standard price is the amount that should be paid
for each unit of raw material. - Standard quantity is the amount of raw material
that should be used to produce one unit
offinished product.
22Standard CostsDirect Materials Example
The High Point Furniture Company makes top
quality tables from sheets of plywood.
- Standard price is the amount that should be paid
for each unit of raw material. - e.g.., each sheet of plywood should cost 6
- Standard quantity is the amount of material that
should be used to produce one unit of finished
product. - e.g., each table should take 5 sheets
23Standard CostsDirect Materials Example
- Standard price is the amount that should be paid
for each unit of raw material. - e.g.., each sheet of plywood should cost 6
- Standard quantity is the amount of material that
should be used to produce one unit of finished
product. - e.g., each table should take 5 sheets
- Standard cost is standard price times standard
quantity for one unit of product - e.g., 6 X 5 sheets 30
24Setting StandardsDirect Labor
EfficiencyStandards
RateStandards
Use wage surveys andlabor contracts
Use time and motion studies foreach labor
operation
25Standard CostsDirect Labor
Standard cost for direct labor is standard wage
rate for one hour of labor multiplied by the
standard number of labor hours needed to produce
one unit of product.
26Standard CostsDirect Labor
The standard labor cost for one unit of product
is standard number standard wage
rate of labor hours
for one hour for one
unit
of product
- Standard wage rate is theamount that should be
paidfor each hour of labor. - Standard number of hoursis the number of hours
thatshould be worked to produceone unit of
finished product.
27Standard CostsDirect Labor Example
The High Point Furniture Companys dining room
tables are made by highly skilled, hourly paid
carpenters.
- Standard wage rate is the amount that should be
paid for each hour of labor. - e.g.., each hour should cost 10
- Standard number of hours is the number of hours
that should be worked to produce one unit of
finished product. - e.g., each table should take 2 hours
28Standard CostsDirect Labor Example
- Standard wage rate is the amount that should be
paid for each hour of labor. - e.g.., each hour should cost 10
- Standard number of hours is the number of hours
that should be worked to produce one unit of
finished product. - e.g., each table should take 2 hours
- Standard labor cost is standard wage rate times
standard number of hours for one unit of finished
product - e.g., 10 X 2 hours 20
29Setting StandardsManufacturing Overhead
Standard Rate
Select a standard level of output and definea
basis for activity
30Standard CostsManufacturing Overhead
A standard manufacturing overhead rate is
applied for each unit of activity.
.
If, however, the overhead rate is based on units
of input such as direct labor hours, the
denominator is based on the input labor
hours. The above calculation is really what?
31Standard CostsManufacturing Overhead
- Budgeted overhead cost is thetotal amount of
overhead cost that should be incurred for the
year to produce at the standard level of output. - Standard level of output is what the activity
level for the cost driver should be for the year.
32Standard CostsManufacturing Overhead Example
The High Point Furniture Company applies
overhead to tables based on
machine hours.
- Budgeted overhead cost is the amount of overhead
cost that should be incurred to produce at the
standard level of output. - e.g., total overhead cost 100,000
- Standard level of output is what the activity
level for the cost driver should be. - e.g., total labor hours should be 20,000
33Standard CostsManufacturing Overhead Example
- Budgeted overhead cost is the amount of overhead
cost that should be incurred to produce at the
standard level of output. - e.g., total overhead cost 100,000
- Standard level of output is what the activity
level for the cost driver should be. - e.g., total labor hours should be 20,000
34Standard CostsManufacturing Overhead Example
- Budgeted overhead cost is the amount of overhead
cost that should be incurred to produce at the
standard level of output. - e.g., total overhead cost 100,000
- Standard level of output is what the activity
level for the cost driver should be. - e.g., total labor hours should be 20,000
100,000 20,000
Standard overheadrate per unit (i.e, hour)
5
35Standard CostsManufacturing Overhead Example
- Budgeted overhead cost is the amount of overhead
cost that should be incurred to produce at the
standard level of output. - e.g., total overhead cost 100,000
- Standard level of output is what the activity
level for the cost driver should be. - e.g., total labor hours should be 20,000
- Standard overhead cost is standard overhead rate
times number of activity units for each unit of
finished product - e.g., 5 X 2 labor hours 10
36Standard CostsSummary of Examples
Standard Costs For One Table Direct materials -
6 X 5 sheets 30 Direct labor - 10 X
2 hours 20 Manufacturing overhead -
5 X 2 labor hours 10 Total
standard cost 60
37Computing Variances
- Standard cost variance
- Amount by which actual cost differs from
standard cost for the actual volume level
attained - Favorable variance
- Actual cost is less than standard cost
- Unfavorable variance
- Actual cost is greater than standard cost
38Computing Variances
Know how to calculate all six cost variances and
what causes each.
For the actual volume level attained
39Computing Variances
Lets use what we have learned to calculate the
six standard cost variances for a different
company, starting withdirect materials.
40Computing VariancesMaterials Price Variance
- Hanson Inc. has the following material standard
to manufacture one Zippy - 1.5 pounds per Zippy at 4.00 per pound
- Records last week show 1,700 pounds of material
were purchased in May at a total cost of 6,630.
The material was used to make 1,000 Zippies in
May.
AP 6,630 1,700 lbs AP 3.90 per lb MPV
(AP - SP) x AQ MPV (3.90 - 4.00) x 1,700
lbs. MPV -170 Favorable
Materials Price Variance
41Computing VariancesMaterials Price Variance
- Hanson Inc. has the following material standard
to manufacture one Zippy - 1.5 pounds per Zippy at 4.00 per pound
- Records last week show 1,700 pounds of material
were purchased in May at a total cost of 6,630.
The material was used to make 1,000 Zippies in
May.
AP 6,630 1,700 lbs AP 3.90 per lb MPV
(AP - SP) x AQ MPV (3.90 - 4.00) x 1,700
lbs. MPV -170 Favorable
Note that the authors use of /- is counter-
intuitive
42Recording VariancesMaterials Price Variance
Price variance is recorded at time of purchase.
43Computing VariancesMaterials Usage Variance
- Hanson Inc. has the following material standard
to manufacture one Zippy - 1.5 pounds per Zippy at 4.00 per pound
- Records last week show 1,700 pounds of material
were purchased in May at a total cost of 6,630.
The material was used to make 1,000 Zippies in
May.
SQ 1,000 units 1.5 lbs per unit SQ 1,500
lbs MUV (AQ - SQ) x SP MUV (1,700lbs -
1,500lbs) x 4.00 MUV 800 unfavorable
Materials Usage Variance
44Recording VariancesMaterials Usage Variance
45Recording VariancesMaterials Usage Variance
Usage variance is recorded at time of use.
Work in Process Inventory must always be debited
for the standard quantity X standard price (1,000
units X 1.5 lbs.) X 4.00 6,000
Can materials price and usage variances be added
to get a total materials variance?
46Computing Variances
Now lets calculate standard cost variances for
direct labor.
47Computing VariancesLabor Rate Variance
Hanson Inc. has the following labor standard to
manufacture one Zippy 1.5 standard hours per
Zippy at 6.00 per hour Payroll records show
1,450 hours were worked at a total labor cost of
8,990 to make 1,000 Zippies.
AR 8,990 1450 hours AR 6.20 per hour
LRV (AR - SR) X AH LRV (6.20 - 6.00) X
1,450 hrs LRV 290 unfavorable
Labor Rate Variance
48Computing VariancesLabor Efficiency Variance
Hanson Inc. has the following labor standard to
manufacture one Zippy 1.5 standard hours per
Zippy at 6.00 per hour Payroll records show
1,450 hours were worked at a total labor cost of
8,990 to make 1,000 Zippies.
SH 1,000 units 1.5 hours per unit SH
1,500 hours LEV (AH - SH) X SR LEV (1,450
hrs - 1,500 hrs) X 6.00 LEV -300 favorable
Labor Efficiency Variance
49Recording VariancesLabor Rate Efficiency
Variances
Note that unlike materials variances, both labor
variances are recorded at the same time. (i.e.,
when the payroll summary account is cleared out.)
50Recording VariancesLabor Rate Efficiency
Variances
Source?
.
Work in Process Inventory must always be debited
for the standard quantity X standard price (1,000
units X 1.5 lbs.) X 6.00 9,000
51Computing Variances
Now lets calculate standard cost variances for
manufacturing overhead.
52Standard Overhead Rate
- Overhead is applied to goods produced using a
standard overhead rate. - Overhead rate is set prior to the start of the
period.
Total budgeted overhead costat the standard
level of outputStandard level of output
Standard overhead rate per unit
53Standard Overhead Rate
Contains a variable per unit component which
stays constant at all levels of activity.
Contains a fixed per unit component
whichdeclines as activitylevel increases.
Is a function of the projected volumelevel
chosen to determine the rate. (i.e., standard
level of output)
54Overhead Variances
- Budget Variance
- Is calculated as the difference between total
actual overhead cost and budgeted amount of
overhead for the actual volume attained - Volume Variance
- Is calculated as the difference between the
budgeted amount of overhead for the actual
volume level attained and the applied overhead
at the standard level of output
55Overhead Variances
AOH - BOH BOH -
Applied OH
AOH Actual Overhead BOH Budgeted Overhead
56Overhead Variances
Budget Variance
VolumeVariance
Total Overhead Variance
57Overhead Variances
Budget Variance
VolumeVariance
Total Overhead Variance
58Overhead Variances
Budget Variance
VolumeVariance
Total Overhead Variance
59Overhead Variances
- Flexible budgets, showing budgeted amount of
overhead for various levels of activity, are used
to analyze overhead costs.
60Overhead VariancesExample
- Hanson, Inc. has the following flexible budget
for overhead
Hanson applies overhead based on machine hour
activityand expects to produce 1,500 Zippies.
(i.e., a standard activity level of 3,000
machine hours)
61Overhead VariancesExample
62Overhead VariancesExample
- Hansons actual production for the period was
1,600 Zippies resulting in 3,200 standard machine
hours. Actual total overhead cost for the period
was 15,450.
Compute the overhead budget and volume variances.
63Overhead VariancesExample
15,450
64Overhead VariancesExample
15,450 9,000 fixed
3,200 hrs.
6,400 variable 5.00 per hr.
15,450 15,400
16,000
Budget variance50 unfavorable
Volume variance600 favorable
65Overhead VariancesExample
Hansons flexible budget for overhead
Standard activity level
66Overhead VariancesExample
Hansons flexible budget for overhead
Standard activity level
Actual volume level attained
67Recording Overhead Variances
Overhead account is closed and both variances
are recorded at end of period in the same entry.
68Investigating Variances
- The decision to investigate a variance is based
on - Dollar amount of variance.
- Size of variance relative to cost incurred.
- Controllability of cost associated with variance.
- All of these relate to the Management by
Exception concept - Variances may be interdependent.
- Performance reports contain variances along with
budgeted and actual cost data.
69Variance Analysis andManagement by Exception
Now that I know all aboutstandard cost
variances, howdo I apply that managementby
exception concept?
70Variance Analysis andManagement by Exception
DirectMaterial
Amount
DirectLabor
ManufacturingOverhead
Type of Product Cost
71Variance Analysis andManagement by Exception
- Possible guidelines are
- Dollar amount or percentage of the standard
- Controllability of the cost variance
72Reporting Variances
73Disposing of Variances
- Variance may be closed entirely to Cost of Goods
Sold (normal case for small variances) or - Variance may be closed by
prorating to Work in Process, Finished Goods, and
Cost of Goods Sold based on relative size of
these accounts.
.
74THE END