Satellite Owners' responsibility for costs and expenses ... manuals as baseline. Measurement Standards. Metering & Allocation. REASONING. APPROACH ... – PowerPoint PPT presentation

Number of Views:52
Avg rating:3.0/5.0
Slides: 19
Provided by: anders79
Category:

less

Transcript and Presenter's Notes

Title: Deepwater Production Handling Agreements


1
Deepwater Production Handling Agreements
THEMES AND CONCEPTS
  • Background
  • Case for action
  • Objective
  • Course of Action/Timing
  • Drafting Team
  • Drafting Process
  • Guiding Principles
  • Status
  • Model Form PHA Major Components
  • Select Themes Concepts
  • Facilities
  • Services
  • Fees Expenses
  • Capacity
  • Metering Allocation
  • Transportation

2
Deepwater Production Handling Agreements
CASE FOR ACTION
  • PHA Evaluations, Negotiations Contractual
    Agreements are Complex
  • No Consistency Framework Relative to the Terms
    Conditions of Contractual Agreements (i.e. Lack
    of Standardization)
  • Negotiations are Time Resource Consuming

3
Deepwater Production Handling Agreements
OBJECTIVE
  • Facilitate efficiency in terms of becoming more
    efficient with time and resources
  • Standardize, but simplify, PHA to extent possible
    (recognizes that each PHA is unique with its own
    set of issues/circumstances)

4
Deepwater Production Handling Agreements
COURSE OF ACTION/TIMING
  • Action Est. Completion
  • Create PHA Drafting Team 02/2003
  •     Assemble Example Forms 03/2003
  •        Develop Base Model Form PHA 03/2004
  •        OCS Committee Review 05/2004
  •        Edit Period 07/2004
  •        Industry Review 09/2004
  •        Edit Period 11/2004
  •        OCS Committee Endorsement 12/2004
  • AAPL Forms Committee Approval 12/2004

5
Deepwater Production Handling Agreements
PHA MODEL FORM DRAFTING TEAM
Drafting Consulting ChevronTexaco
ExxonMobil Shell Exploration Production
6
Deepwater Production Handling Agreements
DRAFTING PROCESS
  • Assemble and review example forms
  • Identify common/unique themes
  • Select base form to develop preliminary model
    form
  • Develop Guiding Principles
  • Draft Major Components
  • Draft Boiler Plate Language

7
Deepwater Production Handling Agreements
GUIDING PRINCIPLES
  • Generic as Possible
  • Broadly Applicable
  • Simplified in Terms of Readability
  • Provide basis for making business decisions
  • (i.e. distinguish business decisions
    from model form decisions)
  • Can be used as a catalyst for a Shelf Model Form
    PHA

8
Deepwater Production Handling Agreements
STATUS
Current Activity
  • Drafting of Major Components

Remaining Activities
  • Complete Drafting of Major Components
  • Drafting of Boiler Plate Language

9
Deepwater Production Handling Agreements
MAJOR PHA COMPONENTS
  • Facilities Design, Construction, Operation, Use
    and Abandonment
  •  Facility Ownership Funding
  • Services
  • Fees Expenses
  • Processing Handling Capacity
  • Production/Fuel Measurement Allocation
  • Downstream Transportation
  • Suspension of Operations
  • Term
  • Tax, Royalty Insurance
  • Liability Indemnification

10
Deepwater Production Handling Agreements
Theme Facilities
11
Deepwater Production Handling Agreements
Theme Services

12
Deepwater Production Handling Agreements
Theme Fees Expenses
13
Deepwater Production Handling Agreements
Theme Capacity
14
Deepwater Production Handling Agreements
Theme Capacity
15
Deepwater Production Handling Agreements
Theme Metering and Allocation
16
Deepwater Production Handling Agreements
Theme Metering and Allocation
17
Deepwater Production Handling Agreements
Theme Gathering Transportation
18
Deepwater Production Handling Agreements
Theme Gathering Transportation
Write a Comment
User Comments (0)
About PowerShow.com