PSR Section 8 - PowerPoint PPT Presentation

1 / 25
About This Presentation
Title:

PSR Section 8

Description:

Satellite Changes since Pre-Environmental Review. Current Mechanical Configuration ... on the exciter in the vertical configuration with the use of a head expander ... – PowerPoint PPT presentation

Number of Views:68
Avg rating:3.0/5.0
Slides: 26
Provided by: pete130
Category:
Tags: psr | expander | section

less

Transcript and Presenter's Notes

Title: PSR Section 8


1
Section 8 Mechanical
. . . Pete Alea Swales Aerospace
2
Topics
  • Satellite Changes since Pre-Environmental Review
  • Current Mechanical Configuration
  • Verification
  • Vibro-Acoustic Testing
  • Post Environmental Testing
  • Alignment Check
  • Solar Array Deployment
  • Loads Assessment
  • Mass Properties
  • Issues
  • Bay 4 Panel Replacement
  • AST rework and vibration test
  • Hyperion Connector Jackpost Rework

3
Satellite Changes since PER
  • Completed sub-system integration prior to
    vibro-acoustic testing
  • WARP
  • ACI Optics module and electronics
  • Flight Hyperion Instrument Electronics
  • Star Tracker
  • XPAA S-Band Antenna
  • Thermal Louver
  • Installed inserts into Bay 1 panel for WARP
    Star Tracker filter boxes
  • Mass mockups of the calorimeters were used during
    the environmental test program. Swales/GSFC
    flight calorimeters will be added to the exterior
    of the Bay 4 equipment panel on December 18, 1999

4
Current Mechanical Configuration
  • As of 11/18/99, the following components have
    been de-integrated
  • LFSA (returned to LM for rework) Thermal Louver
    (removed for flight battery integration)

5
Configuration Status
EO-1 Satellite in Clean tent at GSFC
6
Vibro-Acoustic Verification
  • Satellite environmental testing was performed in
    accordance with the following plans procedures
  • Modal Test SAI-PLAN-341
  • Shock Test SAI-PLAN-341 SAI-PROC-739
  • Vibration Test SAI-PLAN-307 SAI-PROC-739
  • Acoustic Test SAI-PLAN-320
  • Mass Properties SAI-PLAN-319 (Test planned for
    February 10, 2000)

7
Shock Test Overview
  • Two shock tests were conducted by lifting the
    satellite and TPAF approx. 3 and dropping the
    TPAF onto a foam pad
  • No major deviation to the satellite shock test
    plan or procedure was required
  • Launch vehicle contractor performed all clampband
    operations including installation of pyrotechnic
    devices

EO-1 Satellite Prior to Clampband Release
8
Shock Test Results Summary
  • The source shock level was measured to be approx
    1200 gs at the separation plane accelerometer
  • Shock response levels were generally below the
    max level specified in the EO-1 Verification Plan
    and Environmental Specification (SAI-SPEC-158)
  • Some exceedances were recorded on the nadir deck
    at the base of the ALI pallet. No impact to
    sub-system function or performance has been
    observed.

9
Vibration Test Overview
X-Axis Configuration
Y-Axis Configuration
Z-Axis Configuration
  • The sine vibration test was conducted in three
    axes. The satellite was subjected to protoflight
    sine levels 1.25 time maximum expected flight
    loads.
  • The X Y-axes test was performed on the C220
    lateral slip table and the Z-axis test on the
    exciter in the vertical configuration with the
    use of a head expander
  • The MAP Spacecraft vibration test fixture was
    used for this test along with the six force
    response transducers.

10
Test Limit Accelerations
  • Pre-Test analysis was performed to determine the
    correlation between the S/C the instrument CG
    response accelerations and the corresponding
    pre-selected measurement location
  • These levels were used during the test to
    limit/notch the test input levels

Limiting Response Accelerations
11
Vibration Test Specification
Pre-Test Unnotched Specification
Post-Test Notched Specification
12
Vibration Test Response Summary
13
Vibration Test Results
  • Test results are documented in Swales/EO-1 Test
    Summary Report (EO1-TSR-027) and the Vibration
    Facility Report ATAC-23-15-0821
  • Unexpected satellite dynamic response was
    observed during the vibration test. Pre-test
    predictions of the fundamental frequencies were
    16.8 17.9 Hz for the Y X axes bending modes.
    Testing showed the frequencies to be 21.8 23.9
    for Y X axes respectively.
  • This discrepancy was traced to the boundary
    conditions assumed between the conical transition
    adapter and zenith deck. The pre-test model
    assumed pinned boundary conditions for the bolted
    flange at the interface. In reality, this
    preloaded flange acts more like a clamped joint.
    When the model was changed to a clamped boundary
    condition, the fundamental frequencies increased
    to 20.4 Hz and 22.6 Hz for the Y and X axes -
    which is within 6 of the test frequencies.

14
Vibration Test Results (continued)
  • Another lateral mode of interest, a local
    Y-axis/theta-X mode of the Hyperion instrument,
    was predicted at 36.5 Hz with the pre-test model.
    During Y-axis testing, this mode occurred at
    42.5 Hz. When the boundary condition change
    discussed previously was made to the model, the
    analytical frequency increased to 38.1 Hz, which
    is now just 10 lower than the test frequency.
  • For the thrust axis, no axial mode of the
    spacecraft was predicted below 50 Hz. This was
    verified by the thrust axis testing which showed
    no significant axial responses below 50 Hz.

15
Vibration Test Conclusions
  • All the objectives of the test program were meet
  • Satellite aliveness test were performed at
    various times between axes with no major problems
    observed

16
Acoustic Test Overview
  • The acoustic test was performed on the integrated
    satellite in the GSFC acoustic test facility in
    Building 10
  • The satellite was lifted off the transportation
    dolly and raised into the center of the
    microphones acoustic field
  • No deviation to the satellite acoustic test plan
    was required

17
Acoustic Test Levels
18
Acoustic Test Response Summary
19
Acoustic Test Results
  • Test results are documented in Swales/EO-1 Test
    Summary Report (EO1-TSR-028) and the Acoustic
    Facility Test Report ATAC-21-07-1116
  • Desired test levels were achieved. Minor
    deviation in the higher frequencies acceptable
  • Highest measured response were recorded on the
    solar array panels
  • The post acoustic test solar array deployment was
    nominal
  • Satellite aliveness test was performed at the
    completion of the acoustic test with no major
    problems observed
  • All objectives of the test program were met

20
Pre/Post Environment Alignment Verification
  • Baseline alignment measurements were performed
    after all flight components were installed and
    prior to the start of environment testing
  • Alignment measurements were recorded for the IRU
    and star tracker w/r to the ACI Optical Cube
  • Post environment measurements were made to verify
    that component alignment was maintained

21
Flight Load Verification
  • Final flight loads analysis was completed by the
    launch vehicle contractor on 10/14/99
  • The side table compares the VLA loads to the
    previous coupled loads analysis 
  • The instrument and spacecraft loads are enveloped
    by the previous CLA
  • There were some local accelerations of components
    that are slightly higher in this load cycle, but
    are not considered significant

22
Satellite Mass Properties Summary
  • Subsystem weight were measured prior to
    installation on the satellite the solid model
    is updated based on latest measured weights
  • Inertia properties are calculated from solid
    model
  • Final satellite mass will be within flight
    allocation
  • Allocation 588 Kg
  • Projection 573 Kg

23
Satellite Mass Properties Plan
  • The satellite mass properties test plan,
    SAI-PLAN-319, has been created to provide the
    facility test requirements
  • The satellite center of gravity in the X-Y plane
    and the moment of inertia about the Z-axis will
    be measured and compared to the prediction from
    the CAD solid model
  • The test will be preformed on the Miller Mass
    Properties Table in Building 15 on February 10,
    2000
  • The satellite will be placed on the Thermal
    Vacuum Test fixture with the clampband installed

24
Mechanical Alignment Plan
  • Satellite ground alignment plan (SAI-PLAN-206)
    established system requirements
  • ALI ACI Optics Module has been co-aligned to
    within 2 arc-mins. The ACI OM was pinned to the
    satellite nadir deck
  • The following alignment measurements have been
    performed, at Swales, to establish the spacecraft
    primary reference frame
  • S/C MRC to S/C datums
  • S/C SRC to MRC
  • IRU SRC will be mapped to the S/C MRC star
    tracker reference cube, at the launch site
  • ALI HSA reference cubes will be mapped to the
    S/C MRC

25
Issues
  • None ! Currently there are no open mechanical
    problem reports!
  • No residual risk items remain for the satellite
    mechanical system
  • We are ready to ship !
Write a Comment
User Comments (0)
About PowerShow.com