Schedule - PowerPoint PPT Presentation

1 / 77
About This Presentation
Title:

Schedule

Description:

Purpose and planned duration of the installation ... The wiring system should be selected and erected so that no damage is caused by ... – PowerPoint PPT presentation

Number of Views:177
Avg rating:3.0/5.0
Slides: 78
Provided by: Aqu55
Category:

less

Transcript and Presenter's Notes

Title: Schedule


1
Schedule
2
Introduction
Load Estimation
Terminology
Basic Equipment
Codes and Standards
Power Distribution Final Circuit
Standby Generator and Power Supplies
Protection Cable Wiring
Earthing
Design of Electricity Distribution
3
Power Distribution Final Circuit
  • Date 6 Nov 2008

4
Question
  • What kind of factors affecting the choice of
    wiring system?

5
Power Distribution and Wiring System - 1
  • Installation Cost
  • Purpose and planned duration of the installation
  • Environment factors and installation conditions
  • Type of building construction
  • Flexibility of the system and circuit arrangement
  • Appearance of the finished installation
  • Safety aspect
  • Nature of power supply and type of earthing
    system

6
Installation at High Humidity Environment - 2
  • The wiring system should be selected and erected
    so that no damage is caused by high humidity or
    ingress of water during installation, use and
    maintenance.
  • All joint should be suitably insulated and
    protected against the effects of moisture or
    water. Copperclad aluminum conductors should not
    be used.
  • Every entry to finished ducts or trunking should
    be placed so as to prevent the ingress of water
    or be protected against such ingress. Where water
    may collect or condensation may form in a wiring
    system, provisions should be made to drain it
    away.

7
Installation at Adverse Ambient Temperature - 1
  • The wiring system including cables and wiring
    accessories, should be suitable for the highest
    and lowest ambient temperature that likely to
    encountered.
  • The electrical insulation shall withstand the
    maximum permissible operating temperature of the
    class of insulation to BS 2757.

8
Installation at Adverse Ambient Temperature - 2
  • For general-purpose PVC cable, the maximum
    permissible conductor of operating temperature is
    70oC and the maximum permissible ambient
    temperature is 65oC.
  • In every vertical trunking or duct wiring
    installations, suitable internal barriers sould
    be provided between floors or at intervals of 5m
    whichever is the less.

9
Installation at Adverse Ambient Temperature - 3
  • Suitable measures shall be provided to avoid the
    effects of heat from external source including
    solar gain such as shielding or placing
    sufficiently far from the source of heat or
    selecting insulation suitable for those
    temperature.

10
Index of Protection
  • The code that specifies the protection of
    encloses that can be used within certain
    environment. The first numeral indicate the
    protection against ingress of solid bodies. The
    second number indicate the protection against the
    ingress of liquids.

IP XX
11
(No Transcript)
12
(No Transcript)
13
(No Transcript)
14
Index of Protection
  • General Use
  • Indoor Use IP2X
  • Outdoor Use IP54 (Weather-proof)

15
Application of Wiring System
16
Typical Schematic Wiring Diagram for Internal
Power Distribution System
17
General Requirement of Internal Power
Distribution System
  • a) Basic Requirements
  • b) High Voltage Distribution
  • c) Mains
  • d) Sub - Main
  • e) Lateral Main
  • f) Installation Methods of Cables

18
General Requirement of Internal Power
Distribution System
  • a) Basic Requirements 1
  • Every installation shall be divided into circuits
    as necessary to avoid danger in the event of a
    fault, and to facilitate safe operation,
    inspection, testing and maintenance. Each circuit
    should be separately protected by an overcurrent
    protective device. Separate circuits shall be
    provided for parts of the installation which need
    to be separately controlled in such a way that
    these circuits are not affected by failure of
    other circuits.

19
General Requirement of Internal Power
Distribution System
  • a) Basic Requirements 2
  • Protective devices of each circuit should be
    clearly labelled or identified so that the rating
    of the devices and circuits they protect can be
    easily recognized.

20
General Requirement of Internal Power
Distribution System
  • B) High Voltage Distribution-1
  • Although residential and the majority of
    commercial installations are adequately served
    from LV-intake or HV-intake-LV distribution,
    there are many industrial and some large
    commercial development projects require HV intake
    with extensive HV distribution system through the
    sites or buildings.
  • For example, a hospital or an university with a
    large campus, a cross harbor tunnel with
    high-tension motors for ventilation fans, a very
    large commercial block and a large factory with
    several electrode boilers.
  • For these, the power company provides the main
    supply point through its own switchgear complete
    with bulk metering, and the customer is then
    responsible for the installation of suitable high
    voltage switchgear, all cabling and the required
    number of on-site substations.

21
General Requirement of Internal Power
Distribution System
  • B) HV Ring Main Distribution system
  • Just similar to the ring main system which used
    by power company in their 11kV network

22
General Requirement of Internal Power
Distribution System
Standard method of ring main connection mixed
with radial feeding
23
General Requirement of Internal Power
Distribution System
  • B) Advantage of HV Ring Main Distribution system
  • Even in the event of a cable fault on the ring,
    it is still possible to maintain or restore
    supply to all points by opening the switches on
    both sides of the fault.
  • Additional outlets to the ring may be easily
    installed without shut downs.
  • Greater maintenance facilities are available both
    on the ring feeder circuit breakers and the RMUs.
  • In additional, if the main HV switchboard is
    sectionalized and fed from more than one
    suppliers substations, a ring main may be
    supplied from two different sections, thus
    improving security.
  • Apart from fault conditions, it is also possible
    to operate a ring main in open mode as the
    preferred arrangement but, for whatever purpose
    it must be ensured that neither of the section is
    overload.

24
General Requirement of Internal Power
Distribution System
  • c) Mains - 1
  • Consumer main switch shall be installed and
    connected immediately before the supply co.s
    meter.
  • A common main switch shall be installed to
    control all the communal installation of the same
    consumer.
  • The consumer main switch should incorporate
  • Means of isolation and switching
  • Means of protection against overcurrent, and
  • Means of protection against earth leakage.

25
General Requirement of Internal Power
Distribution System
  • c) Mains - 2
  • The main switch or circuit breaker shall have a
    short-circuit breaking capacity of 40kA at low
    voltage.
  • The characteristic of the main switch shall
    disconnect within 5 seconds during an earth
    fault.
  • The switchboard shall incorporate Castell key
    interlock or other means to prevent the supply
    transformers operated in parallel. All
    interconnecting devices including the bus-section
    switch shall be of 4-pole type with electrical
    and mechanical interlock.

26
General Requirement of Internal Power
Distribution System
  • c) Mains - 3
  • Where standby generator is installed,
    mechanically interlocked 4-pole changeover device
    shall be used for interconnection between the
    normal and standby source. A local switch shall
    be installed after a changeover device.
  • Single phase consumer main switch shall be of
    double pole type.
  • A schematic wiring diagram showing the main
    distribution system should be displayed near the
    main switch with rating 100A or above.

27
General Requirement of Internal Power
Distribution System
  • c) Mains - 4
  • Each consumer installation shall provided his own
    earthing system
  • For 3 phase installation with main switch rating
    of 160A and above, C.T. operated meter shall be
    installed.
  • Warning Notice DANGER-ELECTRICITY, UNAUTHORISED
    ENTRY PROHIBITED with Chinese translation shall
    be painted or engraved on plastic boards
    permanently fixed outside the door of
    switchrooms. Each character shall not less than
    50mm high.

28
General Requirement of Internal Power
Distribution System
  • c) Mains - 5
  • The mina earthing terminal of the installation
    should be bonded by a conductor of not less than
    150mm2 copper to the electricity suppliers
    transformer earth or metallic sheaths of service
    cable.

29
General Requirement of Internal Power
Distribution System
  • c) LV Distribution-1
  • LV distribution exist in nearly all electrical
    installations.
  • Nearly all LV distribution are in radial from.
  • The greater the impedance of the cable from the
    secondary of the transformer to the LV
    switchboard, the less be the potential
    short-circuit current, and therefore these cables
    should not be larger than necessary.
  • If two 1500kVA transformer were connected in
    parallel, then the potential fault current could
    be as much as 60MVA. As this exceeds the breaking
    capacity of most standard LV switchboards ( which
    is usually only 31 MVA, it would entail the
    installation of much more expensive switchboard
    or special high-reactance transformers, or split
    the LV main switchboards into two or more
    separate sections, each section being fed from a
    transformer not exceeding 1500kVA.

30
General Requirement of Internal Power
Distribution System
  • c) LV Distribution-2
  • The greater the impedance of the cable from the
    secondary of the transformer to the LV
    switchboard, the less be the potential
    short-circuit current, and therefore these cables
    should not be larger than necessary.
  • If two 1500kVA transformer were connected in
    parallel, then the potential fault current could
    be as much as 60MVA. As this exceeds the breaking
    capacity of most standard LV switchboards ( which
    is usually only 31 MVA, it would entail the
    installation of much more expensive switchboard
    or special high-reactance transformers, or split
    the LV main switchboards into two or more
    separate sections, each section being fed from a
    transformer not exceeding 1500kVA.

31
General Requirement of Internal Power
Distribution System
  • c) LV Distribution-3
  • If sectionised is used in switchboard interlocked
    bus-section switches should be provided

32
Typical ring main feeding six distribution boards
33
Radial distribution diagram for typical small
commercial building meters on each floor if
required
34
General Requirement of Internal Power
Distribution System
  • C) Rising Mains-1
  • 1) Cable, including prefabricated tee-off cable.
  • The selection of cable as rising mains is usually
    limited by its current carrying capacity (CCC)
  • The cable may be single-core insulted cable, or
    multi-core armoured cable.
  • For single-core, p.v.c.-insulated. Non-armoured
    cable, the largest cross sectional area is
    1000mm2 giving a CCC of 1200A.
  • As a rule of thumb, when the demand exceeds 800A,
    busduct is preferred.

35
General Requirement of Internal Power
Distribution System
  • c) Rising Mains-2
  • 2) Insulated busduct (or busbar) system,
    including feeder type and plug-in type busduct.
  • The rating of busduct could be up to 5000A or
    even higher. The provision of plug-in unit
    provide flexibility for tee-off at any location/
    floor at anytime when demand required.
  • The bus may be insulated conductor or bare
    conductors totally enclosed in continuous steel
    trunking.

36
General Requirement of Internal Power
Distribution System
  • c) Rising Mains-3
  • The following factors affect the selection of the
    type of rising main
  • Load assessment
  • Load distribution
  • Environmental conditions such as ambient
    temperature and humidity
  • Heights of riser
  • Maximum allowable voltage drop
  • Fault level
  • Likelihood of alternation and future extension/
    expansion being frequently required
  • form, types and usage of the building
  • whether the wiring is to be installed during the
    construction of a building, in a completed
    building, or as and extension system.
  • Capital outlay required
  • Planned duration of installation

37
General Requirement of Internal Power
Distribution System
  • d) Sub-main - 1
  • Any building of more than four floors including
    the ground floor and designed for occupation of
    more than one consumer shall be provided with 3
    phase electrical rising mains with 3 phase and
    neutral tee-off at each floor
  • Type of rising mains could be one of the
    followings
  • Insulated conductors in trunking/ conduit
  • Armoured cables suitably supported
  • Bare conductors in trunking

38
General Requirement of Internal Power
Distribution System
  • d) Sub-main - 2
  • Each riding mains installation shall be protected
    against overcurrent and earth leakage and shall
    be equipped with suitable means of isolation.
  • For busbar installation having a rated capacity
    not exceeding 400A in each phase of a 3 phase 4
    wire system, the associated neutral busbar should
    have a cross-sectional area not less than the
    cross-sectional area of the phase busbar.

39
General Requirement of Internal Power
Distribution System
  • d) Sub-main - 3
  • Riser earthing conductor for multi-tenant
    installations shall be installed and the minimum
    size of riser earthing conductor is 70mm2 copper.
  • The loadings on 3 phase rising mains should be
    properly balanced. The neutral conductor should
    have a suitable current carrying capacity to
    cater for any imbalance or harmonic current.

40
General Requirement of Internal Power
Distribution System
  • d) Sub-main - 4
  • The design of rising mains installation should be
    agreed by the electricity supplier.
  • No part of the communal installation should pass
    through any individual consumers unit within the
    multi-consumer building.
  • No cable, other than that for lift installation
    governed by BS5655, shall be run in lift shaft.

41
General Requirement of Internal Power
Distribution System
  • e) Lateral Mains - 1
  • Adequate space for lateral mains and meter board
    wiring shall be provided in meter room.
  • The loading on 3 phase lateral mains should be
    balanced as far as practicable.
  • An installation requiring more than 60A is
    required to be arranged to service a 3-phase
    supply.
  • Appropriate correction factors shall be applied
    for determining the current carrying capacity of
    cables.

42
General Requirement of Internal Power
Distribution System
  • e) Lateral Mains - 2
  • Distribution board, switchgear and busbar chamber
    should have phase identification.
  • Where cables, conducts, ducts pass through
    structural element such as floors and walls, the
    openings shall be sealed by appropriate fire
    resistant materials. In addition, internal
    fire-resistant barriers shall be provided to
    prevent the spread of fire.
  • Segregation of low-voltage circuits, fire alarm
    circuits and telephone/ telecommunication
    circuits shall be made when they run together.

43
General Requirement of Internal Power
Distribution System
  • e) Lateral Mains - 3
  • Connection between the electricity suppliers
    meter and the consumers main switch should be
    not less than 4mm2 stranded copper conductor.
  • The insulation and/ or sheath of the cables shall
    be removed for a distance of 150mm from the
    connection, and replaced if necessary by suitable
    heat-resisting insulation when connecting the
    cable to bare conductors/ busbar.

44
General Requirement of Internal Power
Distribution System
  • e) Lateral Mains - 4
  • Warning notice DANGER in red legible letter
    with Chinese translation shall be displayed near
    each distribution board, Each character shall not
    less than 10mm high.
  • Where an installation is connected to rising
    mains, agreement should be obtained from the
    owner of rising mains if new current demand
    exceed that before. Moreover, prior approval from
    the power company should be obtained before any
    alteration work is carried out.

45
General Requirement of Internal Power
Distribution System
  • f) Installation methods of cables
  • According to he CP for WP or IEE Wiring
    Regulations, cables can be in the following ways
  • Open or clipped direct
  • Embedded direct in building ,materials
  • In conduit
  • In trucking
  • In free air, on cleats, brackets or ladder
  • In building voids
  • In trenched

46
General Requirement of Internal Power
Distribution System
  • What is a final circuit?

47
General Requirement of Internal Power
Distribution System
  • Definition of Final Circuit
  • A circuit connected directly to current using
    equipment, or to a socket outlet or other outlet
    points for the connection of such equipment.

48
General Requirement of Internal Power
Distribution System
  • Final Circuit Typical Arrangement 1
  • IEE Reg. 314-01-04 states that an installation
    comprises more than one final circuit, each shall
    be connected to a separate way in a distribution
    board and that the wiring to each final circuit
    shall be electrically separate from each other.

49
General Requirement of Internal Power
Distribution System
  • Final Circuit Typical Arrangement 2
  • Typical Arrangement shall be
  • Two lighting circuits to ensure the whole unit
    will not be in darkness if a fault occurs on one
    lighting circuit.
  • Circuit for 5A or 15A socket outlet to be fed by
    an exclusive radial final circuit. The maximum
    loading of each socket outlet shall be 5A or 15A
    respectively.

50
General Requirement of Internal Power
Distribution System
  • Final Circuit Typical Arrangement 3
  • Circuit for 13A socket outlets complying with
    BS1363.
  • Separate circuit for each large current-using
    appliance such as room cooler, cookre or kitchen
    appliance.
  • Lighting circuits should be electrically separate
    from power circuits except that it may be
    connected to bell transformers or electric
    clocks.

51
Conduit Wiring SystemType of Conduit
  • Steel Conduit to BS 4568 Part 1
  • A) Light duty type plain and conduits
  • Limited to use in dry situation
  • Unsuitable for bending
  • Low degree of mechanical protection
  • B) Heavy duty type screwed-end conduits
  • Back enamel for internal use in dry situation
  • Hot-dip galvanized for external use in situation
    subject to dampness or water condensation
  • Good mechanical strength and electrical
    continuity.

52
Conduit Wiring SystemType of Conduit
  • Steel Conduit to BS 4568 Part 1
  • C) Classification for protection

53
Conduit Wiring SystemType of Conduit
  • Steel Conduit to BS 4568 Part 1
  • D) Heavy duty hot-dip galvanized steel conduit
    system is the most common use system for surface
    conduit wiring and concealed conduit wiring.
    Conduit is supplied in standard lengths of 4
    meters and is manufactured in accordance with
    BS4568.

54
Conduit Wiring SystemType of Conduit
  • Plastic conduits
  • To BS4607 Part 1 and 2
  • Characteristics light, easily bend, less
    installation time, no water condensation, lower
    cost
  • Heavy duty PVC conduits can be concealed but CPC
    are required.

55
Conduit Wiring SystemType of Conduit
  • Copper Conduits
  • High resistance to corrosion
  • Last for long time
  • Higher cost
  • Act as excellent circuit protective conductor
    (CPC)

56
Conduit Wiring SystemType of Conduit
  • Aluminum Conduits
  • Light weight and lower cost
  • Not so good in mechanical protection
  • Flexible Conduits
  • To BS731 Part 1
  • Used for final connection to machinery
  • CPC are required.

57
Conduit Wiring SystemSizing of Conduit - 1
  • EMSDs COP for the Electricity (Wiring)
    Regulations provides the following tables for
    ease of conduit sizing
  • Table A, B for 1/C PVC cables in a straight run
    3m
  • Table C, D for 1/C PVC cable in conduit run gt 3m.
  • The conduit size is considered satisfactory if
    the conduit factor is equal to or exceeds the sum
    of the cable factors

58
Conduit Wiring SystemSizing of Conduit - 2
Table A Cable factors for short straight runs
59
Conduit Wiring SystemSizing of Conduit - 3
Table B Conduit factors for short straight runs
60
Conduit Wiring SystemSizing of Conduit - 4
Table C Cable factors for long straight runs,
or runs incorporating bends
61
Conduit Wiring SystemSizing of Conduit - 5
Refer to Table A and B
Table D Conduit factors for runs incorporating
bends
62
Conduit Wiring SystemSizing of Conduit - 6
  • Example
  • In a conduit installation the length of run is
    10m, assuming 2 right-angle bend. What is the
    conduit size to enclose four 2.5 mm2 PVC cables?
  • From Table C, factor for one 2.5mm2 cable 30
  • Therefore, four 2.5mm2 cables 4 x 30 120
  • From Table D, suitable conduit size with a factor
    of 141(gt120) is 20mm.
  • 10m Vs 2 bends, cable factor 141

63
Trunking Wiring System - 1
  • Use in conditions where a considerable no. of
    cables are required in an installation or where
    cables are too large for drawing into conduits.
  • Erection time is reduced (wiring is easier and
    quicker)
  • Multi-compartment trunking provides circuit
    segregation.

64
Trunking Wiring System - 2
  • Typical types of trunking
  • A) Steel trunking for busbar rising mains.
  • B) PVC skirting 3-compartment trunking for
    fitting-out wiring works where different category
    circuits such as Telephone cable, CABDS cable
    power supply cable are to be installed in same
    run.
  • C) Floor trunking to BS 4678 Part 2 provides
    cabling to service boxes flushed with floor level
    (e.g. in open-plan office or dental room)
  • D) Tap-on trunking in factory for internal power
    supply to machinery by plugging into the overhead
    trunking.
  • E) Steel surface trunking for cable to BS 4678
    Part 1

65
Trunking Wiring System - 3
  • Classification for protection against corrosion

66
Sizing of Trunking - 1
Table E Cable factors for trunking
67
Sizing of Trunking - 2
Table F Factors for trunking
68
Sizing of Trunking - 3
  • Example
  • What is the maximum no. of 10mm2 PVC cables
    permitted in 50mm x 50mm trunking?
  • From Table E, factor of 10mm2 conductor 36.3
  • From Table F, factor of 50 x 50mm trunking 1037
  • Maximum no. of cable 1037 36.3
  • 28.56 (say 28)

69
Ducting - 1
  • It provided mechanical protection for cable run
    in the ground or under concreted floor.
  • Types of ducting
  • Concrete ducts
  • Steel underfloor ducts
  • Fibre underfloor ducts
  • Maximum spacing factor is 35.
  • It should be securely fixed and protected against
    corrosion and mechanical damage.

70
Ducting - 2
  • Entries to duct must be protected against the
    inflow of water.
  • Cables installed in underground ducts shall have
    a metal sheath.
  • Underfloor trunking should be fabricated with
    sheet steel of not less than 12mm thickness for
    compartment width up to 100mm, but at least 1.6mm
    thickness for compartment width over 100mm. The
    minimum thickness of 1mm shall be used for the
    partitions and connector material.

71
Segregation of Circuits - 1
  • 1) Suitable segregation between enclosed circuits
    with different categories shall be provided in
    wiring. For example, a low voltage circuit shall
    be separated from an extra-low voltage circuit.
  • 2) Types of Circuit

72
Segregation of Circuits - 2
  • 3) Low Voltage circuit shall be segregated form
    extra-low voltage circuit. Extra-low voltage
    cables shall not be drawn into the same conduit
    or duct, or terminated in the same box or block
    as low voltage cables unless the former are
    insulated for the highest voltage present in the
    low voltage circuit.
  • 4) Cables of fire alarm and emergency lighting
    circuits shall not in any circumstances be drawn
    into the same conduit duct or ducting of other
    cables.

73
Segregation of Circuits - 3
  • 5) Electrical services shall not be installed
    with pipes or tubes of non-electrical services
    (e.g. air, gas, oil, or water) in the same
    conduit, ducting or trunking. This requirement
    does not apply where the various services are
    under common supervision and it is confirmed that
    no mutual detrimental influence can occur.
  • 6) For cables of category 1,2,3 circuits that are
    installed without enclosure or underground, a
    minimum separation of 50mm should be provided
    between different category circuits or
    alternatively at least 25mm separation with slabs
    of concrete inserted between the circuits and the
    shortest path round the concrete should exceed
    75mm.

74
Segregation of Circuits - 4
  • 7) Insulated bridge of at least 6mm thick should
    be used for separation of surface wiring of
    Category 1,2,3 circuit running across each other.
    The bridge should overlap the cables by at least
    25mm on either side of point of crossing.
  • 8) For cables of Category 4 circuit that are
    installed without enclosure or underground, a
    minimum separation of 300mm should be provided
    between Categories or alternatively a reduced
    separation with 50mm thick slabs of concrete
    inserted between the circuits and the shortest
    path round the concrete should exceed 180mm.

75
Standard Circuit for 13A Socket Outlet
  • The development of the BS1363 plug and socket
    system and the associated concept of ring circuit
    have made possible the provision of large numbers
    of socket outlets at lower installation costs.
  • All ring circuits shall be run in the form of a
    ring looping into the terminals of the socket
    outlets and returning to same protective device.
    The circuit protection conductor (cpc) should
    also be run in a ring unless it is provided in
    form of metallic conduit or trunking.
  • Typical standard circuits are tabulated as
    follows

76
Q A
77
The End
Write a Comment
User Comments (0)
About PowerShow.com