Title: PHOSEMCAL Detector Control System DCS for Front End Electronics
1PHOS/EMCAL Detector Control System (DCS) for
Front End Electronics
In alphabetical order
Sebastian Bablok, Abbie Bauer, Joseph
Butterworth, Per Thomas Hille, Dag Toppe Larsen,
Alexander Mammonov, Matthias Richter, Haakon
Rovik, Benjamin Stockert, Fei Fei Zou
Presenten by Per Thomas Hille
2Future system
PHOS DCS for frontend electronics
Current System
APD GUI
Configuration files
PC
1
Command encoder
Result decoder
Command data
Configuration Data base
BLOBs (SQL)
PC
Readback result
1
Fee Client (DIM)
1
Service info
Request service
Service data
Subscribe to service
Ethernet
DIM DNS
Command data
Detector
Register service
20
Outside world
Fee Server (DIM)
PHOS CE
Execute
DCS card
28
1
DCS/RCU Mezzanine
Command data
1
1
RCU backplane
RCU
Readback
3The PHOS beamtest setup July-August 2006 (grossly
simplified)
Beam trigger
PHOS Module
Dual D-rorc
Led trigger
Trigger
DCS RCU
DCS RCU
Pedestal trigger
Switch
Ethernet
DCS RCU
DCS RCU
4 DDL
DCS network (master fee-net)
DCS gateway
Cern network (lxplus)
DAQ Computer
GUI
4PABC GUIGraphical user interface to the
PHOS/EMCAL DCS software
5Preliminary result of the 2006 calibrationthe
first PHOS module is in operation
- Average working temperature of the PWO matrix ?
16oC - Number of calibrated detector channels 1825
- Gains of all the calibrated channels are equal
within ? 4 (?) - Preliminary relative energy resolution for 2 GeV
electrons (without fine tuning the gains) ? 5. - At ? 16oC an average APD bias voltage ? 350 V,
all the bias voltages are below 400 V ? will be
even lower at ? 25oC - Some problems were found ? to be fixed in
September
The module at T10 beam-line
Position of the calibrated channels (2/8 on top
could not be reached with the beam, 1/8 had the
HV problem)
Channel gains at final APD bias voltages (2 GeV
electron peak position)
Relative energy resolution (very preliminary)
Final APD bias voltage
6(No Transcript)
7DCS achievements before and during PHOS
comissioning beamtest
- APD bias controll.
- Sucessfull calibration of 1825 channels.
- Graphical user interface to DCS software/APD bias
control made in ROOT. - Database for APD bias settings
- Interaction with the database from the PABC GUI
- PVSS
- The full communication chain from the feeservers
running on the DCS cards to PVSS (Thanks to Abbie
Bauer and Joseph Butterworth). - Monitoring of simulated temperatures on the
feeserver - New BC firmware that allows communication via
the RCU slow control unit (Fei Fei Zou)
8Status of PVSS/FSM integration
- FEE Monitoring in PVSS
- Communication chain from the DCS cards to PVSS is
implementet (thanks to Abbie and Joey), but
currently only with monitoring of simulated
temperatures due to hardware problems of the FEE. - Status Not finnished and not in Progress
- FEE Configuration from PVSS
- Low level software is implemented and was
sucessfylly used during beamtest. Configuration
with dedicated software, but not yet via PVSS. - Status In progress
-
9Remaining Tasks
- Development of software for the feeserver to
communicate with the PHOS version of the slow
controll. - When Depends on when PHOS module will be
available for testing. - Responsible Dag Toppe Larse Per T (side
activity) - Communication via PVSS with the PHOS/EMCAL DCS
software. - When January 2007
- Responsible Per T (Only the communication chain)
- PVSS FSM implemantion of the whole DCS system.
- When ?
- Responsible Michail Bugolovski Alexander
Mammonov
10Summary
- Significant progress on the DCS implemetation
during beamtest preparation and beamtest. Most of
the bits and pieces are working, but it is not
yet one integrated system. - We dont have any monitoring of the electronics
- It is to few indians to have all the work done in
time. - The electronics for PHOS is identical to EMCAL.
We shoud take advantage of that and try to do as
much as possible in a common effort. - We should try to reuse as much as possible of the
TPC DCS system. -