GUNITING
by Noor Asyikin Sepiai
EDIT BY CKIEN
2
INTRODUCTION
3
  • What is guniting ?
  • Guniting is a mixture of cement,sand and water
    projected pneumatically at high velocity from a
    suitable nozzle onto the slope surface to produce
    a dense homogeneous protective layer.
  • gunite is a trade name for dry gunned
    concrete.
  • it means spray applied concrete. .
  • Commonly used as facing for steep nailed sloped.
  • Used dry mix with water cement ratio of 0.45 to
    0.5
  • Cement content not less than 350 kg/m³
  • The maximum aggregate size shall be less than
    10mm.

4
  • Function ?
  • Gunite is applied to the excavated slope surfaces
    at locations shown on the drawings or at
    locations directed by engineers.
  • Using guniting, concrete can be applied on
    irregular, vertical and overhead surfaces. This
    application is used commonly to protect slopes
    from erosion, as well as structures of large
    areas or uneven surfaces
  • Gunite is extremely strong, dense, and highly
    resistant to weathering and many forms of
    chemical attack. Gunite can be successfully
    applied to any desired thickness with uniform
    quality throughout.

5
Common gunite application
  • swimming pool construction
  • Refractory Installation
  • Rockscaping
  • Concrete Repair / Rehabilitation of Concrete and
    Masonry structures (bridges, walls, columns,
    beams, slabs, sewers)
  • Backfill (sand gravel)
  • Civil Infrastructure Projects
  • Channels, Piers, Sea Walls
  • Mines
  • Tunnel Lining
  • Slope Stabilization
  • Retaining Fire Walls
  • Concrete Pipe
  • Fireproofing for steel structures
  • Ditches

6
(No Transcript)
7
(No Transcript)
8
  • Quality finish
  • Distance of spraying should be about 0.6m to 1.5m
    from treatment surface.
  • Angle of spraying should as far as possible
    berpendicular to treatment surface.
  • Formed in successively from top down without gaps
    or slumps.
  • freshly gunite surface should be protected from
    rain or strong sunlight
  • Wet slope surface should be allowed to dry by
    covering with tarpaulin for a few days before
    guniting to ensure good bonding between gunite
    slope surface.

9
WORK SPECIFICATION
10
  • This works spec covers technical requirements for
    gunite mix,machine plant, surface preparation,
    method of operation, quality control works
    acceptance criteria.
  • Dry process
  • mixture of cement, aggregate and sand
    weighted / volume batched, throughly mixed dry
    and fed into a purpose-made machine where the
    mixture is suitably pressured, metered into a
    dry air stream and conveyed through hoses / piped
    to a nozzle before which water is introduced to
    hydrate the mix and is projected without
    interuption onto slope surfaces

11
MATERIAL
12
  • Cement
  • Cement shall be OPC and comply with the
    requirements of M.S. 522
  • Sand / Aggregate
  • Sand or aggregate shall be clean and durable, and
    free from clay or organic matters and other
    impurities.
  • Sand and aggregate shall be not more than 10mm
    and shall comply with requirement om M.S 29 and
    M.S 30.
  • Grading limits
  • 10mm sieve ------ 100 passing
  • 5.0mm sieve ------ 90-100 passing
  • 2.36mm sieve ------ 75-100 passing
  • 1.18mm sieve ------ 55-90 passing
  • 600µm sieve ------ 35-59 passing
  • 300µm sieve ------ 8- 30 passsing
  • 150µm sieve ------ 0-10 passing

13
  • c) Water
  • Clean
  • Free from harmful matter.
  • If test are required, they shall be in accordance
    with the requirements of M.S 28
  • d) Reinforcement
  • Unless, otherwise stated in the drawings steel
    fabric reinforcement shall be hard-drawn steel
    wire reinforcing fabric with wire diameter of
    6.0mm pitch of 200mm in the direction (BRC A6)
    and comply with requirements of M.S 145

14
  • e) Mix
  • Gunite shall has minimum cement content of 35kg
    per cubic meter and with water/cement ratio of
    not exceeding 0.5 by mass.
  • Mix proportion
  • shall be designed by contractor to achieve
    minimum grade 30 or the specified grade of
    strength and shall be approaved by engineer
    before commencement of works
  • Mix dry aggregate cement
  • which are not applied on slope surface within
    30 minutes after mixing shall be discharges
  • Admixture
  • added at 3-5 by weight of cement to speed
    the setting rate of cement, when directed by
    engineer.
  • All constituents shall be uniformly dispersed
    throughout mix. Mixing by hand is not allowed.

15
QUALIFICATION OF OPERATORS
16
  • Contractor shall certify or provide documentary
    evidence to the engineer on the satisfactory
    performances and experience of the intended
    foreman, nozzle man and delivery equipment
    operators for the guniting work.
  • Guniting operators shall gunite preconstruction
    panels for the Engineers assesment on skill and
    competence before acceptance of employment for
    guniting works.

17
PLANT AND EQUIPMENTS
18
  • Before commencement of work, it shall be submit
    to engineer for approval the type, make and
    number of plant and equipment to be used.
  • Drawing shown the proposed plant and works
    arrangement with brief description about the
    equipment, the method of operation and mix
    proportion, ect shall be included in the method
    statement as specified in clause 12(a)

19
(No Transcript)
20
(No Transcript)
21
PRECONSTRUCTION TEST PANELS
22
  • Propose
  • - To assess the quality of guniting(density,
    uniformity, strength, etc)
  • - To assess works output rate to ensure the
    resources for guniting works are satisfactory
    with respect to skill quality
  • Preconstruction testing
  • - using plant identification
  • - shall be undertaken in such time before
    commencemnet of the works to allow approval by
    the engineer.
  • Trial mixes
  • - each mix design shall be carried out by
    contractor.
  • - for each mix design, 3 number test panels of
    minimum size 750mm x 750mm x 100mm thick shall be
    sprayed from each position required in the works
    (down-hand,vertical,overhead position) with layer
    thickness appropriate to that position.
  • - panel mould shall be formed from 20mm thick
    plywood adequately braced and held rigidly in
    position.
  • - Test panel min size 750mm x 750mm x 100 mm
    thick shall be sprayed from each position
    required in the works.

23
INTERFACE PREPARATIONS
24
  • Earth or natural surfaces other than rock shall
    be compacted, trimmed and graded before guniting.
  • Earth surface shall be maintained or equilibrium
    moisture (not too wet or to dry before guniting).
  • Gunite shall not be applied on surface with loose
    or soft or wet materials. Wet surface (after
    rainfall) shall be covered by tarpauline for at
    least 2 days or until the surface moisture has
    moisture content within natural moisture content
    3 or as directed by engineers.
  • Rock surfaces shall be cleaned free from loose
    materials, mud of foreign matters.
  • Flow of water interferes with application of
    gunite or cause leaching of cement, the following
    water shall be directed by appropriate drainage
    channels to convenient locations where plugging
    can be carried out.
  • Reinforcement shall be cleaned and free from
    loose mild scale, loose rust, oil or other
    coating prior to the application of gunite.

25
Guniting for swimming pool
26
Guniting for Retaining wall
27
Guniting for drainage
28
References
  • Books workshop specification For Geotechnical
    works
  • http//www.monolithic.com/construction/shotcrete_g
    unite/
  • http//www.google.com.my/url?saXstart0oidefin
    eqhttp//www.needhamre-roofing.com/Glossary.htm
  • http//www.google.com.my/url?saXstart7oidefin
    eqhttp//www.parpool-spa.com/Page/Help/Water_Che
    mistry_Terms.html
  • http//www.reedpumps.com/gunite.htm
  • http//www.reedpumps.com/gunitepool.htm

29