Title: ACMA Membership Survey
1Financing Issues in Hydro Power Projects
9th ASSOCHAM Energy Summit August 24, 2006 New
Delhi
Dhruba Purkayastha General Manager
2Contents Hydro Power Projects
Current Business Models
Financing Issues
3Hydro Power Projects ..the plus side
- Non fossil fuel clean power
- Lowest lifetime cost of power generation
- Effective tool for load variation management-peak
loads - Socio-economic development of remote areas
- Energy security
- No fuel linked inflationary pressures/input price
risks
4Policy directions are progressively ushering
competitive power sector market ..
- EA 2003 introducing
- Non-discriminatory open access to transmission at
least - ERCs to follow competitive bidding process
- CERC to advise GoI on promoting competition
- Controlling abuse of market power
- Competitive Bidding Guidelines
- Competitive acquisition of new generation
capacity - National Tariff Policy 2006
- Promoting retail competition
- Supporting competitive acquisition of generation
capacity - Enabling choice
- Supporting distribution reforms
Should work well with hydro projects also
5However there are some issues with hydro power
projects
- High capital costs, longer gestation periods
- Geological risks leading to increase in project
costs - Long delays in obtaining clearances land and R
R - Disputes between states locking up potential
- Rationalization of tariffs and tariff
determination mechanisms
6 Typical market analysis for creating generation
assets
- Current and forecasted demand supply position
- Merit order situation and likely projections
- Transmission constraints /corridor availability
- Credit worthiness of utilities /off-takers
- Typically would need a state wise analysis
7Contracting options for hydro power projects
- Merchant Power Plant
- Bidding in tariff based competitive bids to be
floated by Discoms - Long term sale of power to Traders
- Can be a combination of the above options
8Typical tariff estimation
Free power
Capital Cost
Design Energy
Cost Plus Tariff
Premium
Short Term
Saleable Tariff
Merit Order in Neighboring States
Transmission Cost
Long Term
9Likely saleable tariffs in some states
- Most of the long term agreements at lt Rs. 3/ unit
- Variable Charges lt Rs.2/unit
- But Merit Order needs to be projected
- Higher tariffs are unlikely
Note Only Variable charges Transmission
Charges, unit- paise/unit
10Short terms tariffs may be somewhat higher
- Since advent of trading, increase in prices
- 190 p/u to 350 p/u
- RTC - 350 p/u
- Peak- 400- 450 p/u
11Transmission Constraints may get eased over time
- In next 7 years 27700 MW of Interregional Link
Capacity addition planned - Substantial addition in North West, North- East
link and North- NE - Total Transmission Linkage from Northern Region
added by 15500 MW - But still intra-regional link capacity of
HP/Uttaranchal/NE with neighboring states need to
be validated along with the expansion plan
121. Merchant Hydro Power Plant Issues
- Merchant Plant with Long Term reservation of
Transmission network - For Hydro plant utilisation of Transmission
Network will be very low - In case of change in buyer the Transmission
Network might need to be reserved again - Un-viable option
- Merchant Plant with Short Term reservation of
Transmission network - Sale in short term - peaking season high
margins - Risk of transmission network availability- every
three months an issue - Feasible Option
132. Bidding in Tariff Based Competitive Bids
- Would need to compete with mine linked pit-head
coal based power plants - NE Hydro Plants - How will they compete in a
scenario where shortfall is in the western ,
northern and southern region ? - Case 1 Standard Bidding Documents still not
finalized by MoP ? - Tariff Structure Single Part or Two Part tariff
- Hydrological Risk ?
- Capacity Index / Incentive ?
- Peak power can be priced at margin
143.Long Term Agreement with Traders
- Traders can either participate in the tariff
based competitive bidding or can sell power in
short term - While selling in long term / tariff based
competitive bidding, what value addition a trader
can provide ? - Credit enhancement
- Bidding assistance
- Creating liquidity
- Need for power exchanges effective market
clearing mechanism
15Contents Hydro Power Projects
Current Business Models
Financing Issues
16Key Risks associated with Hydro Power Plants.1
- Development Phase
- Non-fulfillment of any of the Conditions
Precedent - Issues in getting Environmental Clearance
- Difficulties in Land Possession i.e. RR related
issues - Non-Availability of Financing
- Issues in upfront equity Infusion
- Lenders issues with capital cost/ construction
period in financial closure - Construction Phase
- Geological Risks
- Delay in CoD, shortfall in tested capacity
- Force Majeure, EPC contractor non-performance
- Change in law leading to increase in project
cost
17Key Risks associated with Hydro Power Plants 2
- Operation Phase
- Lower Capacity Index due to Force Majeure
- Change in Law leading to increase in additional
OM expenses and additional capital investment - Reduction in output of Power Plant
- Payment Default by procurer
- Exchange rate fluctuation
18Typical issues in financing infrastructure
- Size, tenure and uncertainty
- High transaction costs
- Improper risk allocation
- Need for efficient subsidization (in some
cases) - Lack of supportive legal and regulatory framework
-
19Supply side issues in Infrastructure financing
- Lack of long term funding sources
- Under developed debt markets
- Banks unable to prudently lend long term
- Absence of financial engineering/
instruments/credit enhancement - Securitization
- Bond insurance
- Risk guarantees
20Typical issues in financing infrastructure also
apply mostly to hydro power projects
- Improper risk allocation- design of
concessions/PPP - Lack of common enabling policy and regulatory
frame works - Lack of proper financial /lending instruments -
credit enhancement securitization, bond
insurance - Need for private equity .
21 Some questions in hydro power projects remain.
- Is it feasible to make the plant run as 100
Merchant Plant ? - Regulatory intervention is capital cost
determination for merchant hydro projects - Will there be a regulatory ceiling on the sale
price, even for selling it on short term ? - Feasibility of routing this power through a
trader /Absence of power exchanges - Reserving the transmission network without a
power purchase agreement/MoUs
22Thank you