Title: Airport CDM at Munich Airport


1
Airport CDM at Munich Airport
2
Airport CDM Munich Operational
Overview
  • 2 independent runways 26L/08R and 26R/08L in
    mixed mode
  • Apron control by Airport Operator (FMG) / Tower
    control by ATC (DFS)
  • De-Icing (98 remote) by EFM
  • 2006 410000 Movements Daily 1250

3
European Airport CDM General
Airport Collaborative Decison Making is an
operational overall process (concept/procedure)
supporting an optimized turnround process at an
airport. It is basis for connection to the
european ATM network
  • Airport CDM in Munich is based on the European
    Airport CDM developments
  • Implementation Manual / Operational Concept
    Document / Functional Requirements

EUROCONTROL AOE and CFMU have pro-actively
supported the Munich Airport CDM project
4
Airport CDM Munich Essential
procedure contents
  • Common Situational Awareness is assured
    !Transparency!
  • Airport CDM procedure MUC comprises the time
    frameATC-Flightplan activation (earliest
    EOBT-3h) until Take Off
  • Comparison and Correlation of ATC-Flightplan and
    Airport Slot
  • Matching and Correlation of related In- and
    Outbound Flight times and data
  • Automatically generation of Target Off Block Time
    (TOBT AO commitment)
  • Usage of Variable Taxi Time for Target time
    calculation
  • Variable Taxi time (Pos/Rwy/Direction)
  • Runway Delay (Season/Day/Hour)
  • Deicing time (if assigned)
  • Introduction of Target Start Up Approval Time
    (TSAT A-CDM commitment) as driver of the Pre
    Departure Sequence and the Departure Management
  • The TSAT is based TOBT, VTT, CTOT and operational
    capacity
  • Start Up clearance will be granted under
    consideration of TOBT and TSAT
  • Connection to CFMU through automated Data
    exchange(inbound estimates / Take Off Target
    times / CTOT adaptation to local target times)

5
Airport CDM Munich Procedure Overview
ATC-DPI (CTOT Freeze)
Early-DPI(FPL/Schedule-Comparison)
Target-DPI (ATTOT)(Slot Adjustment Window)
Information exchange via E-mail(i.e.
EOBT/SOBT-Mismatch Acft-Type Acft-Registration)
6
Airport CDM Munich FUM/DPI
Departure Planning Information Messages DPI -
general
  • Early DPI - 1st ETOT / Flight from CDM Airport
  • Target DPI - TTOT CTOT recalculation if
    possible/necessary
  • ATC DPI - TTOT CTOT freeze
  • Cancel DPI - Last DPI not valid
  • DPI are sent between EOBT-3h till ATOT for all
    flights (reg/non reg)

  • All DPI are generated automatically
  • Taxitime in DPI based on Variable Taxitime

Flight Update Message (FUM)
  • FUM - Estimated Landing Time (ELDT)
  • ELDT-3h prior to landing
  • Update ELDT of 5 min or more
  • Status change

7
Airport CDM Munich COMMUNICATION
CHANNELS
8
Airport CDM Munich DISPLAY AT ALL
AIRCRAFT STANDS
9
Airport CDM Munich
RESULTS
  • Very good involvement of operational partners
    TOBT update / Procedure adherence
  • Minor System adaptations necessary
  • Improved ground handling processes through
    reliable target times e.g. Gate/Positioning
    Push Back truck allocation etc.
  • Measured and proven decrease in taxitimes /
    waiting time at the runway Fuel / Environment
  • Reduction in controller workload (Ground/Apron
    Controller) optimized sequence
  • Lufthansa and its regional partner airlines
    optimized their coordination triangle HCC (ops),
    Flight crew and Ramp agent
  • Improved programmability for all operational
    processes (Airlines, Airport ATC) through
    reliable target times
  • Optimized use of available resources and
    capacities

10
Airport CDM Munich
RESULTS
  • Minor System adaptations for ETFMS necessary
  • FUM increases ELDT quality gt enhanced airport
    operation planning
  • Local Target take of times (DPI) needed for the
    potential CTOT recalculation
  • Increase in CTOT Adherence
  • DPI messages, Identification of Ghost Flight plan
    and less lost CTOT lead to better prediction of
    network traffic which can increase capacity
    (enroute, etc.)

11
Airport CDM Munich Quality
of local TTOT
10.5.07 xTOT vs. ATOT /- 5min window
/-10min window FPL ETOT 50 78
last Target-DPI 85 91 last
ATC-DPI 82 98
12
Airport CDM Munich DFS
Take Off Quality
Take Off Quality 2005 -3min, 27sec 2006 -2min,
49sec 2007 -1min, 08sec
13
Airport CDM Munich ATFM
Slot Adherence
14
Airport CDM Munich Waiting time for Takeoff
Waiting Time 2005 4min, 39sec 2006 4min,
17sec 2007 3min, 25sec
15
Airport CDM Munich Summary
16
Airport CDM Munich PUBLICATION
  • Munich Airport CDM www.munich-airport.de/cdm
  • Documents Munich Airport CDM

- ED AIP Volume II AD2-EDDM Local Traffic
Regulations
- Brief Description (Dispatch/Operations/etc.)
- Flight crew Description
- Leaflets Airport CDM Munich
- EEC Note 3/06 Airport CDM Munich
  • European Airport CDM www.euro-cdm.org

17
Airport CDM München
finally
  • Airport CDM is a procedure
  • Airport CDM is not a IT system
  • Airport CDM considers interests of all
    operational partner
  • Airport CDM is needed for the connection to
    european ATM network
  • Airport CDM is not expensive and not rocket
    science
  • Airport CDM is no blame culture
  • Airport CDM best planned best served