Title: Activity Based Costing
1Activity Based Costing
2Activity Based Costing (ABC)
Both manufacturing and nonmanufacturing costs may
be assigned to products.
Some manufacturing costs may be excluded from
product costs.
Overhead rates may be based on activity at
capacity.
3Plantwide Overhead Rate
Companies tend to use direct labor as the
overhead allocation base. There is a belief that
direct labor and overhead costs are highly
correlated.
4Departmental Overhead Rates
Finishing Department
Many companies have a systemin which each
department hasits own overhead rate. In such
cases, the overhead driver also may differ across
departments.
Painting Department
Shipping Department
5Departmental Overhead Rates
Stage One Costs assigned to pools
Overhead
Department 1
Department 2
Department 3
Cost pools
Direct Labor Hours
Machine Hours
Raw Materials Cost
Stage Two Costs applied to products
Products
Departmental Allocation Bases
6Activity-Based Overhead Rates
Overhead
Stage One Costs assigned to pools
Activity 1
Activity 2
Activity 3
Cost pools
Engineering Change orders
Shipping Locations
Stage Two Costs applied to products
Customer orders
Products
Activity cost driver
7Designing of an ABC System
- Steps for Implementing ABC
- Identify and define activities and activity cost
pools. - Assign actual costs to activity cost pools.
- Calculate activity cost rates per driver unit.
- Assign costs to cost objects based on driver
usage.
8?Identify and Define Activities and Activity Cost
Pools
- Each Activity Cost Pool is a bucket in which
costs are accumulated that relate to a single
activity measure in the ABC system.
9?Identify and Define Activities and Activity Cost
Pools
- Customer Orders - assigned all costs of resources
that are consumed by taking and processing
customer orders. - Product Designs - assigned all costs of resources
consumed by designing products. - Order Size - assigned all costs of resources
consumed as a consequence of the number of units
produced. - Customer Relations assigned all costs
associated with maintaining relations with
customers. - Other assigned all overhead costs that are not
associated with the other cost pools.
10Functional Listing of Overhead Costs
11?Determine the Distribution of Costs to Activity
Cost Pools
Assume that the following distribution of
resource consumption across activity cost pools
is determined.
Not included because they are directly traced
to customer orders.
12?Assign Costs to Activity Cost Pools
13?Calculate Activity Rates
- The ABC team determines that the company will
have these total activities for each activity
cost pool . . . - 1,000 customer orders
- 200 new designs
- 20,000 machine-hours
- 100 customer relations activities
Now the team can compute the individual activity
rates by dividing the total cost for each
activity by the total activity levels.
14?Calculate Activity Rates
15Activity-Based Costing Stage 1
Overhead Costs
First-Stage Allocation
Order Size
Customer Orders
Product Design
Customer Relations
Other
Cost Objects Products, Customer Orders, Customers
16Activity-Based Costing Stage 2
Overhead Costs
First-Stage Allocation
Order Size
Customer Orders
Product Design
Customer Relations
Other
Second-Stage Allocations
/MH
/Order
/Design
/Customer
Cost Objects Products, Customer Orders, Customers
Unallocated