Title: 15 Jan 07 Hoarding erected
115 Jan 07 Hoarding erected
2Jan 07 Two piles of woodchips from vegetation
removed
323 Jan 07 Gathering topsoil for later use
4 30 Jan 07 Surface trees and hedges removed and
site leveled
5 07 Mar 07 Arrival of plant for piling
6 07 Mar 07 Site levelling before piling
715 Mar 07 Drilling piles 8m deep
815 Mar 07 Cement mixer and pump delivering
mixture to drilled pile position
915 Mar 07 400mm augur to drill contiguous piles
10 04 Apr 07 Excavating to the water table
1104 Apr 07 Excavating within piled area
1205 Apr 07 Aggregate delivery
1305 Apr 07 Sheeting the piling columns
1412 Apr 07 Completed basement groundworks
1512 Apr 07 Detail shows squares for deeper
foundations below pillars
1612 Apr 07 Leveling ground before basement steel
reinforcement is laid
1726 Apr 07 Architect inspecting the work
1826 Apr 07 Building the steel floor reinforcement
1906 Jun 07 Basement walls and columns
2006 Jun 07 Preparing cement shuttering for ground
floor
2116 Jul 07 Ground floor slab laid and start of
bricklaying
2206 Aug 07 Ramp to Basement
2306 Aug 07 Ground floor walls
going up !
2408 Oct 07 First floor
construction
2510 Oct 07 Ramp to Basement Car
Park
2610 Oct 07 Front wall and ramp to basement
car park
2710 Oct 07 Front wall and view of
Hospice
2802 Nov 07 Ready for Craning
2902 Nov 07 Roof construction
3002 Nov 07 Roof support beams
3102 Nov 07 Metsec roof lattice
3215 Nov 07 Roof boards on
3313 Dec 07 Roof Construction
3413 Dec 07 Crane no longer on site
3510 Jan 08 Pyramid window roof of Multi
Faith Room
3615 Feb 08 Basement Car Park 01
3715 Feb 08 Plant Room
3815 Feb 08 Inside view of a room
3915 Feb 08 Inside view of multi faith room
4015 Feb 08 Temporary offices on site