Can we Maintain Grid Reliability Without Building Wires - PowerPoint PPT Presentation

1 / 14
About This Presentation
Title:

Can we Maintain Grid Reliability Without Building Wires

Description:

Can we Maintain Grid Reliability Without. Building Wires? Brian Silverstein ... Non-transmission alternatives, such as conservation, demand response, ... – PowerPoint PPT presentation

Number of Views:24
Avg rating:3.0/5.0
Slides: 15
Provided by: bls93
Category:

less

Transcript and Presenter's Notes

Title: Can we Maintain Grid Reliability Without Building Wires


1
Can we Maintain Grid Reliability Without
Building Wires?
  • Brian Silverstein
  • Manager of Network Planning
  • For more information see www2.transmission.bpa.gov
    /Projects/NonWire

2
(No Transcript)
3
Non-Transmission Alternatives
  • Non-transmission alternatives, such as
    conservation, demand response, distributed
    generation, and better siting of large generators
    can defer or reduce the need for transmission.
  • BPA targets for FY03
  • Establish an external Round Table
  • Implement a Demand Exchange Pilot Program
  • Complete detailed analysis for three projects
  • Identify and develop a plan to address
    institutional barriers

4
Multiple Screening
5
Using Screening Criteria
Project
Select Preferred Solution(s)
Not a good candidate for NCAs Focus on
transmission fix
6
Improving Understanding
Develop Screening Criteria
Pilot Programs
Project 1
Project 2
Project 3
Alternatives
Detailed Study
Alternatives
Objective to better understand measures and
institutional barriers to refine our tool kit
Objective to improve and simplify the
planning/analysis process
7
Olympic Peninsula Pilot
  • Objective is to reduce demand or generate power
    at strategic locations to reduce loading when
    needed.
  • Market Based reductions via Demand Exchange.
  • Web-based bidding technology.
  • Can be large individual loads (generation) or
    utility aggregated demand reductions
    (generation).
  • Metering to ensure that reduction (generation) is
    delivered.
  • Systems are in place, negotiations are underway
    and program will be exercised next year.

8
Kangley-Echo Lake Study
  • Objectives
  • Identify technologies that would be cost
    effective alternatives.
  • Evaluate the sensitivity of the cost
    effectiveness analysis to variations in key input
    assumptions.
  • Estimate whether achievable load reduction from
    those cost effective alternatives would be
    sufficient to defer the line.

9
Load Flow Distribution Factors
  • Load reduction at different locations will have a
    different effect on Covington transformer
    loadings due to network power flow interactions
  • Load weighted average distribution factor across
    Puget Sound Area is 32
  • 122MW required at Covington translates to 381MW
    within the Puget Sound Area

10
Study Results
  • Transmission avoided costs are low
  • 25 million of construction costs and 50,000 of
    annual OM costs
  • 1.5 million for a one year deferral
  • 12.25/kW-year at Covington or 3.92 /kW-year in
    the Puget Sound Area based on average load flow
    distribution factors
  • The economic value of the energy loss savings
    from the line is greater than the cost of the
    line
  • 11MW reduction of peak losses on the transmission
    system
  • Annual energy savings of 48,180MWh
  • 2 million at a market price of 40/MWh

11
Study Results
  • Demand Response (DR) is the most cost-effective
    alternative from a transmission rate perspective
  • DR focuses load reduction on only the hours when
    needed for system reliability
  • However, incentive levels are low compared to
    other programs
  • 3.92/kW-yr available for DR incentives
  • Range of incentives from surveyed programs
    4.80-128/kW-yr

12
Study Results
A high level of load reduction and additional
generation is required to defer the line
Load Relief and Generation Requirements for a
3-Year Deferral of the KEL Line
Base Case - 841MW (269MW) Winter 2005-2006 Load
Reduction Requirement within Puget Sound Area
100 of Potential 234MW (75 MW)
28 of Potential 1,380MW (125MW)
100 of Potential 277MW (70MW)
Load Relief Aluminum Smelter
Operation of Existing Local Generation
Load Relief from Area Industrial Load
( xMW) reduction at Covington
13
Round Table
  • To provide insights from a broad stakeholder base
    to ensure that BPAs transmission planning
    process is balanced.
  • To provide a forum for identifying and responding
    to key issues.
  • To address institutional issues that go beyond
    BPA.
  • To help build regional confidence and acceptance
    for a new approach to transmission planning.

14
Institutional Barriers
  • Who pays, who implements and how to capture
    economic value of measures
  • Lack of transparency in transmission planning
  • Lack of incentives to do accurate forecasting
  • Lost revenues for transmission provider and
    distribution utilities
  • Inaccurate peak-load price signals for energy and
    TD customers
  • Uncertainty about reliability of measures
Write a Comment
User Comments (0)
About PowerShow.com