Title: PSR Section 8
1Section 8 Mechanical
. . . Pete Alea Swales Aerospace
2Topics
- Satellite Changes since Pre-Environmental Review
- Current Mechanical Configuration
- Verification
- Vibro-Acoustic Testing
- Post Environmental Testing
- Alignment Check
- Solar Array Deployment
- Loads Assessment
- Mass Properties
- Issues
- Bay 4 Panel Replacement
- AST rework and vibration test
- Hyperion Connector Jackpost Rework
3Satellite Changes since PER
- Completed sub-system integration prior to
vibro-acoustic testing - WARP
- ACI Optics module and electronics
- Flight Hyperion Instrument Electronics
- Star Tracker
- XPAA S-Band Antenna
- Thermal Louver
- Installed inserts into Bay 1 panel for WARP
Star Tracker filter boxes - Mass mockups of the calorimeters were used during
the environmental test program. Swales/GSFC
flight calorimeters will be added to the exterior
of the Bay 4 equipment panel on December 18, 1999
4Current Mechanical Configuration
- As of 11/18/99, the following components have
been de-integrated - LFSA (returned to LM for rework) Thermal Louver
(removed for flight battery integration)
5Configuration Status
EO-1 Satellite in Clean tent at GSFC
6Vibro-Acoustic Verification
- Satellite environmental testing was performed in
accordance with the following plans procedures - Modal Test SAI-PLAN-341
- Shock Test SAI-PLAN-341 SAI-PROC-739
- Vibration Test SAI-PLAN-307 SAI-PROC-739
- Acoustic Test SAI-PLAN-320
- Mass Properties SAI-PLAN-319 (Test planned for
February 10, 2000)
7Shock Test Overview
- Two shock tests were conducted by lifting the
satellite and TPAF approx. 3 and dropping the
TPAF onto a foam pad - No major deviation to the satellite shock test
plan or procedure was required - Launch vehicle contractor performed all clampband
operations including installation of pyrotechnic
devices
EO-1 Satellite Prior to Clampband Release
8Shock Test Results Summary
- The source shock level was measured to be approx
1200 gs at the separation plane accelerometer - Shock response levels were generally below the
max level specified in the EO-1 Verification Plan
and Environmental Specification (SAI-SPEC-158) - Some exceedances were recorded on the nadir deck
at the base of the ALI pallet. No impact to
sub-system function or performance has been
observed.
9Vibration Test Overview
X-Axis Configuration
Y-Axis Configuration
Z-Axis Configuration
- The sine vibration test was conducted in three
axes. The satellite was subjected to protoflight
sine levels 1.25 time maximum expected flight
loads. - The X Y-axes test was performed on the C220
lateral slip table and the Z-axis test on the
exciter in the vertical configuration with the
use of a head expander - The MAP Spacecraft vibration test fixture was
used for this test along with the six force
response transducers.
10Test Limit Accelerations
- Pre-Test analysis was performed to determine the
correlation between the S/C the instrument CG
response accelerations and the corresponding
pre-selected measurement location - These levels were used during the test to
limit/notch the test input levels
Limiting Response Accelerations
11Vibration Test Specification
Pre-Test Unnotched Specification
Post-Test Notched Specification
12Vibration Test Response Summary
13Vibration Test Results
- Test results are documented in Swales/EO-1 Test
Summary Report (EO1-TSR-027) and the Vibration
Facility Report ATAC-23-15-0821 - Unexpected satellite dynamic response was
observed during the vibration test. Pre-test
predictions of the fundamental frequencies were
16.8 17.9 Hz for the Y X axes bending modes.
Testing showed the frequencies to be 21.8 23.9
for Y X axes respectively. - This discrepancy was traced to the boundary
conditions assumed between the conical transition
adapter and zenith deck. The pre-test model
assumed pinned boundary conditions for the bolted
flange at the interface. In reality, this
preloaded flange acts more like a clamped joint.
When the model was changed to a clamped boundary
condition, the fundamental frequencies increased
to 20.4 Hz and 22.6 Hz for the Y and X axes -
which is within 6 of the test frequencies.
14Vibration Test Results (continued)
- Another lateral mode of interest, a local
Y-axis/theta-X mode of the Hyperion instrument,
was predicted at 36.5 Hz with the pre-test model.
During Y-axis testing, this mode occurred at
42.5 Hz. When the boundary condition change
discussed previously was made to the model, the
analytical frequency increased to 38.1 Hz, which
is now just 10 lower than the test frequency. - For the thrust axis, no axial mode of the
spacecraft was predicted below 50 Hz. This was
verified by the thrust axis testing which showed
no significant axial responses below 50 Hz.
15Vibration Test Conclusions
- All the objectives of the test program were meet
- Satellite aliveness test were performed at
various times between axes with no major problems
observed
16Acoustic Test Overview
- The acoustic test was performed on the integrated
satellite in the GSFC acoustic test facility in
Building 10 - The satellite was lifted off the transportation
dolly and raised into the center of the
microphones acoustic field - No deviation to the satellite acoustic test plan
was required
17Acoustic Test Levels
18Acoustic Test Response Summary
19Acoustic Test Results
- Test results are documented in Swales/EO-1 Test
Summary Report (EO1-TSR-028) and the Acoustic
Facility Test Report ATAC-21-07-1116 - Desired test levels were achieved. Minor
deviation in the higher frequencies acceptable - Highest measured response were recorded on the
solar array panels - The post acoustic test solar array deployment was
nominal - Satellite aliveness test was performed at the
completion of the acoustic test with no major
problems observed - All objectives of the test program were met
20Pre/Post Environment Alignment Verification
- Baseline alignment measurements were performed
after all flight components were installed and
prior to the start of environment testing - Alignment measurements were recorded for the IRU
and star tracker w/r to the ACI Optical Cube - Post environment measurements were made to verify
that component alignment was maintained
21Flight Load Verification
- Final flight loads analysis was completed by the
launch vehicle contractor on 10/14/99 - The side table compares the VLA loads to the
previous coupled loads analysis - The instrument and spacecraft loads are enveloped
by the previous CLA - There were some local accelerations of components
that are slightly higher in this load cycle, but
are not considered significant
22Satellite Mass Properties Summary
- Subsystem weight were measured prior to
installation on the satellite the solid model
is updated based on latest measured weights - Inertia properties are calculated from solid
model - Final satellite mass will be within flight
allocation - Allocation 588 Kg
- Projection 573 Kg
23Satellite Mass Properties Plan
- The satellite mass properties test plan,
SAI-PLAN-319, has been created to provide the
facility test requirements - The satellite center of gravity in the X-Y plane
and the moment of inertia about the Z-axis will
be measured and compared to the prediction from
the CAD solid model - The test will be preformed on the Miller Mass
Properties Table in Building 15 on February 10,
2000 - The satellite will be placed on the Thermal
Vacuum Test fixture with the clampband installed
24Mechanical Alignment Plan
- Satellite ground alignment plan (SAI-PLAN-206)
established system requirements - ALI ACI Optics Module has been co-aligned to
within 2 arc-mins. The ACI OM was pinned to the
satellite nadir deck - The following alignment measurements have been
performed, at Swales, to establish the spacecraft
primary reference frame - S/C MRC to S/C datums
- S/C SRC to MRC
- IRU SRC will be mapped to the S/C MRC star
tracker reference cube, at the launch site - ALI HSA reference cubes will be mapped to the
S/C MRC
25Issues
- None ! Currently there are no open mechanical
problem reports! - No residual risk items remain for the satellite
mechanical system - We are ready to ship !