SERC Operator Training Y2k Status Update - PowerPoint PPT Presentation

1 / 24
About This Presentation
Title:

SERC Operator Training Y2k Status Update

Description:

VACAR North - Lou Roeder, Dan Desmond (Va Power) ... Crazies/Fanatics. Saboteurs. Self fulfilling prophecy. Other Risks - UNKNOWN ... – PowerPoint PPT presentation

Number of Views:70
Avg rating:3.0/5.0
Slides: 25
Provided by: e320
Category:

less

Transcript and Presenter's Notes

Title: SERC Operator Training Y2k Status Update


1
SERC Operator TrainingY2k Status Update
  • SERC Operator Training Seminars
  • Charleston, SC
  • April, 1999

2
Agenda
  • SERC Y2k Organization
  • Control Area and Operating Entity Plans
  • Plan Assessment and Coordination
  • SERC Risk Factors and Scenarios
  • Mitigation Strategies
  • System Studies
  • Work Plan
  • Interconnection and Continental Issues
  • What this means to YOU

3
SERC Y2k Organization
4
SERC Y2k Task Force
  • SERC Representation - John Troha
  • Security Coordinator Representation
  • Entergy - Francis Wang / Jim Case
  • Southern - Raymond Vice (Chairman)
  • TVA - James Regg, David Ashley
  • VACAR North - Lou Roeder, Dan Desmond (Va Power)
  • VACAR South - Brock Hennings / Scott Henry (Duke
    Power)
  • Other participants
  • CPL - Phil Creech
  • NCEMC - Mike Featham, Tony Vincik, Ken Kroll
  • Oglethorpe - Brad Leathers
  • Santee Cooper - Linda Wilcox
  • SCEG - Rocky Sease, Tommy Clawson, Jennifer
    Taylor
  • Sonat Power Marketing - Gordon Scott

5
Recent SERC Y2K Activities
  • 12/1/98 SERC Y2K Task Force initial meeting
  • 12/15/98 First draft of individual Y2K
    contingency plans by SERC members
  • 12/21/98 - 12/31/98 Completed assessment of
    individual Y2K contingency plans
  • 1/5/99 - 1/8/99 First draft (Rev. 1) of SERC
    contingency plan
  • 1/11/99 - 1/12/99 Discuss Y2K drills and
    update the work plan.
  • 1/16/99 Second draft (Rev. 2) of the SERC
    contingency plan released.
  • 1/25/99 - 1/26/99 Presented SERC contingency
    plan to NERC SCS Y2K Taskforce
  • 2/1/99 - 2/28/99 Review black start plans
    develop draft of SERC Black Start Coordination
    Procedure.
  • 3/1/99 Coordination of April 9 Y2K drill and
    addressed operational issues (black start,
    constant frequency operation, etc.).

6
SERC Y2k Contingency Planning Principles
  • Contingency Plans will be developed by SERC
    members using the NERC Contingency Planning Guide
    as a reference document
  • SERC Security Coordinators will facilitate
    development of Control Area plans.
  • SERC Y2k Contingency Planning TF will aggregate
    Control Area plans into the SERC Plan.
  • SERC members will cooperate with other regions to
    accomplish coordination of Contingency Plans on
    interregional and interconnection basis.

7
Operating Entity Contingency Plan Development
  • Each Operating Entity (OE) in SERC developed a
    Y2k contingency plan
  • OE s include all SERC Control Areas and Operating
    Entities with large loads and/or generation
  • Contingency Plans followed pattern of the NERC
    Contingency Planning Guide

8
Operating Entity Contingency Plan Assessment
Process
  • The OE plan assessment included all SERC Control
    Areas and Operating Entities with large loads
    and/or generation.
  • Each plan was assessed for completeness and
    quality for each step of the six step NERC Y2k
    Contingency Planning Process.
  • Strengths and Weaknesses were identified for each
    OE plan, and feedback was given.

9
Operating Entity Contingency Plan Assessment
Process
  • Each plan was assessed for completeness and
    quality for each step of the six step NERC Y2k
    Contingency Planning Process.
  • Identify Y2k Operating Risk
  • Scenario Risk Assessment
  • Develop Risk Management Strategies
  • General Preparations
  • Power System Operation Planning
  • Implementation of Y2k System Operating Plan
  • Strengths and Weaknesses were identified for each
    OE plan, and feedback was given.

10
SERC Operating Entity Contingency Plan
Completeness January 1999 Assessment
11
SERC Operating Entity Contingency Plan Quality
January 1999 Assessment
12
SERC Operating Entity Plans
  • Strengths
  • Risk Identification
  • Risk Mitigation Strategies
  • Followed the NERC Contingency Planning Guide
  • Areas for Improvement
  • Implementation Plans
  • System Study Scope
  • Restoration Coordination
  • Intra- and Inter-Regional backup control center
    communications

13
SERC Y2k Contingency Planning Status
  • All SERC Control Areas have started some level of
    contingency planning
  • The majority of SERC Control Areas have made
    strong progress into Steps 3 and 4
  • All SERC Control Areas have increased their
    contingency planning emphasis

14
SERC Scenario Analysis
  • The SERC Y2K task force identified general
    scenarios to be considered by each operating
    entity
  • The individual risk factors identified within
    SERC were used as the basis for these scenarios
  • Each individual operating entity was then
    responsible for developing appropriate and
    detailed scenario analysis for their system.
  • Coordination and review of these individual OE
    scenario analyses is being accomplished at the
    SERC level.

15
SERC Scenario Analysis
In general, the scenarios identified by the
operating entities within SERC fell into the
following categories
  • Loss of Generation (moderate / significant)
  • Loss of Transmission (partial / significant)
  • Loss of Load (moderate / significant)
  • Loss of Telecommunications - EMS/SCADA or voice
    (partial / significant)
  • Combination Scenarios
  • Loss of Generation, EMS/SCADA, communications
  • Loss of Generation, Loss of Transmission
  • System Restart

16
Proactive Mitigation Strategies (Operational
Strategies)
  • Generation
  • Development of a unit commitment and operating
    plan that will allow significant flexibility for
    various scenarios.
  • Recommend a limited number of planned transfers
    between control areas.
  • Minimize transaction schedule changes for
    critical Y2K periods.
  • Man essential system facilities
  • Make backup provisions for critical system data
    and voice communications
  • Identify procedures for validity checks of
    critical system data
  • Coordinate pumped hydro operation

17
Proactive Mitigation Strategies (Operational
Strategies)
  • Transmission
  • Man critical facilities
  • Minimize or eliminate planned facility outages
  • Instigate voltage control strategies
  • Review facility voltage schedules
  • Verify transmission devices (capacitors,
    reactors, etc.) are working properly and respond
    to control.
  • Develop procedures to adjust generation to
    support voltage.
  • Coordinate with Security Coordinators to reduce
    the effects of parallel and/or loop flows.
  • Identify procedures for validity checks of
    critical system data

18
Proactive Mitigation Strategies (Operational
Strategies)
  • Telecommunications
  • Establish backup communication procedures
    (control center to control center, control center
    to critical facility)
  • Establish backup facilities for critical system
    data and voice communications
  • Identify procedures for validity checks of
    critical system data
  • Perform training for backup communication
    procedures

19
System Studies
  • Minimum Load
  • Voltage Control
  • Islanding
  • Black Start
  • Underfrequency Operation
  • Transfer Capability
  • Load Loss
  • Transmission Congestion

20
System Studies
System Studies
MMWG
VST
SERC
Local
ü
ü
Minimum Load
ü
ü
ü
Voltage Control
ü
Islanding
ü
ü
Black Start
ü
ü
Underfrequency Operation
ü
ü
Transfer Capabilities
ü
ü
Loss of Load
ü
ü
Network Congestion
21
Contingency Planning Discoveries
  • EMS remediation/replacement efforts are critical
  • Backup communication is a concern
  • Current assessments continue to indicate that
    operating risks are low for Y2k periods
  • Consideration of time zone diversity is necessary

22
Spring 1999 Work Plan
23
Future Activities
  • Further coordinate intra-SERC contingency plans
  • Improve coordination efforts with neighboring
    regions
  • Identify operational efficiencies available by
    coordinated response
  • Review and coordinate SERC black start plans
  • April 9 Drill

24
What This Means to YOU
  • Technical Risks - Relatively Low but REAL
  • People Risks - UNKNOWN
  • Crazies/Fanatics
  • Saboteurs
  • Self fulfilling prophecy
  • Other Risks - UNKNOWN
  • Disruption of infrastructure
  • Legal Liabilities

25
What This Means to YOU
  • Y2K Drills Duties and Responsibilities
  • Man critical facilities
  • Manually calculate ACE and maneuver generation
    (simulation)
  • Manually monitor system security
  • Y2K Commitment and Dispatch
  • Carry extra reserves w/o bottom out
  • Hydro coordination
  • Least Risk Dispatch

26
What This Means to YOU
  • Holiday Vacation
  • Dont count on it!
  • Additional operators on shift
  • Support staff on site
  • Practice, Practice, Practice
  • If you aint sick of Y2K yet, you will be!
  • We MUST be ready whatever happen
Write a Comment
User Comments (0)
About PowerShow.com