DS3 Deliverables Review
2
DS3-T1Data and Phase transfer
  • Report on COTS technology
  • Done, not published
  • Report on component based technology
  • 90 complete some more work on VCSELS
  • Prototype phase transfer link
  • 100 complete
  • Report on performance of phase transfer link
  • Done
  • Report on prototype data links over short and
    long distances
  • Work complete report needs to merge info from
    Manchester group and BEST
  • Detailed cost model
  • 70 done, need to complete implementation into
    SKACost

3
DS3-T2 Data handling control computing
  • Processing architectural design
  • On going will input experience from LOFAR. Also
    merge relevant experience from DS2 and DS4
  • Software design
  • This has not been started this will be input
    from LOFAR experience into SKA context. Input
    from DS3-T5
  • Cost and power usage evaluations
  • Significant overlap with DS4 merge info into
    report
  • Cost evaluations for software architecture
  • Not started Cambridge will lead input from
    LOFAR
  • Technology assessment and road mapping
  • Good state lots of relevant work, needs
    bringing together

4
DS3-T3Functional simulator
  • Initial report on conceptual issues of SKA
    network
  • Done DC I
  • Delivery of functional simulator
  • Done see this meeting
  • Report on performance
  • DC I and II have lots of relevant material 70
    done
  • Work will be completed as part of the work of the
    Systems group

5
DS3-T4Siting issues
  • First overview report on site selection
    procedures
  • Delivered report is private
  • Report on site selection
  • Delivered report is private
  • Final report including discussion of site, land
    purchase etc.
  • Will send a 1-page report explaining how work has
    been superseded by external events
  • RF workshop on spectrum and other site related
    issues
  • This will be formally met by linking to other
    planned workshops

6
DS3-T5 SKA for the User
  • Original aims
  • Ease of use of the SKA observing modes,
    astronomer interaction
  • Data archives for the SKA what is provided to
    the end user data volumes etc.
  • Visualisation tools for end user astronomers and
    telescope operators what is available, can the
    tools cope, do we need a development programme?
  • What software tools are required for the end
    user how are these distributed where is analysis
    done? Tools for science extraction?
  • Plan for two meetings (combining original 4)
  • First meeting done
  • Will setup discussion on open-access WIKI
  • Second in March 2009 in conjunction with Oxford
    MCCT workshop

7
DS3-T6 Scalable design and implementation
  • Report on prototype control and data processing
    system
  • Significant overlap with DS3-T2 and DS3-T3 meet
    deliverable via these tasks?
  • Specifications and implementation of construct
    interfaces and components
  • Done report needs to be delivered
  • Guidelines for platform dependent deployment of
    control and data handling software
  • Need to consider exactly what we will do here
    this is being done
  • Assessment of readiness for scalability and MDA
    compliance
  • Done and delivered
  • Recommended guidelines for scalable design and
    implementation
  • Merge into report with MDA compliance input
    from LOFAR experience on track

8
Conclusions
  • DS3 remains on track
  • DS3-T1 Excellent progress
  • DS3-T2 Work needs to be done drawing in LOFAR
    experience, but plan is in place for meeting all
    deliverables
  • DS3-T3 Excellent progress
  • DS3-T4 Completed very successfully
  • DS3-T5 On target schedule good progress
  • DS3-T6 Small agreed changes in emphasis of
    deliverables so that they will be met.
Write a Comment