Title: LER BBA: QUAD Shunt History
1LER BBA Quad Shunt Project
Marc Ross Doug McCormick Justin May Janice
Nelson Jerry Yocky Nicole Varela Juan Cruz Tonee
Smith
2LER BBA Retrospective
- Last fall a BBA program was initiated in both
PEP-II rings as part of a larger effort to
further understand the BPM performance. - HER results were successfully implemented, and
served to validate the BBA procedure. - LER results have also been implemented, but not
fully utilized. - Reanalysis of results with fully coupled
algorithm was needed. - IR2 results (the most important) have been
limited by lack of independent quadrupole control
3LER BBA Program goals
- To find the magnetic center of quadrupoles at
optically sensitive locations in the ring.
Shunts are used to vary the field in one magnet
which otherwise lacks individual control. - In IR2, there are four strings powering a total
of 14 quads QFCY1 (4), QDCY2 (4), QFCX3 (2),
QDCX2 (4) - Throughout the ring there are 37 individual QD
and QF (tune) quads which have been identified as
prime candidates for BBA. - These are in the arcs, immediately adjacent to
sextupoles - There are 2-5 quads per half-arc
4LER BBA Quad Shunt History
- In 1995, switchable shunt resistor circuits were
installed on each quadrupole in the SPEAR ring to
facilitate beam-based alignment. They were used
with great success. - These shunts were removed as part of the SPEAR3
upgrade, and the hardware was sent to Salvage. - The shunts were moved to B15 and proposals were
made to upgrade them for use in PEP-II (all
ultimately deemed too costly) . - The shunts were taken as is to NLCTA, cleaned up,
and tested on a LER Quad in Magnetic
Measurements. 42/45 were found to be fully
functional.
5LER BBA Quad shunt hardware
- The shunts consist of two high-power (250W)
resistors in parallel on a 1 copper heat sink,
controlled by an IDOM-driven FET switch.
6LER BBA Shunt Hardware details
- Water cooling unnecessary for our application
(resistors operating at 15 rated power on a
large thermal mass). - We have tested at 150 expected operating power
for 1 hour. Max temperature reached was 55ºC
without water cooling. - Design is simple yet robust, with a low mortality
rate even after months outside in Salvage. - Minor control board modifications (snubber
circuit) were made to protect the FET switches at
our operating values. - No-frills controls (24V, on/off, and
minimally-calibrated analog read back of shunt
current) allowed for a straightforward cable
plant.
7LER BBA Quad shunt installation
- We currently have 18 shunts installed on
individual QD and QF magnets throughout the ring. - High power resistor values 0.45 W and 0.55 W will
shunt 3 of an individual QD or QF magnets
current - These have been checked out on the bench (dummy
load and test stand magnet) and in the field (SCP
control) and are ready for BBA when PEP turns on
next year.
String Magnet R Mag I Mag V Shunt V Shunt R Shunt I Shunt Shunt P
QD(18) 0.019 300 5.7 4.2 0.45 9.3 3.11 39.2
0.019 300 5.7 4.2 0.55 7.6 2.55 32.1
QF(19) 0.019 300 5.7 4.2 0.45 9.3 3.11 39.2
0.019 300 5.7 4.2 0.55 7.6 2.55 32.1
8LER BBA Quad shunt inventory
- We have 8 of the IR2 shunts completed, three were
installed before the safety stand-down. - Resistors available off-the-shelf (18 W, giving 9
W shunts with two in parallel) will shunt 1.8-1.9
magnet current. - Resistors for the remaining 6 boards are on
order, we expect delivery this week. - These will also be 9 W shunts.
- Boards are ready, just awaiting resistor
delivery. - Cable plant is in place. Final checkout SCP ?
Shunt required.
9LER BBA IR2 Quad Shunts
String Magnet R Mag I Mag V Shunt V Shunt R Shunt I Shunt Shunt P
QFCY1.1 0.18 70 12.8 11.3 9 1.3 1.79 14.1
1.2 0.18 70 12.8 11.3 9 1.3 1.79 14.1
1.3 0.18 70 12.8 11.3 9 1.3 1.79 14.1
1.4 0.18 70 12.8 11.3 9 1.3 1.79 14.1
QDCY2.1 0.18 106 19.3 17.8 9 2.0 1.87 35.3
2.2 0.18 106 19.3 17.8 9 2.0 1.87 35.3
2.3 0.18 106 19.3 17.8 9 2.0 1.87 35.3
2.4 0.18 106 19.3 17.8 9 2.0 1.87 35.3
QFCX3.1 0.18 140 25.6 24.1 9 2.7 1.91 64.3
3.2 0.18 140 25.6 24.1 9 2.7 1.91 64.3
QDCX2.1 0.18 147 26.7 25.2 9 2.8 1.91 70.6
2.2 0.18 147 26.7 25.2 9 2.8 1.91 70.6
2.3 0.18 147 26.7 25.2 9 2.8 1.91 70.6
2.4 0.18 147 26.7 25.2 9 2.8 1.91 70.6
10Quad shunt installation, QD/QF
- We have installed 1-2 moveable shunts per
half-arc (2-4 shunts per IR/micro), based on
quad(/sext) population. - The shunts hook directly across the busses of a
quad with leads that bear an uncanny resemblance
to automotive jumper cables. - Shunt blocks/enclosures are grounded to the PEP
magnet rafts. - After a round of BBA, these shunts will be moved
at the next opportunity to a neighboring
candidate QD or QF. - Lather, rinse, repeat. (Two RODs to complete the
QD/QF magnets)
11Quad shunt installation, IR2
- We are planning to complete installation of one
shunt on each of the 14 QF/DCX/Y quads in IR2. - The shunts also hook directly across the busses
of the quads, but will not be moved from magnet
to magnet. - Modifications to the shunt covers have been made
to prevent contact with electrical hazards
within. - IR2 magnets are not PPS-interlocked, and the
shunts are not contained within existing magnet
covers. - We are prepared to install the eight we have
pending work approval, the remaining six as soon
as theyre ready.
12Quad shunt controls
- To the control system, the shunts look like
generic digital devices with a corresponding
analog readback. - Moveable shunts have names like PR04 SHUNT1, 2,
3 - One digital control (IDOM bit) per shunt (command
ON/OFF) - One status (ON/OFF) reflecting that IDOM bit
- One ASTS value reflecting current through the
shunt resistors - Not presently calibrated well enough to tell more
than whether the shunt is shunting or not,
really. - Weve requested that the shunt on/off status be
on the SDS CUD under LGPS with ON being RED.
13SCP Panel Analog display
14How it all works
- We are creating a flat file to hold the
information of which shunt is on which quad, with
a list at the bottom of which shunts can go to
which quads. - This file will live on the VAX with an entry in
e-log (which e-log to be determined) with its
location. - The person who physically moves the shunts to new
magnets is required to change this file. - For data acquisition, a button macro will prompt
which magnet or which shunt you wish to do BBA
on, then load up a CRR and take data. - Data to be analyzed offline by the Woodley/Wolski
coupled analysis matlab code.