HINS Linac Focusing Channel - PowerPoint PPT Presentation

1 / 17
About This Presentation
Title:

HINS Linac Focusing Channel

Description:

Four types of cryostats by length; Two types of cryostats by number of leads ... 1. Fabrication teem should consist of three experienced technicians working ... – PowerPoint PPT presentation

Number of Views:21
Avg rating:3.0/5.0
Slides: 18
Provided by: iouriter
Category:
Tags: hins | channel | focusing | linac | teem

less

Transcript and Presenter's Notes

Title: HINS Linac Focusing Channel


1
HINS Linac Focusing Channel
  • CH Section Solenoid
  • Preparations to Production

2
Production Scope
  • Four types of cryostats by length
  • Two types of cryostats by number of leads (with
    or without correctors)
  • With spares
  • type 1 -- 6
  • type 1C -- 3
  • type 2C -- 5
  • type 3 -- 5
  • type 4 -- 3
  • type 4C -- 3
  • Totally 25 plus two spare cold masses

3
Strand Availability
  • We are expecting 17 km of 0.8 mm strand from
    Oxford in the end of April.
  • The total need of strand for this part of the
    front end is 0.6 km x 30 18 km.
  • Two cold masses have been already built and we
    still have some strand to build another four
    solenoids.
  • 0.6 mm strand for bucking coils is readily
    available from Oxford and is not going to be a
    restricting factor.

4
Stages of fabrication
  • - coil winding
  • - coil impregnation
  • - cold mass assembly
  • - cold mass testing
  • - cryostat assembly
  • - final assembly testing

5
Production Pre-Requisites
  • Fabricate and test cold masses for pre-production
    solenoids two with correction dipoles and two
    w/o correctors
  • Add LHe vessels to some of the tested solenoids
    and test the cold masses with LHe vessels
  • Make final corrections to the cold mass drawings
  • Assemble existing and tested cold masses (with
    LHe vessels) into a cryostat. Test the assemblies
    using a devoted test stand (to be organized).

6
Part Procurement
  • Allow 2 month for parts to start arriving
    after an order has been placed. Procurement of
    some critical parts can be expedited. Help of the
    IB-2 production group can be useful to follow
    orders.
  • With some attention to the issue, winding can
    start in July

7
Fabrication time
8
Time Saving Options
  • Wind coils in batches
  • Impregnate and cure several coils in one cycle
    (several sets of winding tooling is needed)
  • Test several solenoids in one cooling cycle
  • Assemble solenoids in batches
  • Make job in parallel, not in series

9
Needed Resources
  • 1. Fabrication teem should consist of three
    experienced technicians working under T.Ws
    supervision
  • - winding (qualification of Pat Sanches or
    Chuck Pribyl)
  • - impregnation (Dave Burk or Juniar Jones)
  • - assembly (Dan Assel, Bill Robatzek)

Expected average output 1 cold mass per week
10
Needed Resources (cont)
  • 2. Access to stand 3 with some setup help
    provided as needed by Charlie and Fred (1 day a
    week or so)
  • 3. A person from test department to make cold
    mass and assembled solenoid tests (1 day a week
    or so)
  • 4. A stand for testing solenoids assembled in
    cryostats must be set.

11
Sample production schedule
After a 6-week delay we can have one system per
week of output
12
Costs
  • Cryostats 27K x 25 675 K
  • Cold masses 7K x 40 280 K
  • Assembly tooling 20K
  • LHe (if in Dewars) 2K x 2 x 20 80K (cold
    mass)
  • LHe cost if in Duars 2K x 40 80K (assembled
    system)
  • Personnel salary 300K
  • Total 1.4M

13
Other production options
  • Winding and impregnation by a vendor, testing and
    the final assembly at TD
  • Cold mass fabrication and testing by a vendor,
    final assembly and testing at TD
  • Focusing solenoid fabrication and testing by a
    vendor, retesting at TD
  • Focusing Solenoids and Power System outsourced to
    a vendor

14
Power and Protection
  • Option 1
  • Each current circuit is powered by its own
    power supply.
  • Typical size of one 6 V, 300 A power supply is
    400 x 400 x 100 mm3. Installation power is 2 kW.
    One rack can hold 5 power supplies (cooling
    problem). We need 35 channels for the CH section,
    so we need a space for 7 racks. Many 500 A cables
    must go from each rack.
  • Control panel must be in the control room, so
    additional cabling is needed.

15
Power and Protection
  • Option 2
  • Two centralized 6 V, 6 kA power supplies plus
    6kA Al buses. Locally installed transistor
    regulators provide current for each current
    circuit. The regulators are controlled from one
    low-power rack in the control room (35 channels
    6 blocks by 6 channels each).
  • The number of identical regulators makes it
    easy to design and cheap to fabricate. The system
    can be duplicated for solenoids in the s/c
    sections of the linac.

16
Current Regulator
17
Proposed Action Items
  • Attempt to find vendors that can make solenoids
    or cold masses
  • Understand options for powering the solenoids
    (B. Webber and ADs Electrical Department)
  • Try to assign a priority to the job so that the
    needed resources could be found
  • Continue with the pre-production program
Write a Comment
User Comments (0)
About PowerShow.com