Title: Diapositiva 1
1Metro de Madrid Network Extension Projects 1995
2007 Dublin, 05/16/2008 José-Cruz Peña
2SUMMARY
- NETWORK EXTENSIONS
- IMPLEMENTED SYSTEMS OF CONSTRUCTION
- PERFORMANCES AND BUDGETS
3SUMMARY
- NETWORK EXTENSIONS
- IMPLEMENTED SYSTEMS OF CONSTRUCTION
- PERFORMANCES AND BUDGETS
4METRO DE MADRID
Madrid city Madrid region
5METRO DE MADRID
The exploitation of Metro de Madrid started in
1919 with the line Cuatro Caminos-Puerta del Sol
( 3.5 Km, 21 coaches and 8 stations in line 1)
6THE NETWORK IN 1995
164 STATIONS 120.0 km
7THE NETWORK IN 1999
1995-1999 EXTENSION
202 ESTACIONES 176.0 km
38 STATIONS 56.0 km
81999-2003 EXTENSION
THE NETWORK IN 2003
238 STATIONS 235.2 km
36 STATIONS 59.2 km
9 2003-2007 EXTENSION
80 STATIONS 55.7 km METRO 27.8 km LIGHT
RAIL 83.5 km NETWORK
THE NETWORK IN 2007
318 STATIONS 318.7 km
10 2003-2007 EXTENSION COACH DEPOTS
344.34 M 4 NEW COACH DEPOTS 2 ENHANCED DEPOTS
HORTALEZA L1
HORTALEZA L1 4
LR POZUELO AND BOADILLA
CUATRO VIENTOS L10
LINE 1
V ILLAVERDE L3
11NETWORK EXTENSIONS
DEMAND
800
736
750
700
655
620
650
615
Million Users / year
602
600
565
544
550
525
500
480
450
437
423
400
408
397
392
391
350
300
2005
1993
1994
1995
1996
1997
1998
1999
2000
2001
2002
2006
2007
2003
2004
12NETWORK EXTENSIONS
1995
2007 Metro Length (km) 120
318.7 Stations 164 318 Trains
during peak hours 178 393 Coaches
1,126 2,151 Coaches x Km
(Millions) 90.2
208.9 Passengers/day (Millions) 1.5
2.9 Passengers/year (Millions) 397
736 Average journey per passenger 4.57
7.00 Workforce 5,627
6,300 Run by Metro
Metro and Light Rail Municipalities
1 12
13 2007-2011 EXTENSION FORECAST
14SUMMARY
- NETWORK EXTENSIONS
- IMPLEMENTED SYSTEMS OF CONSTRUCTION
- PERFORMANCES AND BUDGETS
15 CRITERIA AND GUIDELINES (I)
- TUNNEL CONSTRUCTION
- MAXIMUM SAFETY AT WORK (minimising accidents)
- MAXIMUM SAFETY AT WORKSITE SURROUNDINGS
(buildings and structures) - GEOTECHNICALLY SAFE
- SAFETY PRIORITY VS DEADLINES AND BUDGET
- UNDERGROUND WORKS SYSTEM OF MONITORISING
- EXCAVATION DEVELOPMENT FORECAST
- FOLLOW UP AND ANALYSIS
- FAST AND DIRECT DECISION TAKING
15
16 CRITERIA AND GUIDELINES (II)
- GEOTECHNICAL ADVICE
- PRESERVATION OF THE ENVIRONMENT
- RESPECTFUL OF LANDSCAPE AND ENVIRONMENT
- ACCESIBLE METRO NETWORK
- TO STATIONS
- TO ROLLING MATERIAL
- PROTECTION OF HISTORICAL HERITAGE
- COMMON EFFORT OF ALL PARTIES INVOLVED
16
17 MADRID
TRADITIONAL SYSTEM
18MADRID TRADITIONAL SYSTEM
19MÉTODO TRADICIONAL MADRID
20MADRID TRADITIONAL SYSTEM
21(No Transcript)
22(No Transcript)
23(No Transcript)
24(No Transcript)
25(No Transcript)
26CUT AND COVER (With in situ cast tunnel)
- Suburban areas and not very deep tunnels
- The system allows several variations
2727
28(No Transcript)
29(No Transcript)
30CUT AND COVER (Within diaphragm walls)
31CUT AND COVER (Within diaphragm walls)
- Urban areas where line is superficial and there
are no buildings around
- Allows different construction systems slab,
vault roof, etc.
- With Slab the system is competitive vs EPB or vs
Madrid System when depth is less than 4 m 9 m
when using vault roof
32CUT AND COVER (Within diaphragm walls)
33STATIONS
FIRST LEVEL EXCAVATION
DIAPHRAGM WALLS AND PILE-COLUMNS
COVER SLAB AND FLOOR BEAMS
SECOND EXCAVATION AND FLOOR SLAB
34(No Transcript)
35(No Transcript)
36TUNNEL BORING MACHINE
37TUNNEL BORING MACHINE E.P.B.
ADVANTAGES
- Mechanical excavation with performances 10 to 15
times higher than other systems
- Under preassure earth confined in the front
chamber. Therefore, settlements in surface are
reduced.
- Best machine in soft and instable soils.
- Minimises induced settlemens and damages to
surrounding structures.
- Wide experience it has been used since the
1999-2003 extension project
38TUNNEL BORING MACHINE E.P.B.
DISADVANTAGES
- Requires a minimum of 1.5 or 2 diameter depth
- Needs a huge hollow area to allow entry and exit
of equipment and earth.
- It has line limits. Minimum curve radium must be
300 m
- Only profitable beyond 5 km line.
39PERFORMANCES REACHED
Timing 20 minutes for excavation 20 minutes
to complete the ring
Speed of progression 40 minutes / ring
Theoretical Capability Three shifts/day (20
hours )(4 maintenance hours) 30 rings 6
days/week and 4.3 weeks/month 770 rings/
month. 1.5 m/ring equals 1,155 m/month
40 SYSTEMS OF CONSTRUCTION E.P.B.S.
1 EPB VÍA SIMPLE
41(No Transcript)
42(No Transcript)
43(No Transcript)
44ON THE SURFACE TRACK
45ON THE SURFACE TRACK
- Implemented for Light Rail
- Good adaptability to town development
46(No Transcript)
47(No Transcript)
48(No Transcript)
49 SYSTEMS OF CONSTRUCTION
50 SYSTEMS OF CONSTRUCTION
2003-2007
51- Current Facilities
- (March 2007)
- 159 Local Control Centres
- 1582 Escalators
- 26 Travelators
- 420 Lifts
- 115 Electric Substations
- 287 Transfomation Centres
- 919 Platform Teleindicators
- 3,591 Intercoms
- 3,595 Cameras CCTV
- 621.5 GWh energy consumed in 2006
52 2003-2007 NETWORK EXTENSION
FACILITIES PROJECTS. METRO
53 2003-2007 NETWORK EXTENSION ROLLING STOCK
Serie 9000 52 UDS
Metro Ligero 70 UDS
Serie 3000 80 UDS
LÍNEA 7, LÍNEA 9 Y METRONORTE
LÍNEA 3 , LÍNEAS 2 Y 4
POZUELO, BOADILLA Y SANCHINARRO
236 TRAINS
Serie 2000 90 UDS
Serie 8000 14 UDS
LÍNEA 5
LÍNEA 8
54NETWORK EXTENSION PICTURES 2003-2007
55ESTACIÓN DE ALAMEDA DE OSUNA - LÍNEA 5
56INTERCAMBIADOR DE CHAMARTÍN
57ESTACIÓN SAN FRANCISCO LÍNEA 11
58LÍNEA 7 METROESTE ESTADIO OLÍMPICO
59METRONORTE MARQUÉS DE LA VALDAVIA
60INTERCAMBIADOR DE PINAR DE CHAMARTÍN
61 LÍNEA 3 ESTACIÓN HOSPITAL 12 DE OCTUBRE
62SANCHINARRO ANTONIO SAURA
63BOADILLA CIUDAD DE LA IMAGEN
64SUMMARY
- NETWORK EXTENSIONS
- IMPLEMENTED SYSTEMS OF CONSTRUCTION
- PERFORMANCES AND BUDGETS
6565
66 2003 2007 NETWORK EXTENSION
67INVESTMENT (M) 2003 2007 NETWORK EXTENSION
4,923.64
FOR NEW AND OLD LINES
68METRO CONSTRUCTION COMPARISON
69GOVERMENT COMUNIDAD DE MADRID
MINISTRY OF CIVIL WORKS AND URBANISM
DIRECCION GENERAL DE INFRAESTRUCTURAS
METRO DE MADRID
FINANCING, DESIGN AND PROJECT MANAGEMENT
PROJECT MANAGEMENT AND OPERATION
70PROJECT SCHEDULE
0
30
40
10
20
50
60
70
80
90
100
Project Engineering
Tenders and contracting
Construction
- Simultaneous execution of project and work
- Major times of draft of design
- Possibility of including changes and improvements
during the work - Reduction of the total term.
- Major control of the work
71KEY SUBJECTS
Know How
High implication with Authorities
Efficiency
Continuous technical assistance
Flexibility
Financing Model
Strict supervision and control
Experience
71
72KEY SUBJECTS
73Some more KEY SUBJECTS
74THANK YOU VERY MUCH FOR YOUR ATTENTION MUCHAS
GRACIAS POR SU ATENCIÓN