Title: NEET Work Group 6 Update: BPA Demand Response
1NEET Work Group 6 Update BPA Demand Response
- April 21st
- Karen Meadows
- Pam Sporborg
2Why is BPA Interested in Demand Response?
- Continued load growth is leading to a forecasted
capacity shortage in 2013. - Wind integration, fish operations, and other
operational constraints are limiting the
flexibility of the hydro system to meet peak
demand. - Demand Response is a proven, low-cost resource
that can help BPA meet projected Capacity
Constraints.
3Capacity Constraint Scenarios
4BPA Demand Response Guiding Principles
- Collaboration Partnership BPA will work
collaboratively with our Public Utility Customers
to develop and implement Demand Response pilots
and programs - Balance Cost and Risk BPA will work to
implement cost-effective, least-risk DR
solutions. However, BPA recognizes that this may
frequently require trade-offs between these two
goals. - Regional Leadership Role BPA will lead by
example in the region, though information
sharing, collaborative research efforts, and
demonstrating state of the art technology. This
includes integrating Demand Response into the
Smart Grid. - Reliability Flexibility BPAs Demand Response
resource will primarily aim to improve system
reliability and enhance flexibility. - Environmental Stewardship BPA will consider the
environmental impacts of each DR Option.
5BPA Activities in Demand Response
- Past Pilot Projects include
- Non-Wires Solutions Pilot (direct load control,
back up generation) - Irrigation Pilot
- Ashland Pilot (Direct Load Control)
- Demand Exchange (Wholesale)
- Demand Response Potential Assessment
- Developed DR Supply Curves that will be inputs
into the Resource Program - Planned DR Activities
- Research Action Plan developed
- Pilot programs to test impacts and costs of
various DR strategies to meet Capacity Constraint
Scenarios - Pilot programs to build regional capability
6Planned Pilots
- 2009 Residential Direct Load Control
- 2009 Open ADR for large commercial
- 2010 Dynamic Pricing Pilot
- 2010 Industrial Pilot
- Considering Irrigation and Wind Integration Pilots
7Open-Auto Demand Response Technology Demonstration
- Partnership with Lawrence Berkley National Labs
and Seattle City Light - First test of Open-ADR for winter peaks
- Open-ADR technology interfaces with the
buildings Energy Management System to enter a
custom, pre-programmed shed when notified - Tested five commercial sites with four events per
site, including one Day-Of event - Buildings shed 8-19 of total load for morning
7-10am peak, with little to no rebound
8Open ADR Example Event Seattle Municipal Tower
9Open-ADR Building Performance
Note Target T0637 data not downloaded from
meter in time for presentation. Results expected
to be similar to Target T1264.
10Residential DLC Pilot
- Project Overview
- Work with 3-4 Utilities
- Leverage investments in Automated Meter Reading
(AMI) systems - Control both hot water heaters and thermostats.
- Address both summer and winter peaks
- Utilize temperature setback instead of duty
cycling - 100-300 homes in first year 700-2,500 homes in
second year - Project Goals
- Develop strategies for BPA and utilities to work
collaboratively to achieve demand response in the
Northwest. - Test integrating demand response technologies
with AMI systems in the residential sector
through a DLC program. - Test recruitment strategy, customer education,
and persistence - Test costs and impacts (kW) for each capacity
constraint
11Next Steps
- Expand Residential DLC Pilot
- Continue testing Open-ADR technology
- 2010 Plan launch Dynamic Pricing Pilot
- 2010 Plan launch Large Commercial Industrial
Pilot
12Where are opportunities for Regional
Collaboration?
- Value in sharing ideas and results across
regional utilities - Leverage investments in research and pilots
- Share results, lessons learned
- Forum to bring in experts from other regions