Monthly 4_25/ Page 1 - PowerPoint PPT Presentation

1 / 15
About This Presentation
Title:

Monthly 4_25/ Page 1

Description:

Continued Defining and Implementing IDFS Web Tools ... We have modified the schedule to reflect using the 'proto' ELS boards for flight. ... – PowerPoint PPT presentation

Number of Views:19
Avg rating:3.0/5.0
Slides: 16
Provided by: patgon
Category:
Tags: monthly | page | proto | tools

less

Transcript and Presenter's Notes

Title: Monthly 4_25/ Page 1


1
Monthly Status Report Report due 4/25/00 Schedule
statused as of April 7, 2000
2
Project Status Summary
  • Technical
  • Feb Mar Apr

Programmatic Feb Mar Apr
Schedule Feb Mar Apr
Resources Feb Mar Apr
Detailed Description (for items identified as
yellow or red)
  • The contract is now in place at SwRI. This is no
    longer a (big) worry.
  • We do not see any problems at this time either
    technical, schedule, or programmatic. We are
    still on schedule though the schedule is tight.
    We have been continuing to use additional
    personnel (while remaining on our spend plan) to
    maintain the schedule.
  • Latest project photos are available on Aspera-3
    web site.

3
Problem and Concern Summary
PProblem CConcern RResolved
4
Accomplishments of the Last Month -ELS
  • Completed UV coating of the prototype parts.
  • Finished fabrication of the MCP holder for the
    prototype, flight and flight spare instrument.
  • Continued bench level compatibility tests between
    HVPS and FEE.
  • Continued work on the ELS EGSE completing the
    cabling, software and test setup.
  • We decided that the current printed circuit
    boards (HVPS and FEE) that were used for the
    prototype are suitable for flight. (Note They
    were bought with certs. And are in the prcess of
    being blessed by QA)
  • Finished the Dynamic Analysis of the ELS sensor.
  • Began drafting test procedures for upcoming
    prototype testing.

5
Accomplishments of the Last Month - IMA
  • Finished populating the anode board and the
    digital board.
  • Bench tested the IMA electronics to determine the
    noise floor and sensitivity. Boards look very
    good!
  • Finished the machining of the mechanical parts
    for IMA prototype, flight and flight spare IMA
    detector.
  • Performed fit check with IMA electronics, MCPs,
    and mechanical parts. Two mechanical parts
    needed to be remade / modified. They are now
    complete.
  • Following the bench test and the fit check, we
    decided that the current printed circuit boards
    (anode and digital) that were used for the
    prototype are suitable for flight. (Note They
    also were bought with certs.)
  • Finished the Dynamic Analysis of the IMA detector.

6
Accomplishments of the Last Month - IMA (cont.)
  • IMA MCPs are in house.
  • Continued design and coding of the IMA GSE.
  • Designed test set-up and fabricated IMA test
    Break Out Box.
  • Began drafting test procedures that will be used
    for IMA prototype testing.

7
Accomplishments of the Last Month - Data
Reduction Software
  • Configured ASPERA-3 Development Computer
    (phobos.space.swri.edu)
  • Updated ASPERA-3.org Web Site Documentation
  • Provided Technical Assistance for EPO Web
    Information
  • Continued Defining and Implementing IDFS Web
    Tools
  • Provided Support for ELS Characterization
    Software
  • Held monthly ASPERA-3 Software Status Meeting
    (April 20, 2000)

8
Planned Activities for the Next Month - ELS
  • Perform fit check of housing, HVPS and FEE when
    housing is received back from UV coating at
    Walton Plating. Note The parts were held up in
    customs for about a week coming back from England
    but are now in-house at SwRI as of 4/24/00.
  • Finalize cabling for ELS vacuum tests.
  • Finalize testing of the Astrid EGSE to use for
    ELS.
  • Decide on course of action regarding ELS
    alignment (fab in-house, fab out-of-house)
  • Continue to monitor status of ELS vs. IMA
    prototype to determine which one will be ready to
    go into cal chamber first.

9
Planned Activities for the Next Month - IMA
  • Finish testing the IMA EGSE.
  • Finish drafting IMA test procedures.
  • Continue to monitor status of ELS vs. IMA
    prototype to determine which one will be ready to
    go into cal chamber first. It looks like it will
    be IMA due to lack of MCPs for ELS.
  • Begin vacuum testing the IMA detector.

10
Planned Activities for the Next Month - Data
Reduction Software Tasks
  • Release Software Development Plan, Version 1.1
  • Deliver Project Data Management Plan, Version 1.0
    (by May 5, 2000)
  • Baseline ASPERA-3.org Web Site Documentation
  • Continue Providing Technical Assistance for EPO
    Web Information
  • Continue Defining and Implementing IDFS Web Tools
  • Provide Software Support for ELS Characterization

11
Problem and Concern Status
  • Getting final contract in Place by March 1, 2000
    (now April 1 2000)
  • The contract is now in place. We will now start
    to get our subcontracts in place with outside
    vendors (Burle, MSSL) and CoIs.
  • Assembly Process for ELS with UV Coated Parts
  • Still a concern. We have received the prototype
    parts back from Walton Plating and are now
    developing procedures, processes, jigs etc. to
    aid in the assembly of ELS.

12
Problem and Concern Status (cont.)
  • . Delivery of MCPs from Burle
  • This is a new concern. The microchannel plates
    were ordered Dec 5, 1999 with an incentive fee to
    be awarded if they were delivered within 12 weeks
    (2/27/00) ARO and a penalty if they were
    delivered after 15 weeks (3/19/00) ARO. As of
    4/11/00 the projected delivery date was 4/28/00,
    well beyond the penalty date. If we do not
    receive the prototype plates in early May, we
    will start to impact our prototype schedule. We
    are actively tracking this problem and may be
    visiting Burle in the next couple of weeks to
    better assess the problem.

13
Problem and Concern Status (cont.)
  • Alignment of ELS
  • This is a new concern. We have finally received
    a quote from an outside machine shop, Hyperfine
    of Boulder, CO, for manufacture of the ELS
    deflection plate system to meet the desired
    tolerance limits. The quote is substantially
    more expensive than we currently have budgeted
    and is slightly longer than scheduled. We are
    currently looking at other options including an
    optics machine shop at MSFC, in-house fab, other
    outside shops, and operational workarounds.

14
Schedule Summary
  • Total float on the tasks in the schedule has
    increased since the last schedule reporting
    period for two reasons
  • Modifying the flow of flight printed circuit
    board flow
  • Adjusting some of the predecessor / successor
    logic to better reflect the current build and
    test plan
  • Mechanical activities are the critical path for
    ELS (28 days float) and electrical interconnects
    is the critical path for IMA activities (23 days
    float). As with last month
  • Schedule still has 21 days slack at the end
    (DEL0050) in addition to float shown for each
    task
  • Most flight activity is serial with prototype
    activities. We can (will) do activities in
    parallel to maintain schedule.
  • We have modified the schedule to reflect using
    the proto ELS boards for flight. We will
    update the schedule accordingly for IMA assuming
    they are bought off by QA for flight..
  • Software activities continue to be on schedule.
  • The full-up schedule is available on the ASPERA-3
    Web site.

15
ASPERA-3 PHASE B/C/D MASTER SCHEDULE
Write a Comment
User Comments (0)
About PowerShow.com