Title: Can we Maintain Grid Reliability Without Building Wires
1Can we Maintain Grid Reliability Without
Building Wires?
- Brian Silverstein
- Manager of Network Planning
- For more information see www2.transmission.bpa.gov
/Projects/NonWire
2(No Transcript)
3Non-Transmission Alternatives
- Non-transmission alternatives, such as
conservation, demand response, distributed
generation, and better siting of large generators
can defer or reduce the need for transmission. - BPA targets for FY03
- Establish an external Round Table
- Implement a Demand Exchange Pilot Program
- Complete detailed analysis for three projects
- Identify and develop a plan to address
institutional barriers
4Multiple Screening
5Using Screening Criteria
Project
Select Preferred Solution(s)
Not a good candidate for NCAs Focus on
transmission fix
6Improving Understanding
Develop Screening Criteria
Pilot Programs
Project 1
Project 2
Project 3
Alternatives
Detailed Study
Alternatives
Objective to better understand measures and
institutional barriers to refine our tool kit
Objective to improve and simplify the
planning/analysis process
7Olympic Peninsula Pilot
- Objective is to reduce demand or generate power
at strategic locations to reduce loading when
needed. - Market Based reductions via Demand Exchange.
- Web-based bidding technology.
- Can be large individual loads (generation) or
utility aggregated demand reductions
(generation). - Metering to ensure that reduction (generation) is
delivered. - Systems are in place, negotiations are underway
and program will be exercised next year.
8Kangley-Echo Lake Study
- Objectives
- Identify technologies that would be cost
effective alternatives. - Evaluate the sensitivity of the cost
effectiveness analysis to variations in key input
assumptions. - Estimate whether achievable load reduction from
those cost effective alternatives would be
sufficient to defer the line.
9Load Flow Distribution Factors
- Load reduction at different locations will have a
different effect on Covington transformer
loadings due to network power flow interactions - Load weighted average distribution factor across
Puget Sound Area is 32 - 122MW required at Covington translates to 381MW
within the Puget Sound Area
10Study Results
- Transmission avoided costs are low
- 25 million of construction costs and 50,000 of
annual OM costs - 1.5 million for a one year deferral
- 12.25/kW-year at Covington or 3.92 /kW-year in
the Puget Sound Area based on average load flow
distribution factors - The economic value of the energy loss savings
from the line is greater than the cost of the
line - 11MW reduction of peak losses on the transmission
system - Annual energy savings of 48,180MWh
- 2 million at a market price of 40/MWh
11Study Results
- Demand Response (DR) is the most cost-effective
alternative from a transmission rate perspective - DR focuses load reduction on only the hours when
needed for system reliability - However, incentive levels are low compared to
other programs - 3.92/kW-yr available for DR incentives
- Range of incentives from surveyed programs
4.80-128/kW-yr
12Study Results
A high level of load reduction and additional
generation is required to defer the line
Load Relief and Generation Requirements for a
3-Year Deferral of the KEL Line
Base Case - 841MW (269MW) Winter 2005-2006 Load
Reduction Requirement within Puget Sound Area
100 of Potential 234MW (75 MW)
28 of Potential 1,380MW (125MW)
100 of Potential 277MW (70MW)
Load Relief Aluminum Smelter
Operation of Existing Local Generation
Load Relief from Area Industrial Load
( xMW) reduction at Covington
13Round Table
- To provide insights from a broad stakeholder base
to ensure that BPAs transmission planning
process is balanced. - To provide a forum for identifying and responding
to key issues. - To address institutional issues that go beyond
BPA. - To help build regional confidence and acceptance
for a new approach to transmission planning.
14Institutional Barriers
- Who pays, who implements and how to capture
economic value of measures - Lack of transparency in transmission planning
- Lack of incentives to do accurate forecasting
- Lost revenues for transmission provider and
distribution utilities - Inaccurate peak-load price signals for energy and
TD customers - Uncertainty about reliability of measures