Control Through Standard Costs - PowerPoint PPT Presentation

1 / 74
About This Presentation
Title:

Control Through Standard Costs

Description:

This chapter is second only to Chapter 15 (bonds) for the amount of grief it ... Materials inventory must always be debited for the actual quantity X standard price ... – PowerPoint PPT presentation

Number of Views:23
Avg rating:3.0/5.0
Slides: 75
Provided by: ebarr
Category:

less

Transcript and Presenter's Notes

Title: Control Through Standard Costs


1
CHAPTER 24
CONTROL THROUGH STANDARD COSTS
.
2
CHAPTER 24
CONTROL THROUGH STANDARD COSTS
Caution! This chapter is second only to Chapter
15 (bonds) for the amount of grief it causes most
students in this course.
3
Nature of Standard Costs
  • Up to this point in the course, we have been
    using actual costs.
  • This chapter considers standard costs (i.e., what
    costs should be under stated conditions).
  • The achievement of standard represents a
    reasonable and acceptable level of performance.
  • Standards for materials, labor, and overhead are
    determined through engineering studies and time
    and motion studies.

4
Nature of Standard Costs
5
Nature of Standard Costs
DirectMaterial
DirectLabor
ManufacturingOverhead
6
Standard Cost Variances
7
Standard Cost Variances
The overhead variance is favorable becausethe
actual cost is less than the standard cost.
The materials variance is unfavorable because the
actual cost exceeds the standard cost.
DirectMaterial
DirectLabor
ManufacturingOverhead
8
Standard Cost Variances
DirectMaterial
DirectLabor
ManufacturingOverhead
9
Standard Cost Variances
10
Setting Standard Costs
Engineer
11
Setting Standard Costs
Productionmanager
12
Setting Standard Costs
HumanResourcesManager
13
Setting Standard Costs
ManagerialAccountant
14
Advantages of Standard Costs
Improved cost control and performanceevaluation
Better Informationfor planning anddecision
making
More reasonableand easier inventorymeasurements
Cost savings inrecord-keeping
Possible reductionsin production costs
15
Disadvantages of Standard Costs
Emphasis onnegativeexceptions maylower morale.
It may be difficultto determinewhich
variancesare significant.
Emphasis on negativeexceptions maylead to
under-reporting.
16
Use of Standard Costs in Developing Budgets
17
Specifics
O.K., lets get down and dirty with some
specifics!
18
Types of Standard Costs
  • The total standard cost for one unit of finished
    product is the sum of
  • Standard cost for direct materials
  • Standard cost for direct labor
  • Standard cost for manufacturing overhead
  • necessary to produce one unit of the product.

19
Setting StandardsDirect Materials
UsageStandards
PriceStandards
Use competitivebids for the qualityand quantity
desired
Use product design specifications
20
Standard CostsDirect Materials
  • Standard cost for direct materials is standard
    price for one unit of raw material (pound, yard,
    etc.) multiplied by the standard quantity of raw
    material to produce one unit of product

21
Standard CostsDirect Materials
The standard material cost for one unit of
product is standard quantity
standard price for of material
one unit of material
required for one unit of product
  • Standard price is the amount that should be paid
    for each unit of raw material.
  • Standard quantity is the amount of raw material
    that should be used to produce one unit
    offinished product.

22
Standard CostsDirect Materials Example
The High Point Furniture Company makes top
quality tables from sheets of plywood.
  • Standard price is the amount that should be paid
    for each unit of raw material.
  • e.g.., each sheet of plywood should cost 6
  • Standard quantity is the amount of material that
    should be used to produce one unit of finished
    product.
  • e.g., each table should take 5 sheets

23
Standard CostsDirect Materials Example
  • Standard price is the amount that should be paid
    for each unit of raw material.
  • e.g.., each sheet of plywood should cost 6
  • Standard quantity is the amount of material that
    should be used to produce one unit of finished
    product.
  • e.g., each table should take 5 sheets
  • Standard cost is standard price times standard
    quantity for one unit of product
  • e.g., 6 X 5 sheets 30

24
Setting StandardsDirect Labor
EfficiencyStandards
RateStandards
Use wage surveys andlabor contracts
Use time and motion studies foreach labor
operation
25
Standard CostsDirect Labor
Standard cost for direct labor is standard wage
rate for one hour of labor multiplied by the
standard number of labor hours needed to produce
one unit of product.
26
Standard CostsDirect Labor
The standard labor cost for one unit of product
is standard number standard wage
rate of labor hours
for one hour for one
unit
of product
  • Standard wage rate is theamount that should be
    paidfor each hour of labor.
  • Standard number of hoursis the number of hours
    thatshould be worked to produceone unit of
    finished product.

27
Standard CostsDirect Labor Example
The High Point Furniture Companys dining room
tables are made by highly skilled, hourly paid
carpenters.
  • Standard wage rate is the amount that should be
    paid for each hour of labor.
  • e.g.., each hour should cost 10
  • Standard number of hours is the number of hours
    that should be worked to produce one unit of
    finished product.
  • e.g., each table should take 2 hours

28
Standard CostsDirect Labor Example
  • Standard wage rate is the amount that should be
    paid for each hour of labor.
  • e.g.., each hour should cost 10
  • Standard number of hours is the number of hours
    that should be worked to produce one unit of
    finished product.
  • e.g., each table should take 2 hours
  • Standard labor cost is standard wage rate times
    standard number of hours for one unit of finished
    product
  • e.g., 10 X 2 hours 20

29
Setting StandardsManufacturing Overhead
Standard Rate
Select a standard level of output and definea
basis for activity
30
Standard CostsManufacturing Overhead
A standard manufacturing overhead rate is
applied for each unit of activity.
.
If, however, the overhead rate is based on units
of input such as direct labor hours, the
denominator is based on the input labor
hours. The above calculation is really what?
31
Standard CostsManufacturing Overhead
  • Budgeted overhead cost is thetotal amount of
    overhead cost that should be incurred for the
    year to produce at the standard level of output.
  • Standard level of output is what the activity
    level for the cost driver should be for the year.

32
Standard CostsManufacturing Overhead Example
The High Point Furniture Company applies
overhead to tables based on
machine hours.
  • Budgeted overhead cost is the amount of overhead
    cost that should be incurred to produce at the
    standard level of output.
  • e.g., total overhead cost 100,000
  • Standard level of output is what the activity
    level for the cost driver should be.
  • e.g., total labor hours should be 20,000

33
Standard CostsManufacturing Overhead Example
  • Budgeted overhead cost is the amount of overhead
    cost that should be incurred to produce at the
    standard level of output.
  • e.g., total overhead cost 100,000
  • Standard level of output is what the activity
    level for the cost driver should be.
  • e.g., total labor hours should be 20,000

34
Standard CostsManufacturing Overhead Example
  • Budgeted overhead cost is the amount of overhead
    cost that should be incurred to produce at the
    standard level of output.
  • e.g., total overhead cost 100,000
  • Standard level of output is what the activity
    level for the cost driver should be.
  • e.g., total labor hours should be 20,000

100,000 20,000
Standard overheadrate per unit (i.e, hour)

5

35
Standard CostsManufacturing Overhead Example
  • Budgeted overhead cost is the amount of overhead
    cost that should be incurred to produce at the
    standard level of output.
  • e.g., total overhead cost 100,000
  • Standard level of output is what the activity
    level for the cost driver should be.
  • e.g., total labor hours should be 20,000
  • Standard overhead cost is standard overhead rate
    times number of activity units for each unit of
    finished product
  • e.g., 5 X 2 labor hours 10

36
Standard CostsSummary of Examples
Standard Costs For One Table Direct materials -
6 X 5 sheets 30 Direct labor - 10 X
2 hours 20 Manufacturing overhead -
5 X 2 labor hours 10 Total
standard cost 60
37
Computing Variances
  • Standard cost variance
  • Amount by which actual cost differs from
    standard cost for the actual volume level
    attained
  • Favorable variance
  • Actual cost is less than standard cost
  • Unfavorable variance
  • Actual cost is greater than standard cost

38
Computing Variances
Know how to calculate all six cost variances and
what causes each.
For the actual volume level attained
39
Computing Variances
Lets use what we have learned to calculate the
six standard cost variances for a different
company, starting withdirect materials.
40
Computing VariancesMaterials Price Variance
  • Hanson Inc. has the following material standard
    to manufacture one Zippy
  • 1.5 pounds per Zippy at 4.00 per pound
  • Records last week show 1,700 pounds of material
    were purchased in May at a total cost of 6,630.
    The material was used to make 1,000 Zippies in
    May.

AP 6,630 1,700 lbs AP 3.90 per lb MPV
(AP - SP) x AQ MPV (3.90 - 4.00) x 1,700
lbs. MPV -170 Favorable
Materials Price Variance
41
Computing VariancesMaterials Price Variance
  • Hanson Inc. has the following material standard
    to manufacture one Zippy
  • 1.5 pounds per Zippy at 4.00 per pound
  • Records last week show 1,700 pounds of material
    were purchased in May at a total cost of 6,630.
    The material was used to make 1,000 Zippies in
    May.

AP 6,630 1,700 lbs AP 3.90 per lb MPV
(AP - SP) x AQ MPV (3.90 - 4.00) x 1,700
lbs. MPV -170 Favorable
Note that the authors use of /- is counter-
intuitive
42
Recording VariancesMaterials Price Variance

Price variance is recorded at time of purchase.
43
Computing VariancesMaterials Usage Variance
  • Hanson Inc. has the following material standard
    to manufacture one Zippy
  • 1.5 pounds per Zippy at 4.00 per pound
  • Records last week show 1,700 pounds of material
    were purchased in May at a total cost of 6,630.
    The material was used to make 1,000 Zippies in
    May.

SQ 1,000 units 1.5 lbs per unit SQ 1,500
lbs MUV (AQ - SQ) x SP MUV (1,700lbs -
1,500lbs) x 4.00 MUV 800 unfavorable
Materials Usage Variance
44
Recording VariancesMaterials Usage Variance

45
Recording VariancesMaterials Usage Variance

Usage variance is recorded at time of use.

Work in Process Inventory must always be debited
for the standard quantity X standard price (1,000
units X 1.5 lbs.) X 4.00 6,000
Can materials price and usage variances be added
to get a total materials variance?
46
Computing Variances
Now lets calculate standard cost variances for
direct labor.
47
Computing VariancesLabor Rate Variance
Hanson Inc. has the following labor standard to
manufacture one Zippy 1.5 standard hours per
Zippy at 6.00 per hour Payroll records show
1,450 hours were worked at a total labor cost of
8,990 to make 1,000 Zippies.
AR 8,990 1450 hours AR 6.20 per hour
LRV (AR - SR) X AH LRV (6.20 - 6.00) X
1,450 hrs LRV 290 unfavorable
Labor Rate Variance
48
Computing VariancesLabor Efficiency Variance
Hanson Inc. has the following labor standard to
manufacture one Zippy 1.5 standard hours per
Zippy at 6.00 per hour Payroll records show
1,450 hours were worked at a total labor cost of
8,990 to make 1,000 Zippies.
SH 1,000 units 1.5 hours per unit SH
1,500 hours LEV (AH - SH) X SR LEV (1,450
hrs - 1,500 hrs) X 6.00 LEV -300 favorable
Labor Efficiency Variance
49
Recording VariancesLabor Rate Efficiency
Variances
Note that unlike materials variances, both labor
variances are recorded at the same time. (i.e.,
when the payroll summary account is cleared out.)
50
Recording VariancesLabor Rate Efficiency
Variances

Source?
.


Work in Process Inventory must always be debited
for the standard quantity X standard price (1,000
units X 1.5 lbs.) X 6.00 9,000
51
Computing Variances
Now lets calculate standard cost variances for
manufacturing overhead.
52
Standard Overhead Rate
  • Overhead is applied to goods produced using a
    standard overhead rate.
  • Overhead rate is set prior to the start of the
    period.

Total budgeted overhead costat the standard
level of outputStandard level of output
Standard overhead rate per unit

53
Standard Overhead Rate
Contains a variable per unit component which
stays constant at all levels of activity.
Contains a fixed per unit component
whichdeclines as activitylevel increases.
Is a function of the projected volumelevel
chosen to determine the rate. (i.e., standard
level of output)
54
Overhead Variances
  • Budget Variance
  • Is calculated as the difference between total
    actual overhead cost and budgeted amount of
    overhead for the actual volume attained
  • Volume Variance
  • Is calculated as the difference between the
    budgeted amount of overhead for the actual
    volume level attained and the applied overhead
    at the standard level of output

55
Overhead Variances
AOH - BOH BOH -
Applied OH
AOH Actual Overhead BOH Budgeted Overhead
56
Overhead Variances
Budget Variance
VolumeVariance
Total Overhead Variance
57
Overhead Variances
Budget Variance
VolumeVariance
Total Overhead Variance
58
Overhead Variances
Budget Variance
VolumeVariance
Total Overhead Variance
59
Overhead Variances
  • Flexible budgets, showing budgeted amount of
    overhead for various levels of activity, are used
    to analyze overhead costs.

60
Overhead VariancesExample
  • Hanson, Inc. has the following flexible budget
    for overhead

Hanson applies overhead based on machine hour
activityand expects to produce 1,500 Zippies.
(i.e., a standard activity level of 3,000
machine hours)
61
Overhead VariancesExample
62
Overhead VariancesExample
  • Hansons actual production for the period was
    1,600 Zippies resulting in 3,200 standard machine
    hours. Actual total overhead cost for the period
    was 15,450.

Compute the overhead budget and volume variances.
63
Overhead VariancesExample
15,450
64
Overhead VariancesExample
15,450 9,000 fixed
3,200 hrs.


6,400 variable 5.00 per hr.
15,450 15,400
16,000
Budget variance50 unfavorable
Volume variance600 favorable
65
Overhead VariancesExample
Hansons flexible budget for overhead
Standard activity level
66
Overhead VariancesExample
Hansons flexible budget for overhead
Standard activity level
Actual volume level attained
67
Recording Overhead Variances
Overhead account is closed and both variances
are recorded at end of period in the same entry.
68
Investigating Variances
  • The decision to investigate a variance is based
    on
  • Dollar amount of variance.
  • Size of variance relative to cost incurred.
  • Controllability of cost associated with variance.
  • All of these relate to the Management by
    Exception concept
  • Variances may be interdependent.
  • Performance reports contain variances along with
    budgeted and actual cost data.

69
Variance Analysis andManagement by Exception
Now that I know all aboutstandard cost
variances, howdo I apply that managementby
exception concept?
70
Variance Analysis andManagement by Exception
DirectMaterial
Amount
DirectLabor
ManufacturingOverhead
Type of Product Cost
71
Variance Analysis andManagement by Exception
  • Possible guidelines are
  • Dollar amount or percentage of the standard
  • Controllability of the cost variance

72
Reporting Variances
73
Disposing of Variances
  • Variance may be closed entirely to Cost of Goods
    Sold (normal case for small variances) or
  • Variance may be closed by
    prorating to Work in Process, Finished Goods, and
    Cost of Goods Sold based on relative size of
    these accounts.

.
74
THE END
Write a Comment
User Comments (0)
About PowerShow.com