Description:

Of all of the RBMK plants, the Chernobyl was run the best, and the crew knew it, ... The disaster at Chernobyl released 300 times more radioactive pollution ... – PowerPoint PPT presentation

Number of Views:34
Avg rating:3.0/5.0
Slides: 16
Provided by: sucs
Category:
Tags: chernobyl | evans | ryan

less

Transcript and Presenter's Notes

Title: Ryan Evans


1
High Integrity Systems Nuclear Power Plant
  • Ryan Evans Nick Shepherd

2
How a Power Plant works
Uranium is the principle element used in nuclear
reactors
Nuclear fission is the process of splitting atoms.
The free neutrons can be captured by other atoms
such as boron, which can be used to control the
reactions.
E mc2
3
The Power plant
4
Events Leading Up To The Accident
  • 25th April 1986 experiment
  • Requirements for test
  • Backup generator takes 40 seconds to work
    effectively
  • Turbines used between power failure and backup
    generators working
  • Test to take place at 20 - 30

5
  • Problem 1 Too many control rods raised power
    output dropped to 7

6
  • Problem 2 Automatic shutdown disabled more
    rods pulled out beyond safe limit

7
  • Problem 3 Test started below the minimum level

8
  • Problem 4 Emergency procedure short circuited by
    operators

9
(No Transcript)
10
Statistics
  • Between 600,000 and 1 Million liquidators
  • Reached Level 7 on International Nuclear Events
    Scale
  • Still feel the effects of the disaster in 100,000
    years time
  • Unofficially 60,000 of liquidators have died
    either from Acute Radiation Poisoning or other
    related illness
  • Between 10 and 50 tons of nuclear fuel
    unaccounted for

11
Level 2 Conditions
  • Operators under extra pressure because tests were
    planned prior to routine maintenance. If the
    testing was not completed now, then it would have
    to be done in a years time.
  • Of all of the RBMK plants, the Chernobyl was run
    the best, and the crew knew it, they became
    overconfident.
  • Test was perceived as an electrical test and had
    been conducted uneventfully before. Thus the
    operators did not think carefully when performing
    tasks upon the reactor.
  • Positive Coefficient of the Reactor makes it very
    difficult to control, safety being dependent on
    control.
  • Used RBMK instead of PWR.

12
Level Three Conditions
  • Much debate including
  • Flawed Operators Theory
  • Flawed Design Theory

13
Extensions and Additions
  • Adding a roof to cover the sarcophagus. A French
    company building a stadium-like building that
    will house the whole of the former reactor 4
    building.
  • 300 liquidators and 600,000 further employed.
    Real figures need to be guessed at because of the
    Soviets
  • Soviets built RBMK plants instead of the safer
    PWR design, they built the RBMK because they
    decided they would produce Plutonium and
    electricity from a single reactor, rather than in
    two separate reactors like the PWR. They also
    didnt have the funding that most countries that
    use the PWR system.

14
Preventions
  • Better training for all employees
  • (general nuclear physics knowledge)
  • Better control of safety protocols
  • Make it so they cant be disabled / short
    circuited
  • More respect for equipment and technology
  • The disaster at Chernobyl released 300 times more
    radioactive pollution than Hiroshima

15
Further Reading
  • http//news.bbc.co.uk/1/hi/in_depth/europe/2006/ch
    ernobyl/default.stm
  • http//en.wikipedia.org/wiki/Chernobyl_disaster
  • Google Video
  • BBC Horizon Nuclear Nightmares