Title: NIH Stormwater Management Program
1NIH Stormwater Management Program
2Stormwater, Why do we care?
- http//www.youtube.com/watch?v2Sxwl_SOSAQ
3The NIH Campus
- The NIH research facility occupies a 310 acre
adjacent to the Bethesda CBD and residential
neighborhoods. It contains two distinct storm
water drainage areas.
4(No Transcript)
5NIH Campus Disharges to Stormwater
- Campus Stormdrains
- NIH Power Plant
- Exterior Water Usage
- Grounds keeping
- Construction sites
- Hydrant Testing
6National Pollutant Discharge Elimination System
(NPDES)
- Federally mandated by the Environmental
Protection Agency (EPA) under the Clean Water Act - Maryland Department of the Environment has
implementation authority - Originally regulated POINT SOURCE end of pipe
discharges from locations such as sewage
treatment plants and industrial facilities - Broadened to Address NON-POINT SOURCES -
pollution from stormwater runoff spread out over
large areas - Medium and Large urban areas,
construction activity disturbing 5 acres of land
or greater, categorical industrial
7NIH NPDES Phase II General Permit Requirements
- SIX best management practices (BMPs) to be
implemented and measurable goals for each, - public education and outreach
- public participation and involvement
- illicit discharge detection and elimination
- construction site runoff control
- post-construction runoff control and
- pollution prevention/good housekeeping
8NIH Best Management Practices
91) Public education and outreach
2) Public participation and involvement
Earth Day at NIH includes stream tours
Along with other activities that showcased the
NIH environmental efforts.
103) Illicit Discharge Detection
- The DEP staff monitors the headwalls along the
stream as well stormwater lines around campus for
signs of water pollution coming through the system
114) Weekly Inspections of Sediment Erosion
Control Measures.
- Each week, NIH/DEP staff conduct inspections of
all potential sources of sediment pollution and
possible erosion spots along all construction
projects.
125) post-construction runoff control
Low Impact Development Stormdrain
Map and Maintain Existing BMPs
136) Pollution prevention/good housekeeping
14Best Management Practices for the NIH Campus
- Existing
- Stormwater Stuctures (Natcher Bldg, Metro
Station, NLM, Day Care) - Sediment Basin at NIH Stream Outfall
- Underground Stormwater Management Structure
(behind MLP-10) - Wilson Lane Frog Pond Streamside sand filters
- Stormceptors at MLP 9 and Bldg 33
- Bldg 1 underground sand filters
- Curbless Gutters (Wilson Lane, East Drive)
- Reduction in impermeable surfaces (Multi-level
Parking Structures) - Reforestation/No-mow habitat areas
- Sand and Ice-Melt (Magnesium chloride) instead
of Salt for Ice/Snow - Improved Hydrant Flushing Practices
- Tree Box Filter
- Green Roof at NIH Visitor Center
- Upcoming
- NIH South Pond
15NIH Bethesda Stormwater Management Plan
- Plan addresses improvement to water quality and
reduction in water runoff speed - Plan eventually provides credits for future
projects - Three major projects conducted to accrue credits
- Revitalize NIH stream
- Underground structure for CRC (water speed)
- Montgomery County to build Stony Creek Pond
16Ultimate GOAL Protect the tributaries of the
Chesapeake Bay Watershed
17The NIH Stream
- The NIH Stream is the main storm water outfall
for the NIH campus. It collects drainage from
over 210 acres of the campus.
18The NIH Stream Restoration Project
- In 2003, NIH began work on a project designed to
restore the main stormwater outlet for the
campus, the NIH Stream. This project upgraded
the water quality of the stream, and improved the
aesthetics of the campus for all employees. The
project was completed in 2004.
19NIH Stream Pedestrian Bridge
February 20th, 2004
20NIH Stream Pedestrian Bridge
August 4th, 2006
21NIH Stream Pool
February 20th, 2004
22NIH Stream Pool
August 4th, 2006
23NIH Stream North
January 12, 2004
24NIH Stream North
August 4th, 2006
25Pool Areas
26Retention Filter Wilson Drive
27Retention Pond 2006
28Northeast Stormwater Control
29North Underground Storage Structure
30Retention Structure Construction
31STONEY CREEK POND BACKGROUND
- Primary Project Objectives
- To restore water quality and stream habitat in
lower Rock Creek by - Reducing stormwater flow rates to address stream
bank erosion - Improving runoff water quality from downtown
Bethesda - Contribute to meeting a portion of the
requirements listed in the NIH Campus-wide Master
Plan - Construction funds available under a County/State
matching grant under TEA-21 - 204-Acre drainage area to the pond site
32(No Transcript)
33Stony Creek Pond - Continued
- Project required close coordination among a
variety of partners - Montgomery County
- NIH
- Utility companies
- State of Maryland
- Community
34DESIGN FEATURES
- Permanent water surface area will cover 1.3
acres with maximum depth of 6 feet - 1 year storm event (frequent storm event)
water surface area will cover 1.7 acres - Maximum water surface area during large
storms (100 year storm event) will cover 3.3
acres - Reduce peak flows from the 6- month storm to
pre-developed conditions - Significant peak flow reductions will also be
made for the 1-year storm (which has the greatest
impact in reducing stream bank erosion downstream
of the pond)
35DESIGN FEATURES
- Two underground trash and oil collection devices
will capture trash and oil washing through the
Bethesda storm drain system - Safety bench along the ponds edge will ensure
shallow - water ( 6-12) along the shoreline
- Landscaping with native trees, shrubs, herbaceous
plants, - grasses, and wetland vegetation will help
to support a - diverse and balanced ecosystem. Will
try to reuse Cypress locally. - Landscaping strategies recommended by the
Maryland - Department of Natural Resources When
Resident Geese Become a Problem will be
incorporated to discourage geese
36DESIGN FEATURES
- Aerators are planned to increase water
circulation to enhance water quality and
predatory insect populations - DEP will introduce native fish and aquatic
organisms to assist in creating a balanced
ecosystem - DEP will monitor and perform regular maintenance
- Proposed primary construction access will be from
southbound exit lane for Woodmont Avenue - The construction contractor will be required to
follow the Montgomery County Noise Ordinance,
Section 31 (b) of the County code. Work hours
during construction are between the daytime hours
of 700 a.m. to 500 p.m.
37PROJECT STATUS TentativeUpdated pfister May
2008
- Pending Final Design Review with NIH and
Permitting Agencies Complete - Plan Signing and Permitting Process,
Easements Summer 2008 - Advertise Fall 2008
- Contract Approval Fall 2008
- Preconstruction TBD Utility relocations
during stream closure.
38Questions
39Backup Slides
40PUBLIC PARTICIPATION
- DEP held a follow-up field meeting on November
23, 2002 for the community, and presented the 60
design to the CLC in March 2003. - Montgomery County Planning Board unanimously
endorsed the project on February 13, 2003 - NCPC Provided Conditional Approval in May 2003
(pending finalizing permitting)