Title: FSMAIRPORT IMPROVEMENT PROJECT UPDATES
1FSMAIRPORT IMPROVEMENT PROJECT UPDATES
- 2008 PACIFIC AVIATION DIRECTORS WORKSHOP
Presented by Massy Halbert
Garapan, Saipan March 31, 2008
2FSM-AIP PROJECTS
- Project Contractor CM
- Yap Apron - GPPC, Inc. - LAD
- Yap ARFF - Penta-Ocean - GMP
- Pohnpei Runway - Penta Ocean - GMP
- Pohnpei ARFF - Penta Ocean - GMP
- Kosrae ARFF - Black Micro - GMP
- Chuuk ARFF - China Jiangsu - GMP
3YAP APRON REHABILITATION
- Project started on 18 February 2008
- Contract Cost is 10,298,000.00
- Expected to be completed by 20-Aug-09
- Contractor is GPPC, Inc. with CM Leo A. Daly
4YAP ARFF
- Contract with Penta-Ocean Const. approved
amounting to 5,909,000.00 - Contract and Bonds will be submitted to FAA
shortly for concurrence and issuance of NTP - Construction expected to commence by
- mid April 2008
- Target completion date is April 2009
- The CM for this project is GMP Hawaii, Inc.
5POHNPEI RUNWAY ARFF
- Construction contract agreement is currently
being processed for approval at FSM Finance - Pre-const meeting was held on 28-Mar-08 and
expected to start construction by mid April 2008 - The scope of work for Runway rehabilitation has
been revised and divided into 3 Phases due to
funding shortage - The ARFF costs 12,150,000.00
- Phase 1 of the Runway costs 22,788,000.00
- Contract duration for ARFF is 365 cal. days
while the Pohnpei Runway is 610 cal. days
6POHNPEI RUNWAY ARFF
7POHNPEI RUNWAY
8POHNPEI RUNWAY
9CHUUK ARFF
- The project costs 4,899,901.52
- Contract agreement with China Jiangsu is
currently with FSM Finance - Pre-construction meeting was held on February 26,
2008 - Anticipated to start construction within this
month of April with 365 calendar days contract
duration
10KOSRAE ARFF
- Construction officially started on February 22,
2008 - Contractor is Black Micro Corp. with CM GMP
Hawaii, Inc. - Contract costs 5,788,000.00 with a duration of
365 calendar days - Scheduled completion date is February 20, 2009
11EQUIPMENT FOR DOI FUNDING
- Proposed list of airport equipment for each State
has been forwarded to DOI for review - Submission of FSM request to DOI has been delayed
as we encountered difficulties in getting price
quotation from suppliers - Formal request will be submitted to DOI together
with the required supporting documents as soon as
the DOI confirmed that the equipment being
requested is qualified for funding
12CHALLENGES
- C1. Lack of interested Bidders during the
procurement stage of the project - C2. Difficulties in the availability, shipment
and cost of major construction materials - C3. Compliance with Buy American Requirement
- C4. Contract Management
- C5. FAA bonding requirement
- C6. Timely approval of Contract Agreement
- C7. Timely payment of Invoices
- C8. Unmanageable Consultant
13RESOLUTION TO CHALLENGES
- R1. Use of Sole Source Procurement Process as
approved by the FAA - R2. Pre-construction meeting at earlier stage to
identify potential sources and suppliers - R3. FAA waiver for Buy American Requirement
provided the Contractor could submit proof of
unavailability of materials - R4. Regular coordination between FAA, FSM
National State Government, Consultant and
Contractor - R5. Imposition of Retention Money in lieu of
Payment Bond - R6. Sufficient funding, completeness of
supporting documents and constant follow-up - R7. Sufficient funds, proper drawdown scheduling,
record keeping of project funds - R8. Selection of manageable and responsible
Consultant
14YAP TERMINAL REHABILITATION
- Completed on 20 Sept. 2007 amounting to
2,063,811.00
15YAP TERMINAL REHABILITATION
16YAP APRON GROUNDBREAKING February 21, 2008
17YAP APRON GROUNDBREAKING February 21, 2008
18CHUUK ARFF PRE-CONSTRUCTION MEETING February
26,2008
19CHUUK ARFF PRE-CONSTRUCTION MEETING February
26,2008
20KOSRAE ARFF GROUND BREAKING February 28,2008
21KOSRAE ARFF GROUND BREAKING February 28,2008
22KOSRAE ARFF GROUND BREAKING February 28,2008
23One of a Kind Temporary Shelter for Firefighting
Vehicles
24ONLY IN YAP !