Title: Duke Production Status


1
  • Duke Production Status

2
Module Production
  • Mechanical Construction
  • All Type II (M2.01 to M2.37) are completed and
    gas tight.
  • All Type III (even number Type III (minus
    M3.32,M3.34)) are completed and gas tight.
  • Stringing
  • Type II
  • M2.33 and M2.34 are remaining to string.
  • Super spares (M2.35, M2.36, M2.37) will be strung
    by the end of September.
  • Type III
  • 5 Modules were sent to Hampton for stringing
  • M3.16, and M3.30 are remaining to string.
  • Either Duke or Hampton will string
  • Super spares (M3.36) will be strung by the end of
    September.

3
Modules to be strung
4
Stringing stations
5
  • Duke Acceptance testing
  • Type II
  • M2.02, M2.03, M2.04. M2.16 are completed
    including final gas leak test and signal test.
  • Type III (even)
  • M3.02, M3.04, M3.06 M3.14 are completed
    including final gas leak test and signal test.
  • 8 Type II, and 6 Type III are at Hampton for gain
    mapping

6
Wire-joint production
  • Original estimation was 65,000, but we are
    approaching 100,000.
  • Original estimation was 280/day, but we have
    been producing 400/day or 2000/week.
  • We have slowed down to 1200-1500/week, which is
    still enough to meet the reduced stringing rate
    at the three sites.
  • After 34 modules of all three types were strung,
    the rate will be reduced to 1000/week. Need
    6000 for super spares (35/36/37).
  • After 37 modules, plan is to produce 1000 for
    re-work at CERN and 2000 for reserve.
  • The wire-joint production should be over by the
    end of August.

7
Fuses Boxes
  • The design is completed and they are being
    machined. We should have them back by the end of
    June.
  • Production is 40 sets of each type module (240
    fuse boxes).
  • We also need dummy fuse boxes for the other
    module side. These are being machined as well.
  • Plan to start the assembly in July.
  • Need fuse delivery schedule. We only have 100
    pre-production fuses.
  • No good estimation for the production time yet.
  • Should we test fuses through random sampling?
  • Not in critical path

8
Fuse Boxes
9
HV capacitors
  • Decision was made to go with NPO/850pf /2000
    volts.
  • Passed initial testing.
  • Arcing test at 2000 volts 50 capacitors
  • Neutron radiation test 20 capacitors
  • Co60 radiation test 20 capacitors
  • HV soaking for two months at 2750 volts 50
    capacitors
  • A fixture to assemble 20,000 cap is being tested
  • 500 will be made for the beam test
  • Final testing with the assembled capacitors
  • Full production should start in August and would
    take two month.
  • Long term HV soaking test (10 days at 2750 volts)
    would take six months.
  • Not in critical path

10
Capacitor assembly fixture
11
Beam test structure
12
People
  • May /2003 6.5 techs stringing, wire-joints
  • June /2003 5.5 techs stringing, wire-joints
  • July /2003 3.5 techs stringing, wire-joints,
    fuse boxes
  • Aug /2003 3.5 techs stringing, wire-joints,
    fuse boxes, capacitor assembly
  • Sep /2003 3.5 techs stringing, fuse boxes,
    capacitor assembly
  • Oct /2003 2 techs fuse boxes, capacitor
    assembly