Title: JOA:Issues Challenges
1JOAIssues Challenges Governance of Inter se
relationship
- By
- J. Sagar Associates
- New Delhi, Mumbai Banglore
- New Delhi, December 10, 2004
2Designates an Operator
Rights/ Duties
JOA
Pools the rights of the Parties
Sets up OC
Authorization of expenditure
Financial security Default
3Outline
- The Context Interse allocation of Rights and
obligations amongst JOA Parties - Key JOA Issues
- Joint Operations
- Operating Committee
- Deemed Withdrawal
- Final Thoughts/Key Take Away
3
4Context
- JOA r/w PSC nominates an Operation to conduct
Petroleum Operation in the Contract Area on
behalf of the Consortium - Operator is akin to the lead project developer
with certain rights, duties and obligations to
conduct Joint Operations on behalf of the
Consortium - Operator binds the other Consortium members to
the Petroleum Operations under PSC subject to OC
and MC approval - Takes the lead in finalising the Work/ Appraisal
Programmes and finalises the POD on behalf of the
Consortium
4
5- RIGHTS AND OBLIGATIONS OF OPERATOR/NON-OPERATOR
6Rights of an Operator
- Operator shall have exclusive control of all
Joint Operations. - To conduct all joint operations in a diligent,
safe and efficient manner in accordance with good
and prudent oil field practices including
carrying out Petroleum Operations as per GIPP.
7Obligations of an Operator
- Perform the duties for the OC and prepare and
submit to them the proposed work programs,
budgets and AFEs. - Acquire all permits, consents etc. that may be
required under this JOA. - Allow the representatives of any of the parties
reasonable access to the Joint Operations and to
inspect all Joint Property and conduct financial
audits.
8Obligations of an Operator
- Maintain the PSC in full force and effect.
- To make prompt payment and discharge all
liabilities etc. in connection with joint
operations and keep all the joint property free
from encumbrances etc. - To make all periodic payments, taxes, fee and
other payment pertaining to Joint Operations.
9Obligations of an Operator
- To carry out the obligations of Contractor
pursuant to the PSC. - To represent the parties in all dealings with the
Govt. with respect to matters arising under the
PSC and JOA at MC meetings. - Furnishing expenses statement of joint operations
to the Non-Operator(s) and to raise cash calls. - Give access to the areas of joint operations with
the right to observe any and all Joint
Operations.
10Obligations of an Operator
- To defend the Non-operator any and all claims
etc, relating to Joint Operations. - Operator to maintain insurance under the PSC and
other laws.
11Rights of Non-Operator
- Right of reasonable access to the Joint
Operations and to inspect all Joint Property and
conduct financial audits. - Receive expenses statement of joint operations
from the Operator. - To receive from Operator various data and reports
related to the Joint Operations. - To have access to all other data acquired in the
conduct of Joint Operations.
12- KEY ISSUES JOINT OPERATIONS/ OPERATING COMMITTEE
13Key Issues Joint Operations
- Petroleum Operations in accordance with GIPP
HSE compliance - Transparent Data sharing
14Key Issues Operating Committee
- Conduct of the Parties Active vs Sleeping
- Scope of Petroleum Operations
- Finalisation of Plan of Development
15DEFAULT AND FORFEITURE
16Legal Perspective
- Why should there be a forfeiture provision?
- high investment risk.
- unique requirements of OG industry
- very high initial investment and estimation of
return at a very late stage. - requirement to make regular payments made by
operator to sub-contractors. - unfair to expect one party to carry financial
obligation. - parties receive proportional benefit from the PSC
hence they should also pay the expenses
accordingly. - All investments are already approved by the MC
having representation from all the parties.
17Legal Perspective
- What does a typical default and forfeiture
provision contemplate? - It says Operator shall make cash calls and the
Non-Operators are obligated to pay the cash calls
at that time without question. In case of non
payment of the cash calls or untimely payment of
cash calls, a defaulting party, may amongst other
remedies, have to forfeit its participating
interest and withdraw itself from the PSC and the
JOA.
18Legal Perspective
- What does the above mean?
- Operator to
- - make cash calls
- - which non-operators are obligated to pay
- - at that particular time
- - without question
-
- - untimely or non payment may lead to default,
and - - the defaulting party may
- - have to forfeit its participating interest
and withdraw from the PSC and JOA.
19Legal Perspective
- "Equity abhors a forfeiture.
- The object of "Equity" is to render justice more
completely by affording relief to a party based
on grounds of fundamental fairness and justice
where a court acting in law may not be able to
furnish such relief if the law does not allow it
to do so. - Courts do not want to take a property right away
from a party unless it is unavoidable. - Party seeking to enforce the forfeiture has an
uphill battle to have the forfeiture granted.
20Legal Perspective Compensation under Indian law
- Critical provisions are s. 73 and 74 of the
Indian Contract Act, 1872. - Law allows liquidated damages but not
penalty. - Section 73 Allows compensation for loss or
damage caused by breach of contract. - Section 74 Allows compensation for breach of
contract but this compensation shall not be more
than the penalty stipulated for in the agreement.
21- Damages payable on breach may be of the following
kinds - i. Genuine pre-estimate of liquidated damages
- ii. Liquidated damages based on a definitely
ascertainable and quantifiable formula - iii. Liquidated damages far beyond the actual
injury that would be suffered in the event of
breach and - iv. Penalty in the form of overtly estimate
damages. - The first two are recognised under Indian law
but last two are not.
22- Supreme Court has recently held in ONGC versus
Saw Pipes JT(2003) 3 SC 171 - When parties have expressly agreed that
recovery from the contractor for breach of
contract is pre-estimated genuine liquidated
damages and is not by way of penalty duly agreed
by the parties, there is no justifiable reason
for the arbitral tribunal to arrive at a
conclusion that still the purchaser should prove
loss suffered by it because of delay in supply of
goods.
23- However, the above case did not deal with a
situation when the pre-estimate figure under the
conract is itself a penalty.
24Conclusion
- Whether forfeiture is reasonable compensation
or penalty is not very clear. - Upon default, the defaulting partys interest in
the PSC and JOA may be withdrawn.
25Final Thoughts
- Transparent Data Sharing w.r.t Well Reports
Seismic Data Subsurface Analysis. - HSE Liability
- Non-Operator should play more active role
(especially non-EP) - Misrepresentation Material breach issues
26Thank YouAmit Kapur, PartnerVenkatesh R.
Prasad, Sr. AssociateVishnu Sudarsan, Associate