Closing the Bid - PowerPoint PPT Presentation

1 / 27
About This Presentation
Title:

Closing the Bid

Description:

The quantity takeoff, recaps, general expenses, and the summary sheet, with the ... Failure to do either will forfeit the bond. ... – PowerPoint PPT presentation

Number of Views:64
Avg rating:3.0/5.0
Slides: 28
Provided by: MOHA7
Category:
Tags: bid | closing | forfeit

less

Transcript and Presenter's Notes

Title: Closing the Bid


1
Closing the Bid
2
  • The objective in this stage is to ensure the
    completeness of the estimate and to assemble and
    submit the bid with all other required documents
    with.
  • A summary sheet can be prepared as a convenient
    tool to achieve this objective (See Figure 15.1)

3
(No Transcript)
4
Stages for completion of Bid
  • Advance Stage
  • Review Stage
  • Closing Stage

5
The Advance Stage
  • The quantity takeoff, recaps, general expenses,
    and the summary sheet, with the exception of the
    subcontractors prices, are completed
  • Unit prices and alternates prices for the
    contractors work are determined
  • The Bid Bond and other required documents by the
    Contract are prepared
  • The Bid Forms is completed and signed.

6
Unit Prices
  • The Contract documents may contain a Schedule of
    Work Items and the Contractor will be responsible
    for pricing these items (See Figure 15.2).
  • The prices are used for evaluating change orders

7
(No Transcript)
8
Example Calculating Unit Price for Concrete
Reinforced Beam Based on 100-ft Section
9
Alternates
  • Alternates are alternative features (e.g.
    differently specified material) proposed by the
    designer or the owner. The Contractor is required
    to price the original feature in the base bid as
    well as price the alternates.
  • The work may be performed by subcontractor and
    consequently the price may not come until late in
    the bidding process.
  • Alternates give the owner opportunity to
    investigate options based on the prices
    submitted.

10
(No Transcript)
11
Bid Bond
  • Often the contractor will be required to submit a
    bid bond along with the bid package
  • A bid bond (or bid guarantee) is a guarantee for
    the owner that if the bid is selected the
    contractor will enter into contract with the
    owner and submit a Performance Bond. Failure to
    do either will forfeit the bond.
  • If contractor does not submit the bond with the
    bid, he is disqualified

12
Bid Review
  • Objectives of Review
  • Make sure there are no obvious omissions or
    errors
  • Consider how the bid price can be made more
    competitive
  • Consider what the appropriate FEE for the project
    should be

13
Issues Discussed in the Review Meeting
  • Scope Is it all covered in the estimate?
  • Construction methods Are there more efficient
    methods?
  • Supervision What positions are needed? Are they
    available?
  • Labor What is the demand? Available?
  • Equipment What is needed? Available?
  • Risk Which items in the estimate considered
    risky?
  • Project OH What can be done to improve
    competitiveness?
  • Subcontractors Are there any anticipated
    problems?
  • Markup What is appropriate? What are the risks
    in the project?

14
Bid Markup
  • Bid markup is a fee added the previously
    estimated costs to determine the final Bid Price
  • It is made up of
  • Company Overhead
  • Profit

15
Company Overhead
  • Costs associated with conducting the business of
    the company but not directly related to the
    project
  • Rental or ownership cost of company offices
  • Office utilities
  • Furnishings and equipment
  • Salaries of executives and office personnel
  • Marketing
  • Accounting and legal consulting
  • Financial charges
  • Company travel

16
Determination of Overhead
  • Estimate company overhead per year
  • Estimate total projects value to be undertaken
    for the year
  • An overhead fee (percentage) is found as
  • Total OH per year Annual Projects Value

17
Example Allocating Company OH
  • Project Cost SR 4 millions
  • Annual Company OH SR 1,500,000
  • Total projects value for year SR 25 million
  • OH fee 1,500,000 / 25,000,000
  • 0.06
  • Company OH allocated to project
  • 0.06 x 4,000,000 SR 240,000

18
Profit
  • Profit is generally determined taking into
    considerations several factors
  • Organizations Minimum Required Rate of Return
  • Amount of risk involved in the project
  • Current commitments
  • Market situations and degree of competitiveness
  • Desirability of the project

19
Closing the Bid
  • During this stage some subcontract bids may still
    be incoming. Estimator need to review these bids,
    especially for any conditions that could impact
    the price. In that case the impact should be
    evaluated and added to the bid price.

20
Unit Price Bids
  • Unit price contracts differ from Lump sum
    contracts in that the contractor is not paid the
    quoted amount in the bid. The contractor is paid
    based on the quantities completed as priced by
    the quoted unit price.
  • In a unit price contract the contractor submits a
    Schedule of Prices which comprises an itemized
    breakdown of the project. The breakdown and the
    estimated quantities of each item are prepared by
    the Designer.

21
(No Transcript)
22
Procedure for Estimating Unit Prices
  • Takeoff As in the case of lump sum, unit price
    contracts are taken from contract drawings.
  • Recap
  • This is different from lump sum because recap
    need to be prepared according to the items in the
    Schedule of Prices. Each item is recapped
    individually.
  • Estimator must ensure that all tasks required to
    complete an item in the Schedule of Prices are
    included and priced.
  • Pay Quantity Unit price Contracts define a
    method of measurement for quantities. If the
    takeoff method used is different, the estimator
    need to make the necessary adjustment.

23
(No Transcript)
24
Procedure for Estimating Unit Prices (Continued)
  • General Expenses The total of the General
    Expenses is determined in the same manner as for
    Lump sum contracts. The total is then prorated
    over the items based on the items labor price.
  • Summary
  • (See Summary Sheet)

25
(No Transcript)
26
(No Transcript)
27
Unbalanced Bids
  • Unbalanced bids refers to the situation where the
    contractor does not quote the actual prices. The
    contractor increases the prices of some items
    (those that occur early in the schedule) and
    reduces prices of others (those that occur late
    in the schedule) to obtain the same total amount.
  • This practice is considered unethical and can
    result in the disqualification of the contractor.
Write a Comment
User Comments (0)
About PowerShow.com