Title: CHAPTER 6 COST ESTIMATION
1CHAPTER 6COST ESTIMATION
- Jinashree Rajendrakumar
- Jisha Nambiar
- Madhuri Chakraborty
- Priyanka Tyagi
- Shalini Singh
2 3Case 6.2 The Pump Division
- The Pump Division has one plant dedicated to the
design manufacture of pumps. - Typical production cycle of a pump is 1-3 years.
- Job is highly technical customized.
- Orders are obtained through bids (based on cost
estimate) and negotiation sessions. - The contracts generally are fixed price.
- Sometimes orders accepted as loss leaders.
- High risk of job cost overruns.
4Examples
- (In thousands) Job 1 Job2
- Original Cost Estimate 2,113 1,800
- Costs Incurred to date
- Manufacturing 2,100 -
- Engineering 373 100
- Estimate to complete 367 2,500
- Total current Estimate 2,840 2,600
- Lower-of-cost-or-market Contract sales
price 2,520 2,000 - Less 10 Allowance for Normal Profit Margin
(252) (200) - Inventory Value 2,268 1,800
- Inventory Reserve Adjustment (loss) (572)
(800)
5Current Problems in the Department
- Final job costs significantly varied from
original cost estimates. - Major decline in profitability, combined with
several unfavorable year-end surprise inventory
adjustments. - As company policy is to record revenue costs on
a completed contract basis, it is difficult to
determine early, the variances between job costs
estimates.
6Some unanswered Questions ?
- It is clear from the table, Job-Order costing is
being used as each job is customized. But is
job-order costing being used within the
departments (Engineering, Manufacturing etc) ? - What allocation base/cost driver is being used
for applying overhead costs? - What estimation method (High-Low or Regression
Analysis) is being used for overhead costs? - How is Under or Over applied Overhead Balances
being disposed (Closed out to Cost of goods sold
or Allocated between accounts)?
7Inventories
- Valuation of the Inventory
- - FIFO, LIFO or Weighted Average Method
- Inventory Adjustments
- The accounting procedures include two year-end
adjustments to be made prior to the close of the
fiscal year - Adjusting inventory to physical count Perform
an annual physical inventory count of inventories
and reconcile the changes with the inventory
balance. - Adjusting the inventory reserve balance
Departments may be required to maintain an
inventory reserve. Reserves must be at least
equal to and may not exceed the physical
inventory by more than 15. Therefore, if the
reserve account is less than the physical
inventory count or is more than 15 greater than
the physical inventory you will need to adjust
the reserve balance. (NOTE Departmental
storerooms using a periodic inventory system are
not required to keep a reserve.)
8What courses of action appropriate for plant
manager his controller relating to Estimating
Costs
- Cost estimation team should include Engineering,
Design and Manufacturing representatives. Cost
estimation should be cross-disciplinary for
better accuracy and insight. - Sales department should be given the threshold
cost of the project and be trained to negotiate
on more favorable payment terms. - Cost Estimate should be updated to reflect new
information, given a projects phase of planning
and/or execution. - Plant Manager should review the cost estimates
and actual costs more frequently to track
variances. - Controller should record costs as a percent of
completion rather than on a completed contract
basis.
9Contd..
- Since the PLC of the jobs are usually 1-3 yrs,
the cost estimates should incorporate future
costs such as risk contingency costs for major
cost elements. - Cost estimation should build in inflation into
the cost estimates using Index. Historical data
can be used to load the estimates for inflation. - Perform a risk assessment on the entire project
in order to define and quantify the potential
risk areas and types. - Cost estimation methods used should be
consistent, thorough and traceable.
10Lower of Cost or Market value
- LCM requires that inventory be reported in the
financial statements at whichever is lower its
historical cost or its market value. Also damaged
or obsolete inventory is written-off in LCM. - The loss (market value lt historical cost) must be
charged against revenues of the period. Cost of
goods sold will absorb the inventory write-down. - The replacement cost (market value) must lie
between a ceiling and a floor amount. - The ceiling is the net realizable value(selling
price less disposal cost). - The floor is the net realizable value less a
normal profit margin. - If cost is lowest of the four values (cost,
replacement cost, ceiling, floor), use cost.
Otherwise use the second lowest value.
11What courses of action appropriate for plant
manager his controller relating to the
application of LCM rule
- This method applies to the following
- - Goods purchased and on hand
- - The basic elements of cost (direct materials,
direct labor, and an allocable share of indirect
costs) of goods being manufactured and finished
goods on hand - This method does not apply to the following and
must be inventoried at cost - - Goods on hand or being manufactured for
delivery at a fixed price on a firm sales
contract (that is, not legally subject to
cancellation by either you or the buyer) - - Goods accounted for under the LIFO method
(www.irs.gov) - The Pump Division should have an accurate cost
estimation method in place and try to avoid
whatever it takes to get the order practice.
12What is the significance of the following methods
on the performance of the operation?
- Progress Payments
- Advance Payments
- Escalation Clauses
13Progress Payments
- Payment on basis of percentage or stage of
completion - Payments are based on costs incurred as work
progresses - Progress payments are currently limited to 80
percent of incurred costs - Contractors must have approved accounting systems
- Advantageous from a cash flow perspective
- Improves the working capital of the firm
- Progress payments can decrease interest expense
- Important for long term contracts
- Information is critical for effective contract
administration and for audit and investigative
purposes
14Advance Payments
- Advance payments are prepayments and cash
advances for the manufacturer to start the job,
buy materials and begin production - Advance payments if partial payments or progress
payments are not feasible and private financing
is not available - Contractors must have approved accounting systems
15Escalation clause
- Definition
- A clause in a contract that allows the seller
to be offered a higher price should the buyer or
another party make a higher bid in the market
within a certain period. Contracts can also be
indexed for inflation or cost increases.
16Benefits of escalation clause
- Effective method of coping with inflation
- Hold significance for long term contracts
- Price adjustment clauses for long-term contracts
- Identifies the item(s) that are subject to the
escalation clause - The escalation clause should specify frequency
for price adjustment - Price index for the calculation of price
adjustments (PPI) - Transfers the burden of the price hike to the
buyer - Corrects the distortion in the cost estimations
17 18Case 6-1(Background)
- The Brenham General hospital prepares in-house
meals for its patients - The hospital is facing steady decline in revenues
and wanted to cut costs wherever possible - It is approached by a Health Food Inc . Which
offers it meals _at_ 11.50 - BG Hospital wants to have some idea about the
cost of their in-house meal service - Based on that they wanted to decide whether to
accept the proposal of HFI or not
19Data
Patient Days (X) Other staff (Y1) Maintenance (Y2) Patient Equipment (Y3) Dietitian (Y4) food cost (Y5)
Jan 1382 3122 1401 1649 2875 9674
feb 1312 2908 1322 1415 2875 9184
march 1186 2655 1322 1313 2875 8302
april 1012 2600 1288 1105 2875 7084
may 914 2433 1200 1089 2875 6398
june 604 2083 1133 1011 2875 4338
july 516 1809 1093 900 2875 3612
august 896 2322 1122 1112 2875 6275
sept 962 1434 1235 1103 2875 6734
oct 1286 2700 1302 1300 2875 9002
Nov 1208 2789 1300 1442 2875 8456
dec 1114 2600 1322 1396 2875 7798
20High Low Method
- The high-low method is based on the rise-over-run
formula for the slope of a straight line. It uses
two points to estimate the general cost equation - Y a ? b ?H
- H the cost driver
- Y dependent variable
- Variable Cost (Y) Change in Cost
- Change in Activity
- Fixed Cost (H) Total Cost Variable Cost
21Simple Regression
- A regression analysis has two types of variables
- The dependent variable is the cost to be
estimated - The independent variable is the cost driver used
to estimate the value of the dependent variable - Evaluating a regression analysis
- R2, the coefficient of determination, is a
measure of the explanatory power of the
regression, the degree that changes in the
dependentvariable can be predicted by changes in
the independent variable. - The t-value is a measure of the reliability of
each of the independent variables.
22Simple Regression Steps
23Steps..
24Steps
25Scatter Plot steps
26Steps
27Steps
28High Low Method Simple Regression
- Very simple to apply
- Least expensive
- A critical defect uses only two data points
- Periods in which activity level is unusually
low/high will produce inaccurate results.
- Most accurate and Most costly
- Complex and involves numerous calculations but
principle is simple. - Spreadsheet programs now available to handle the
complexities.
29High Low Method Simple Regression
- Other staff 1.52 Days 1021.36
- Food Cost 7.00Days
- Maintenance 0.36 Days 903.48
- Equipment 0.86Days 460.48
- Dietitian 2875
- Total cost 9.74Days5250.32
- Other Staff 1.35 Days 1051.7
- Food Cost 6.94 Days 69.75
- Maintenance 0.32 Days 915
- Equipment 0.722Days 490.31
- Dietitian 2875
- Total cost 9.35Days 5401.76
Regression analysis is a better cost estimation
method
30In house food service Health
Food Inc
- Other Staff X
- Food Cost X
- Maintenance X
- Equipment X
- Dietitian X
- 11.50Per meal
- XServices utilized by the respective proposals
31In house service Health
food Inc.
- Other Staff VF
- Food Cost VF
- Maintenance VF
- Equipment VF
- Dietitian F
- 11.50 /Meal
- VVariable FFixed Cost
Figures in italics and underlined are not
considered for comparison because they are common
between the options
32Compare the two options
- Cost of In-house meals
- Equation1.35Days1051.76.94Days69.750.32Days
0.722Days -
- Cost 9.33 Days 1121.45
- Cost of HFI s Proposal
-
- Cost 11.50 per meal
33Comparing variable component of two options
- In-house meal costs 9.33 per patient day
- HFIs proposal 11.50 per meal
- (1 patient day 2.8 meals )
- HFIs proposal 11.50 2.8 32.20 per patient
day - Conclusion In-house meal preparation is cheaper
34Comparison of total cost of the options using two
different occupancy levels
Days In house HFI
X1200 (33 occupancy) 9.3312001121.45 12317.45 32.21200 39640
X600 (16 occupancy) 9.336001121.45 6719.45 32.2600 19320
35 36APPLYING OVERHEAD HOW TO FIND THE RIGHT BASES
AND RATES?Overview
- Application of Regression Analysis to
determine the relationship between the overhead
costs and the cost drivers/ application bases - Selection of application bases that reflect the
causes of overhead costs - Using data and an objective tool to understand
the relationships - Using the regression results of rates to ABC
models. - Using regression analysis for construction of
multiple overhead rate
37What is Regression analysis used to accomplish in
this article?
- PURPOSE
- Determine the relationship between the overhead
costs and the various cost drivers using
regression analysis - Identify the application bases/cost drivers that
better reflect the causes of the overhead costs - Select proper bases that have strong
cause-and-effect relationship with the factory
overhead costs using objective technique - From a wide selection of application bases three
cost drivers were picked for overhead costs in
the article - direct labor hours
- machine hours
- number of production setups
38What is Regression analysis used to accomplish in
this article?
- Step 1 searching for a proper base
- Simple regressions on collected data
- Three different simple regression analyses were
performed - R squared values ( explain the variability of
FOH costs that can be explained by the
independent variable) are as under - R squared or coefficient of determination
measures the extent of the relationship between
the two variables
(Y) dependent variable (X) independent variable R squared values
Factory OH costs (FOH) Direct labor hours 0.77 (strong)
FOH costs Machine hours (MH) 0.39 (middle)
FOH costs No of production setups 0.29 (weak)
39What is Regression analysis used to accomplish in
this article?
- Step 2 construction of a single overhead rate
- Constant refers to the estimate of fixed portion
of FOH costs - X coefficient is an estimate of the variable
FOH costs - The regression equation
- Monthly overhead costs (OH) 72,794 74.72
(MH) - fixed variable
40What is Regression analysis used to accomplish in
this article?
- Step 2 contd..
- Assign the fixed portion of the overhead costs
to the products and jobs using a separate base - Find a separate base that reflects the demands
made by the products and jobs on the fixed
resources. - Use two rates for applying OH costs based on
two different bases - - one for fixed component
- - one for variable component
41What is Regression analysis used to accomplish in
this article?
- Step 3 Construction of multiple overhead rate
- Variable overhead costs may be driven by
several equally important factors - Using more than one base for application of
overhead costs will give more accurate cost
estimates. - Perform a multiple regression to construct more
than one overhead rate - - Machine hours (0.77)
- Number of setups (0.39)
- Use FOH costs observations as Y-Range and
select the range of observations for both machine
hours and no. of setups for X-Range
42What is Regression analysis used to accomplish in
this article?
- Step 3 Construction of multiple overhead rate
- Regression Equation
- OH 19,796.43 65.44 MH 322.21 NS
- - monthly total fixed OH costs 19,796.43
- variable OH costs 65.44 per Machine hour
322.21 per setup - R squared of multiple regression using MH and
NS gt R-squared of simple regression for MH. (
0.95 vs 0.77) - Variable OH costs based on both machine hours
and no of setups would give more accurate
estimates - Total fixed costs may be applied using a
separate base.
43What is Regression analysis used to accomplish in
this article?
- Step 3 Construction of multiple overhead rate
- Reliability of the multiple regression
- No of observations used 12
- t value X coefficients/ Std error of the Coef
- t critical 2 ( general rule 2 indicates highly
reliable estimate) - t value for machine hours 9.7 (65.44/6.74)
- t value for no of setups 5.49
(322.21/58.66)
44What is Regression analysis used to accomplish in
this article?
- Step 4 Rates for activity based costing
- Regression analysis is used to investigate the
strength of the relationship between the various
activities and cost drivers for selection of
proper bases. - To classify a large no of activities into a
few groups (cost pools) based on common
bases/drivers - Use simple regression to study the
relationship between activities and cost
drivers. - Based on R squared values, group activities
into cost pools which have common bases/cost
drivers. - Regression analysis is
- practical, effective and objective
- simple when powered by Excel!!!
45What are the steps to perform a simple regression
analysis?
- Collect actual data on selected variables for
several periods. - Ensure consistency in period daily, weekly,
monthly - Tabulate dependent (Y) and independent (X)
variable on a spreadsheet. - Use the Toolsdata analysis-regression
- The window will ask to specify X and Y variable
to perform regression. - Interpret the regression results
- Use regression equation to estimate
46Table 1 Data for Regression Analysis
A B C D
Data points Factory OH costs Direct labor hours Machine hours no of setups
(Y) X1 X2 X3
1 155000 985 1060 200
2 160000 1068 1080 225
3 170000 1095 1100 250
4 165000 1105 1200 202
5 185000 1200 1600 210
6 135000 1160 1100 150
7 145000 1145 1080 165
8 150000 1025 1090 180
9 180000 1115 1300 204
10 175000 1136 1400 206
11 190000 1185 1500 208
12 200000 1220 1700 212
47What does Table 4 tell you? there is no table 7
- Table 4 gives the relationship between the cost
type/activities and the cost drivers. - It gives the strength of the relationship between
the cost driver and the activities. Explains how
much of the variability of the cost type can be
explained by the cost driver.
R squared values for various pairs of Activities and Cost drivers R squared values for various pairs of Activities and Cost drivers R squared values for various pairs of Activities and Cost drivers R squared values for various pairs of Activities and Cost drivers R squared values for various pairs of Activities and Cost drivers R squared values for various pairs of Activities and Cost drivers
Activities Cost driver Maintenance Packaging Materials handling Storage Production scheduling
Machine hours 0.85 0.46 0.68 0.45 0.82
Pounds of materials 0.38 0.88 0.90 0.75 0.43
Labor hours 0.30 0.28 0.38 0.22 0.43
48Which cost driver would you pick for each cost
type?
- The cost drivers having higher R squared values
indicate stronger causal relationship. - According to this analysis, the cost driver would
be - Machine hours Maintenance and Production
Scheduling - Pounds of materials Packaging, Materials
handling, Storage
R squared values for various pairs of Activities and Cost drivers R squared values for various pairs of Activities and Cost drivers R squared values for various pairs of Activities and Cost drivers R squared values for various pairs of Activities and Cost drivers R squared values for various pairs of Activities and Cost drivers R squared values for various pairs of Activities and Cost drivers
Activities Cost driver Maintenance Packaging Materials handling Storage Production scheduling
Machine hours 0.85 0.46 0.68 0.45 0.82
Pounds of materials 0.38 0.88 0.90 0.75 0.43
Labor hours 0.30 0.28 0.38 0.22 0.43