Title: New World School of the Arts


1
Click once to view next slide
New World School of the Arts Building Renovation
/ Remodeling Board Meeting May 20,
2004 Presented by Gloria Jacomino
2
Agenda
  • Introduction of Project Teams
  • Completed Projects
  • Projects Under Construction
  • Projects Under Design
  • Future Projects
  • Summary

3
The MDC Team
Facilities Design and Construction
  • Dr. John Pennington
  • Assistant Vice Provost for Facilities Design and
    Construction
  • Gloria Jacomino
  • Director for Facilities Design and Construction

Carlos Aspillaga Project Manager
Fernando Rodriguez Director Business Affairs and
Facilities
4
The Architectural Team
Brown Brown Architects
Alfredo Ruiz Project Architect
Jennifer Slavik Project Architect
David Prada Project Manager
5
The Construction Management Team
Stobs Bros. Construction Company
Donovan Terrelonge Project Construction Manager
Bruce Beehler Project Superintendent
Mike Seney Senior Project Manager
6
Completed Projects
Exterior Painting
Front Elevation After
Before Notice extensive concrete deterioration
Entrance After
7
Completed Projects
Entrance Lobby and Art Gallery Renovation
Elevator Entrance Before
Elevator Entrance After
8
Completed Projects
Entrance Lobby and Art Gallery Renovation
Entrance to Classroom Spaces Before
Entrance to Classroom Spaces After
9
Completed Projects
Entrance Lobby and Art Gallery Renovation
Security Desk Before
Security Desk After
10
Completed Projects
Entrance Lobby and Art Gallery Renovation
Elevator Lobby
Restroom Entrance
11
Completed Projects
Entrance Lobby and Art Gallery Renovation
New Art Gallery Ceiling, Walls Floors
12
Completed Projects
Installation of a new Chiller
Installation of a new Chiller
Installation of mechanical infrastructure has
started.
13
Projects Under Construction
Print Making
Before
Under Construction Expand Graphics and
Photography shops
14
Projects Under Construction
New Basement Classrooms
Classroom Corridor Under Construction
15
Projects Under Construction
New Music Ensemble Rooms
Before Overcrowded with Minimal Sound Proofing
16
Projects Under Construction
Sculpture Studio
Add a plaster casting shop and integrate into the
Carpentry shop.
Before
17
Projects Under Design
Exterior Signage
Approved Signage Design
18
Projects Under Design
Ceramics Studio
Before
Expansion of the shop will allow additional
workstations and the integration of the kiln
activity
19
Projects Under Design
Dance Studio
Replacement of aging movable partition and
specialized Dance flooring system
Before
20
Projects Under Design
Theater Labs
  • Upgrade lighting and audio systems.
  • Replace flexible seating platform system

Before
21
Future Projects
  • Classroom Computer Labs
  • Restroom Refurbishing
  • A/C Upgrades
  • Fire Alarm Upgrades
  • Smoke Evacuation System Upgrades

22
Summary
Schedule
Construction from November 2003 through December
2005
Budget
All projects within the approved budget of 6M.