Payback Period Analysis

1 / 27
About This Presentation
Title:

Payback Period Analysis

Description:

... some possible companies. BHP-Billiton. Woodside. Coles-Myer. Woolworths. David Jones. Fosters Group. Qantas. Virgin Blue. Patrick Corporation. Orica. Wesfarmers ... – PowerPoint PPT presentation

Number of Views:67
Avg rating:3.0/5.0
Slides: 28
Provided by: Michael2109

less

Transcript and Presenter's Notes

Title: Payback Period Analysis


1
Payback Period Analysis Life-Cycle Cost
  • Engineering Economics

Lecture 5 26 August, 2005
2
Assignment some possible companies
  • BHP-Billiton
  • Woodside
  • Coles-Myer
  • Woolworths
  • David Jones
  • Fosters Group
  • Qantas
  • Virgin Blue
  • Patrick Corporation
  • Orica
  • Wesfarmers
  • Telstra
  • Hutchieson
  • Optus (Singtel)
  • Telecom NZ
  • ERG
  • CSL
  • Fairfax
  • Newscorp
  • PBL
  • Tabcorp
  • Pacific Brands

3
Payback Period Analysis
  • Two forms for this method
  • Conventional Payback Period (zero interest rate)
  • Discounted Payback Period (uses an interest rate)
  • Payback is the period of time it takes for the
    cash flows to recover the initial investment.
  • It is useful in providing the initial screening
    for a number of alternatives.
  • What is the relationship between the payback
    period and the actual useful life of an item?

4
Example
  • An organisation leases 4 x 2 Mbps point-to-point
    digital service to interconnect its private
    network in 5 buildings in the CBD from the local
    telecom carrier for 52,000 per annum.
  • The organisation decided to install and operate
    its own digital microwave radio links for the
    capital investment of 140,000
  • The annual licence fee 1,500 and maintenance
    contract 4,800 will be ongoing expenses.

5
Network Diagram
2
3
2Mbps
2Mbps
1
2Mbps
2Mbps
5
4
6
Conventional Payback Period
  • The conventional payback period for the capital
    investment would be
  • np 140,000 / 52,000 2.7 years
  • This method is very simple and can be give very
    misleading results.
  • It may be acceptable as a rough indication only
    but not as a business evaluation tool.

7
Questions to be asked
  • What is the revenue or benefit that the
    organisation gets from this service ?
  • Where will the organisation get the 140,000
    initial investment from ?
  • What is the useful life of the equipment ?
  • Are there any other costs or factors that need to
    be considered ?

8
Possible Answers
  • Having the private links, the organisation will
    not have to pay 52,000 a year for connectivity.
  • If the organisation borrowed the money, it will
    have to pay interest. If the organisation had the
    money, it can earn interest on it. (Opportunity
    Cost)
  • The useful life has to be significantly longer
    than the payback period (typically 10 to 15
    years)
  • System design, permits and licences,
    installation, commissioning, and maintenance must
    be considered.

9
Discounted Payback Period
  • An interest rate i gt 0 is used for this
    calculation.
  • There is a logical linkage between this method
    and the breakeven analysis.
  • The analysis produces a payback period np that is
    the estimated time, usually in years, it will
    take for the estimated revenues and other
    economic benefits to recover the initial
    investment and a stated rate of return.

10
Discounted Payback Approach
  • Find the value of np such that

where P is the initial investment, NCF is the
estimated net cash flow for each year t as
determined by the equation
NCF cash inflows - cash outflows
11
Calculations
Using the equations
for P 140,000, A 52,000 and i 0.1
(10) the number of years (n) is 3.29 years
12
Comments
  • Even if the organisation did not have to borrow
    the 140,000 an interest rate must be considered.
  • The discounted cash flow method show that the
    payback period is much longer than that obtained
    using the conventional method.
  • The ongoing licence and maintenance fees must not
    be forgotten.

13
Cost Elements
  • System engineering
  • Permits and licences
  • Capital investment (equipment)
  • Installation and commissioning
  • Annual maintenance
  • Annual licences
  • Salvage/Disposal

14
Payback Method - Summary
  • Payback is only a rough estimator of desirability
  • Use as an initial screening method
  • Avoid using this method as a primary analysis
    technique for selection projects
  • Totally avoid the no-return payback period

15
Payback Method - Summary
  • The No-return method
  • Does not employ the time value of money
  • Disregards all cash flows past the payback time
    period
  • If used, can lead to conflicting selections when
    compared to more technically correct methods like
    present worth!

16
Life Cycle Costs ( LCC )
17
Life Cycle Costs (LCC)
  • Extension of the Present Worth method
  • Used for projects over their entire life span
    where cost estimates are employed
  • Used for
  • Military/Defense Projects
  • New Product Lines
  • Large construction projects

18
Phases of Life Cycle
  • Needs Assessment Phase
  • Conceptual Design Phase
  • Detailed Design Phase
  • Production/Construction Phase
  • Operation (upgrading to extend) Phase
  • Retirement/Disposal Phase

19
Life Cycle Two General Phases
Cost-
Cumulative Life Cycle Costs
Time
Acquisition Phase
Operation Phase
20
The Design Phase
  • The design phase is the most critical phase in
    the system engineering process.
  • If not managed correctly, it can lead to some
    undesired outcomes
  • There will always be changes during the design
    phase, the amount of which can be attributed to
    the phases preceding it.

21
LCC Impact of Design Changes
  • Cost of a design change tends to multiply by 10
    with each phase
  • Any design changes that might occur late in the
    life cycle drastically increase the total life
    cycle costs!
  • Design freeze period

22
LCC Acquisition Phase
Rule About 80 of LCC are locked in by the end
of the Acquisition Phase. Emphasis is on good
design!
Costs -
Needs Assessment
Conceptual Design
Detailed Design
Acquisition Phase
23
Life-Cycle Costs Purpose
  • Make as explicit as possible the relationship of
    costs over the total life span of a
    product/system
  • Design Process Objective
  • Minimize the life-cycle costs
  • And meet other performance requirements
  • By making correct trade-offs between costs in the
    acquisition phase and costs during the operations
    phase

24
Life-Cycle Costs Warning
  • Beware of introducing certain cost- cutting
    measures in the acquisition phase and early
    production phase
  • Such cost-cutting measures could impact the
    future operations and degrade safety or require
    modifications later on
  • These cost-cutting measures can be misleading and
    dangerous!

25
Life-Cycle Costs Warning
  • Engineers have a ethical and moral responsibility
    to ensure that designs are
  • Economically sound
  • Functional
  • Safe
  • Perform as expected

26
LCC of the Microwave System
  • For Microwave example
  • Useful life 10 years
  • Interest rate 10
  • Initial costs 153,000
  • Recurring costs 8,800 per annum
  • Salvage value 0
  • Total PW 207,072
  • Total PW for carrier-provided service 319,517
  • Refer to the spreadsheet example Microwave
    Example

27
References
  • Blank, L., Tarquin, A., Engineering Economy,
    McGraw-Hill, 5/e (Chapter 5)

Thanks for your attention
Write a Comment
User Comments (0)