Title: Monthly 4_25/ Page 1
1Monthly Status Report Report due 4/25/00 Schedule
statused as of April 7, 2000
2Project Status Summary
Programmatic Feb Mar Apr
Schedule Feb Mar Apr
Resources Feb Mar Apr
Detailed Description (for items identified as
yellow or red)
- The contract is now in place at SwRI. This is no
longer a (big) worry. - We do not see any problems at this time either
technical, schedule, or programmatic. We are
still on schedule though the schedule is tight.
We have been continuing to use additional
personnel (while remaining on our spend plan) to
maintain the schedule. - Latest project photos are available on Aspera-3
web site.
3Problem and Concern Summary
PProblem CConcern RResolved
4Accomplishments of the Last Month -ELS
- Completed UV coating of the prototype parts.
- Finished fabrication of the MCP holder for the
prototype, flight and flight spare instrument. - Continued bench level compatibility tests between
HVPS and FEE. - Continued work on the ELS EGSE completing the
cabling, software and test setup. - We decided that the current printed circuit
boards (HVPS and FEE) that were used for the
prototype are suitable for flight. (Note They
were bought with certs. And are in the prcess of
being blessed by QA) - Finished the Dynamic Analysis of the ELS sensor.
- Began drafting test procedures for upcoming
prototype testing.
5Accomplishments of the Last Month - IMA
- Finished populating the anode board and the
digital board. - Bench tested the IMA electronics to determine the
noise floor and sensitivity. Boards look very
good! - Finished the machining of the mechanical parts
for IMA prototype, flight and flight spare IMA
detector. - Performed fit check with IMA electronics, MCPs,
and mechanical parts. Two mechanical parts
needed to be remade / modified. They are now
complete. - Following the bench test and the fit check, we
decided that the current printed circuit boards
(anode and digital) that were used for the
prototype are suitable for flight. (Note They
also were bought with certs.) - Finished the Dynamic Analysis of the IMA detector.
6Accomplishments of the Last Month - IMA (cont.)
- IMA MCPs are in house.
- Continued design and coding of the IMA GSE.
- Designed test set-up and fabricated IMA test
Break Out Box. - Began drafting test procedures that will be used
for IMA prototype testing.
7Accomplishments of the Last Month - Data
Reduction Software
- Configured ASPERA-3 Development Computer
(phobos.space.swri.edu) - Updated ASPERA-3.org Web Site Documentation
- Provided Technical Assistance for EPO Web
Information - Continued Defining and Implementing IDFS Web
Tools - Provided Support for ELS Characterization
Software - Held monthly ASPERA-3 Software Status Meeting
(April 20, 2000)
8Planned Activities for the Next Month - ELS
- Perform fit check of housing, HVPS and FEE when
housing is received back from UV coating at
Walton Plating. Note The parts were held up in
customs for about a week coming back from England
but are now in-house at SwRI as of 4/24/00. - Finalize cabling for ELS vacuum tests.
- Finalize testing of the Astrid EGSE to use for
ELS. - Decide on course of action regarding ELS
alignment (fab in-house, fab out-of-house) - Continue to monitor status of ELS vs. IMA
prototype to determine which one will be ready to
go into cal chamber first.
9Planned Activities for the Next Month - IMA
- Finish testing the IMA EGSE.
- Finish drafting IMA test procedures.
- Continue to monitor status of ELS vs. IMA
prototype to determine which one will be ready to
go into cal chamber first. It looks like it will
be IMA due to lack of MCPs for ELS. - Begin vacuum testing the IMA detector.
10Planned Activities for the Next Month - Data
Reduction Software Tasks
- Release Software Development Plan, Version 1.1
- Deliver Project Data Management Plan, Version 1.0
(by May 5, 2000) - Baseline ASPERA-3.org Web Site Documentation
- Continue Providing Technical Assistance for EPO
Web Information - Continue Defining and Implementing IDFS Web Tools
- Provide Software Support for ELS Characterization
11Problem and Concern Status
- Getting final contract in Place by March 1, 2000
(now April 1 2000) - The contract is now in place. We will now start
to get our subcontracts in place with outside
vendors (Burle, MSSL) and CoIs. - Assembly Process for ELS with UV Coated Parts
- Still a concern. We have received the prototype
parts back from Walton Plating and are now
developing procedures, processes, jigs etc. to
aid in the assembly of ELS.
12Problem and Concern Status (cont.)
- . Delivery of MCPs from Burle
- This is a new concern. The microchannel plates
were ordered Dec 5, 1999 with an incentive fee to
be awarded if they were delivered within 12 weeks
(2/27/00) ARO and a penalty if they were
delivered after 15 weeks (3/19/00) ARO. As of
4/11/00 the projected delivery date was 4/28/00,
well beyond the penalty date. If we do not
receive the prototype plates in early May, we
will start to impact our prototype schedule. We
are actively tracking this problem and may be
visiting Burle in the next couple of weeks to
better assess the problem.
13Problem and Concern Status (cont.)
- Alignment of ELS
- This is a new concern. We have finally received
a quote from an outside machine shop, Hyperfine
of Boulder, CO, for manufacture of the ELS
deflection plate system to meet the desired
tolerance limits. The quote is substantially
more expensive than we currently have budgeted
and is slightly longer than scheduled. We are
currently looking at other options including an
optics machine shop at MSFC, in-house fab, other
outside shops, and operational workarounds.
14Schedule Summary
- Total float on the tasks in the schedule has
increased since the last schedule reporting
period for two reasons - Modifying the flow of flight printed circuit
board flow - Adjusting some of the predecessor / successor
logic to better reflect the current build and
test plan - Mechanical activities are the critical path for
ELS (28 days float) and electrical interconnects
is the critical path for IMA activities (23 days
float). As with last month - Schedule still has 21 days slack at the end
(DEL0050) in addition to float shown for each
task - Most flight activity is serial with prototype
activities. We can (will) do activities in
parallel to maintain schedule. - We have modified the schedule to reflect using
the proto ELS boards for flight. We will
update the schedule accordingly for IMA assuming
they are bought off by QA for flight.. - Software activities continue to be on schedule.
- The full-up schedule is available on the ASPERA-3
Web site.
15ASPERA-3 PHASE B/C/D MASTER SCHEDULE