Cost Data - PowerPoint PPT Presentation

1 / 41
About This Presentation
Title:

Cost Data

Description:

Cost Data – PowerPoint PPT presentation

Number of Views:16
Avg rating:3.0/5.0
Slides: 42
Provided by: universi79
Category:
Tags: budget | cost | data | how | set | to | up

less

Transcript and Presenter's Notes

Title: Cost Data


1
Cost Data
2
Cost Data Overview
  • Factors
  • Earned Value
  • 50/50 Rule
  • Examples

3
Factors
  • BCWS - Budgeted Cost Work Scheduled - Budget
    entry numbers
  • ACWP - Actual Cost Work Performed - Actuals, what
    you spent
  • BCWP - Budgeted Cost Work Performed - Earned
    Value, what you have accomplished

4
Factors
  • BAC - Budget at Completion - the total of all the
    budget numbers, the bottom line
  • EAC - Estimate at Completion - based on your rate
    of expenditures, what you probably will spend by
    the end of the project
  • CV - Cost Variance, BCWP - ACWP CV
  • SV - Schedule Variance, BCWP - BCWS SV

5
Factors
  • CPI - Cost Performance Index
  • BCWP/ACWP CPI
  • SPI - Schedule Performance Index
  • BCWP/BCWS SPI

6
BCWP - Earned Value
  • Calculating Earned Value should be easy if you
    set up your budget correctly.
  • Earned Value or BCWP is the value of what you
    have produced. If you have produced 500,000
    worth of the 1,000,000 project, your BCWP is
    500,000 or 50.

7
BCWP - Earned Value
  • Lets use a wall as an example
  • There are 50 per foot in materials
  • It will take 4 labor hours per foot to build at
    20/hour
  • There will be 200 in other labor charges
  • There is a crew of four working
  • The wall is 80 feet long
  • On the first and last days the crew has 8 hours
    of set up and tear down time each

8
BCWP - Earned Value
  • Budget
  • Materials - 50 X 80 4000
  • Labor for wall - 4 X 80 X 20 6400
  • Labor for set up and tear down - 16 X 20 320
  • Additional Labor - 200
  • Total 10,920

9
Budget for Wall
10
Budget for Wall
11
Budget for Wall
12
Wall
  • Question
  • How would you do this budget different?

13
Actual Construction
14
Actuals For Wall
  • Day 1
  • Set up 6 hours
  • 10 feet done
  • Materials - 10 X 50 500
  • Labor 18.18 (32 X 20) 668.18
  • Total 1168.18
  • BCWS 958.18
  • ACWP 1168.18
  • BCWP ?

15
BCWP
  • How would you allocate the budget so you could
    determine BCWP?

16
BCWP
  • Easiest is to take total costs and prorate over
    some easy thing to measure, like the length of
    the wall.
  • 10,920/80 136.50 / foot completed

17
Actuals For Wall
  • Day 1
  • Set up 6 hours
  • 10 feet done or a value of (10 X 136.50)
    1365.00 or 1365.00/10,920 complete 12.5
    complete
  • Materials - 10 X 50 500
  • Labor 18.18 (32 X 20) 668.18
  • Total 1168.18
  • BCWS 958.18
  • ACWP 1168.18
  • BCWP 1365.00

18
Actuals for Wall - Day 1
  • BCWS 958.18
  • ACWP 1168.18
  • BCWP 1365.00
  • CV BCWP - ACWP 1365.00 - 1168.18 196.82
    Positive so it is favorable
  • SV BCWP - BCWS 1365.00 - 958.18 406.82
    Positive so it is favorable
  • CPI BCWP/ACWP 1365/1168.18 1.168 or for
    every dollar that is spent, we earn 1.17 in
    value
  • SPI BCWP/BCWS 1365/958.18 1.42 or we are
    doing about 40 better on schedule than
    anticipated.
  • EAC BAC/CPI 10,920/1.17 9333.33

19
Actuals For Wall
  • Day 2
  • It rained - no work performed
  • Labor 18.18 (32 X 20) 668.18
  • Total 668.18
  • BCWS 2016.36
  • ACWP 1836.36
  • BCWP 1365.00

20
Actuals for Wall - Day 2
  • BCWS 2016.36
  • ACWP 1836.36
  • BCWP 1365.00
  • CV BCWP - ACWP 1365.00 - 1836.36 - 471.36
    Negative so it is unfavorable
  • SV BCWP - BCWS 1365.00 - 2016.36 - 651.35
    Negative so it is unfavorable
  • CPI BCWP/ACWP 1365/1836.36 0.74 or for
    every dollar that is spent, we earn 0.74 in
    value
  • SPI BCWP/BCWS 1365/2016.36 0.67 or we are
    doing much worse than we budgeted
  • EAC BAC/CPI 10,920/0.74 14756.76

21
Actuals For Wall
  • Day 3
  • Sunny day, crew motivated, did 14 feet today.
  • Materials 14 X 50 700
  • Total Done 24
  • BCWP 24 X 136.50 3276.00
  • Labor 18.18 (32 X 20) 668.18
  • Total 1368.18
  • BCWS 3074.54
  • ACWP 3204.54
  • BCWP 3276.00

22
Actuals for Wall - Day 3
  • BCWS 3074.54
  • ACWP 3204.54
  • BCWP 3276.00
  • CV BCWP - ACWP 3276.00 - 3204.54 71.46
    Positive so it is favorable
  • SV BCWP - BCWS 3276.00 - 3074.54 201.46
    Positive so it is favorable
  • CPI BCWP/ACWP 3276/3204.54 1.02 or for
    every dollar that is spent, we earn 1.02 in
    value
  • SPI BCWP/BCWS 3276/3074.54 1.06 or we are
    doing much worse than we budgeted
  • EAC BAC/CPI 10,920/1.02 10,705.89

23
S - Curves
  • Ok, so now we can calculate the statistics
  • Next we want to be able to graph the numbers and
    see where we are from a visual perspective.

24
S Curves
  • S Curves are a good way to see at a glance what
    is going on.
  • The following curve shows our data on a graph.

25
S Curves
BCWS
ACWP
BCWP
26
S Curves
BCWS
BCWP
ACWP
27
S Curves
BCWS
BCWP
ACWP
28
S Curves
BCWS
ACWP
BCWP
29
S Curves
BCWS
ACWP
BCWP
30
S Curves
BCWS
ACWP
BCWP
31
S Curves
BCWS
ACWP
BCWP
32
S Curves
BCWS
ACWP
BCWP
33
Wall Example Continued
  • The following Excel example shows how the curves
    can be used.

34
50/50 Rule
  • Frame has an easier way to calculate earned
    value.
  • It is called the 50/50 rule.
  • With this rule, you earned 50 of the earned
    value the instant you start a task and the other
    50 when the task is complete.

35
50/50 Rule
Task 1 50k
Task 2 25k
Task 3 40k
36
50/50 Rule
Task 1 50k Started so, we have earned 25k
Task 2 25k
Task 3 40k
BCWP ?
37
50/50 Rule
Task 1 50k Started so, we have earned 25k
Task 2 25k
Task 3 40k
BCWP 25K
38
50/50 Rule
Task 1 50k Started so, we have earned 25k
Task 2 25k Started so have earned 12.5k
Task 3 40k
BCWP ?
39
50/50 Rule
Task 1 50k Started so, we have earned 25k
Task 2 25k Started so have earned 12.5k
Task 3 40k
BCWP 37.5K
40
50/50 Rule
Task 1 50k Finished so, we have earned 50k
Task 2 25k Started so have earned 12.5k
Task 3 40k Started so we have earned 20k
BCWP 82.5K
41
Reminders
  • BCWP can never exceed BCWS
  • At the end of a project the schedule variance
    will always equal zero
  • Cost variance can exceed BCWS
Write a Comment
User Comments (0)
About PowerShow.com